Broker Not Negligent When Insured Rejects Additional Coverage
January 31, 2018 —
Tred R. Eyerly – Insurance Law HawaiiThe broker was not negligent when it proposed additional coverage that was rejected by the insured. Cromer v. Rosenzweig Ins. Agency Inc., 2017 N.Y. App Div. LEXIS 8969 (N.Y. App. Div. Dec. 21, 2017).
Plaintiff was injured while employed as a painter at property owned by Allen Skriloff. Coverage was denied because injuries to employees, contractors and employees of contractors were excluded. Plaintiff sued Skriloff and obtained a jury verdict of $6.1 million. Skirloff assigned to plaintiff all rights and claims held against the insurer and insurance brokers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred Eyerly, Insurance Law Hawaii
Massachusetts Judge Holds That Insurer Breached Its Duty To Defend Lawsuit After Chemical Spill
October 16, 2018 —
Lawrence J. Bracken, II & Alexander D. Russo - Hunton Insurance Recovery BlogA District Court Judge for the District of Massachusetts recently ruled that Ace Property and Casualty Insurance Co. breached its duty to defend its insured in a lawsuit brought by Plaistow Project, LLC, after a family owned laundromat leaked chemicals onto Plaistow Project’s property. Plaistow Project, LLC v. ACE Prop. & Cas. Ins. Co., No. 16-CV-11385-IT, 2018 WL 4357480, (D. Mass. Sept. 13, 2018). Plaistow Project sued State Line Laundry Services in state court, and ACE denied coverage under the pollution exclusion in State Line Laundry’s insurance policy. Plaistow Project then settled with State Line Laundry. Under the settlement terms, Plaistow Project was assigned State Line Laundry’s rights against ACE.
In the subsequent coverage litigation, Plaistow Project alleged that ACE had breached its duty to defend State Line Laundry under its insurance policy. ACE argued that (1) the burden was on the policyholder to demonstrate that the policy’s “sudden and accidental” exception applied to the policy’s pollution exclusion; and (2) the policyholder could not show the “sudden and accidental” exception applied based on the complaint.
Reprinted courtesy of
Lawrence J. Bracken, II, Hunton Andrews Kurth and
Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken, may be contacted at lbracken@HuntonAK.com
Mr. Russo may be contacted at arusso@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Mechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
January 04, 2021 —
William L. Porter - Porter Law GroupMechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
California law entitles unpaid contractors, subcontractors, and material suppliers to record a mechanics lien on property where they performed work or supplied materials. The mechanics lien attaches to the real property as a legal interest and secures the right to payment for the work performed and materials supplied. If payment is not forthcoming the mechanics lien allows the property where the work was performed and materials supplied to be sold under court order to satisfy the debt. It is a powerful remedy against owners and their agents who do not pay for work performed and materials supplied to improve the owner’s property.
A Mechanics Lien Release Bond Frees Property from a Mechanics Lien
Owners typically do not wish to have their property sold out from under them. Fortunately for owners, there is a method by which a mechanics lien can be substituted for another interest and sale of the property thereby avoided. This method is through the use of a mechanics lien release bond. California Civil Code §8424 allows a property owner or contractor effected by a mechanics lien to record a mechanics lien release bond equal to 125 percent of the lien amount with the County Recorder where the mechanics lien has been recorded. The effect of this is to substitute the mechanics lien release bond for the mechanics lien itself, thereby relieving the property from the possibility of that property being sold to satisfy the debt. Instead, any payment made will come from the release bond.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Ninth Circuit Holds that 1993 Budget Appropriations Language Does Not Compel the Corps of Engineers to use 1987 Wetlands Guidance Indefinitely
October 09, 2018 —
Anthony B. Cavender - Gravel2GavelOn September 21, 2018, the U.S. Court of Appeals for the Ninth Circuit decided the case of Tin Cup, LLC v. U.S. Army Corps of Engineers. A divided panel of the Court of Appeals (although all members concurred in the result) held that legislative language in a 1993 appropriations act does not require the U.S. Army Corps of Engineers (Corps) to continue to use its 1987 Clean Water Act (CWA) wetlands guidance beyond 1993. The Ninth Circuit noted that it approaches the interpretation of budget bills somewhat differently.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Steps to Defending against Construction Defect Lawsuits
July 21, 2011 —
CDJ STAFFWriting in Claims Journal, Bryan Rendzio notes that the decline in construction has not been matched by a decline in construction defect lawsuits over condominiums. He reviews the ways in which lawyers representing developers can help protect their clients. He identifies four important considerations in defending developers from claims of construction defects.
