You Need to be a Contractor for Workers’ Compensation Immunity to Apply
November 16, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are a contractor, you are aware of workers’ compensation immunity when it comes to injuries on the site; and, if not, you should be. It is this workers’ compensation immunity (where workers compensation is the exclusive form of liability for an injured employee) which is why a contractor should generally always want to ensure its subcontractors have workers’ compensation insurance. Workers’ compensation immunity would protect a contractor that is being sued by a subcontractor’s employees that are injured on the job. For more information on workers’ compensation immunity, please check out this
article and this
article.
In this regard, Florida Statute s. 440.10(1)(b) provides:
In case a contractor sublets any part or parts of his or her contract work to a subcontractor or subcontractors, all of the employees of such contractor and subcontractor or subcontractors engaged on such contract work shall be deemed to be employed in one and the same business or establishment, and the contractor shall be liable for, and shall secure, the payment of compensation to all such employees, except to employees of a subcontractor who has secured such payment.
(If the subcontractor does not have workers’ compensation insurance, the contractor is deemed the statutory employer and its workers’ compensation insurance would apply. Otherwise, the subcontractor’s workers compensation insurance would apply.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
There's No Such Thing as a Free House
April 01, 2015 —
Megan McArdle – BloombergShould people be able to get a free house by refusing to pay their mortgage?
That's the question Florida has to answer. The housing crisis is over, and the housing market is healing itself, though slowly in some places. But a backlog of foreclosures still remains ... and it has been going on so long that some homes are now past the statute of limitations for collecting debt. Lawyers for the homeowners are arguing that this means they get to keep the house. Lawyers for the banks are, unsurprisingly, arguing that each month they fail to pay the mortgage payment starts the statutory clock anew.
Both arguments create problems if the courts endorse them. If failing to pay really restarted the clock every month, then there wouldn't be a statute of limitations on debt -- creditors could just keep sending you bills forever and dun you right up to the edge of your grave. There's a very good reason that we have statutes of limitations on most crimes and most debts: The law recognizes that our interests in justice and contract rights must be balanced against other considerations. People need to be able to plan their lives without decades-old problems coming back to bite them, and also, as cases age, they get harder and harder to prove as witnesses die, evidence gets lost and memories fade.
Read the court decisionRead the full story...Reprinted courtesy of
Megan McArdle, BloombergMs. McArdle may be contacted at
mmcardle3@bloomberg.net
Defining Constructive Acceleration
March 22, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to the definition of “constructive acceleration,” the case of Fraser Const. Co. v. U.S., 384 F.3d 1354 (Fed.Cir. 2004) is a cited case and contains an instructive definition, quoted below, for proving a constructive acceleration claim.
In a nutshell, a constructive acceleration claim is when the contractor incurs added costs for trying to complete the contract on time when it should be provided extensions of time to perform based on excusable delay (i.e., delay not caused by the contractor). These added costs could be bringing in additional supervision to manage the work, adding manpower to perform the work, working overtime, working weekends, adding more shift work, stacking trades, etc. However, just because a contractor claims they have been constructively accelerated does not make it so. The contractor has to actually ask for an extension of time based on an excusable delay and the owner either denied the extension or unreasonably sat on the request for an extension of time; thus, the contractor incurred significant costs to accelerate in order to finish the project on time because it was deprived of a requested time extension for excusable delay.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Does a Landlord’s Violation of the Arizona Residential Landlord-Tenant Act Constitute Negligence Per Se?
September 21, 2020 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogIn a recent Arizona Court of Appeals case, Ibarra v. Gastelum, 2020 WL 4218020 (7/23/20), the Court of Appeals addressed the question whether – in a tenant’s personal injury claim against the landlord – a landlord’s violation of the Arizona Landlord-Tenant Act constituted negligence per se. The tenant alleged he was injured by stubbing his toe on a crack in the floor. The tenant alleged that he had made repeated demands that the landlord repair the crack. The statute required the landlord to make all repairs and do whatever is necessary to put and keep the premises in a fit and habitable condition. The tenant argued that a violation of the statute constituted negligence per se, meaning that the violation of the statute satisfied (as a matter of law) the first two elements of a negligence claim – duty and breach of duty. The tenant requested a negligence per se jury instruction. The trial court declined that request and refused to give the requested instruction. The tenant lost the jury trial and appealed.
Reprinted courtesy of
Kevin J. Parker, Snell & Wilmer
Mr. Parker may be contacted at kparker@swlaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Drastic Rebuild Resurrects Graves' Landmark Portland Building
September 14, 2020 —
Nadine M. Post - Engineering News-RecordFifteen minutes into a 105-minute job interview for the $195-million overhaul of the long-troubled Portland Public Service Building in Oregon’s largest city, owner’s rep Mike Day threw a curve ball to the unwitting design-build team of Howard S. Wright Construction Co. and architect DLR Group. Already hard at work solving Day’s first faux crisis scenario—a budget buster that threatened the viability of the makeover of the notoriously dysfunctional landmark—they had to regroup.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Summary Judgment in Construction Defect Case Cannot Be Overturned While Facts Are Still in Contention in Related Cases
September 09, 2011 —
CDJ STAFFThe Alabama Court of Civil Appeals has dismissed an appeal of a summary judgment in the case Bella Investments, Inc. v. Multi Family Services, Inc. MFS was hired by Bella to be the general contractor for a hotel in Gardendale, Alabama. MFS hired various subcontractors, including the architect for the project. After completion of the hotel in April, 2006, Bella made requests for MFS to repair cracked floor tiles.
In August, 2008, Bella sued MFS, the architect, and various fictitiously named defendants. Subsequently, Bella amended its complaint, naming some of the fictitiously named defendants.
MFS in turn claimed that Bella’s claims were void under the statute of limitations and that Bella was in beach of contact by failing to pay MFS the full amount owed. MFS moved for summary judgment under the statute of limitations, which was granted by the court.
Bella requested that the court “alter, amend, or vacate its summary judgment order.” When this was denied, Bella appealed to the Alabama Supreme Court, which transferred the appeal to the Court of Civil Appeals. The Court of Appeals refused to vacate the summary judgment as claims that form part of the case against MFS are also part of Bella’s claims against the other defendants. For this reason, the court upheld the summary judgment.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Coverage for Construction Defects Barred by Business Risk Exclusions
September 01, 2011 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the court determined there was an occurrence, coverage was excluded by the business risk exclusions. See Cont’l W. Ins. Co. v. Shay Constr. Co., 2011 U.S. Dist. LEXIS 82839 (D. Colo. July 28, 2011).
White was the general contractor on the project. White had three subcontracts with Shay to provide framing, siding, and related work on the project. Shay was insured under a CGL policy issued by Continental Western.
Two of Shay’s subcontractors furnished materials, labor and equipment to Shay. These subcontractors filed suit in state court alleging they had not been compensated for the work and materials. White and Shay were named as defendants. White cross claimed against Shay, alleging Shay had breached its obligations under the subcontracts. Several allegations sounded in contract. Other allegations, however, contended Shay had performed defective work and had damaged the work of other trades in correcting deficiencies in its own performance.
Shay sought coverage under Continental Western’s policy. Continental Western filed suit for a declaratory judgment and moved for summary judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Meet the Hipster Real Estate Developers Building for Millennials
October 02, 2015 —
Ben Steverman – BloombergJohn Chaffetz is showing off an apartment building that his development firm, Timberlane Partners, just bought for $7.2 million. He admits it doesn’t look so hot. “This has been treated like a prison camp,” he says of the 32-unit building in Los Angeles’s Echo Park neighborhood. Steel bars stick out of a cinder-block fence, threatening to impale someone. The front door is an ugly metal gate.
But an organic supermarket opened around the corner in November, and a Blue Bottle Coffee just arrived down the block. There’s a farmers market nearby each Friday, and five minutes up Sunset Boulevard is the Silver Lake neighborhood, a nest of hipster cafes and places to buy rare cheese and handmade clothes. Timberlane plans to tear down the building’s security fencing, put terracotta back on the roof, and repair windows that date to its pre-1930 construction. “The goal,” Chaffetz says, “is for this to look like a Moroccan boutique hotel.”
Read the court decisionRead the full story...Reprinted courtesy of
Ben Steverman, Bloomberg