He advocates a careful review of the contract. “Under a breach of contract claim, the insured’s duties to the party who brought the claim against the insured flow from the contract. Commonly, construction contracts limit the scope of recoverable damages, such as by waiving consequential damages.’
The next step, according to Rendzio is to check of a settlement agreement is already in place, noting that these are “a familiar occurrence in the construction industry, regardless of any lawsuits having been filed.”
He considers the statute of repose “the single-most decisive weapon an insured possesses in its arsenal during a condo defect lawsuit.” He notes that no lawsuits can be brought for construction defects after the end specified by the statute of repose, and if a lawsuit is brought beforehand, no additional parties can be named once the statute has taken effect.
Finally, he warns adjusters to be suspicious when a condo association requests contractual indemnification. He notes that the pitfall in this is that developers and the subsequent condominium association often have similar names, given the theoretical example of a condo project built by “Fake Lakes LLC” and later run by the “Fake Lakes Condominium Association.” Writing in regards to Florida law, he notes that condominium associations do not have successor interest in contracts developers made with contractors.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
The Fair Share Act Impacts the Strategic Planning of a Jury Trial
May 10, 2017 —
Andrew Ralston, Jr. - White and Williams LLPComplex questions surrounding the application of the Fair Share Act, which modified Pennsylvania’s common law “joint and several” liability law, are being taken up by courts in the Commonwealth with increasing frequency. Given the practical consequences of the differences in application between the Act and “joint and several” liability, additional litigation over the application of the Fair Share Act to real world factual situations will undoubtedly arise.
Recent Caselaw
Currently, in Roverano v. PECO Energy, the Superior Court of Pennsylvania is considering the question of whether, under the Fair Share Act, the jury, or else the trial judge, is responsible for the task of apportioning liability to multiple defendants in a strict liability case. In Roverano – an asbestos case -- a jury awarded the plaintiff $6.3 million. On the verdict sheet were eight joint tortfeasor co-defendants. The judge did not allow the jury to apportion liability to each defendant and, as a result, no guidance was provided by the jury about how much each defendant was to contribute to the award. Instead, the judge merely divided the jury’s award by eight (the number of defendants in the case) and apportioned to each defendant one-eighth of the verdict amount.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew Ralston, Jr., White and Williams LLPMr. Ralston may be contacted at
ralstona@whiteandwilliams.com
Court Concludes That COVID-19 Losses Can Qualify as “Direct Physical Loss”
September 28, 2020 —
Lorelie S. Masters & Jorge R. Aviles - Hunton Andrews KurthIn a victory for policyholders, a federal district court found that COVID-19 can cause physical loss under business-interruption policies. In Studio 417, Inc., et al. v. The Cincinnati Insurance Co., No. 20-cv-03127-SRB (W.D. Mo. Aug. 12, 2020), the court rejected the argument often advanced by insurers that “all-risks” property insurance policies require a physical, structural alteration to trigger coverage. This decision shows that, with correct application of policy-interpretation principles and strategic use of pleading and evidence, policyholders can defeat the insurance industry’s “party line” arguments that business-interruption insurance somehow cannot apply to pay for the unprecedented losses businesses are experiencing from COVID-19, public-safety orders, loss of use of business assets, and other governmental edicts.
The policyholders in Studio 417 operate hair salons and restaurants asserting claims for business interruption. In suing to enforce their coverage, the policyholders allege that, over the last several months, it is likely that customers, employees, and/or other visitors to the insured properties were infected with COVID-19 and thereby infected the insured properties with the virus. Their complaint asserts that the presence of COVID-19 “renders physical property in their vicinity unsafe and unusable.” Unlike some other complaints seeking to enforce such coverage, it also alleges that the presence of COVID-19 and government “Closure Orders” “caused a direct physical loss or direct physical damage” to their premises “by denying use of and damaging the covered property, and by causing a necessary suspension of operations during a period of restoration.”
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Jorge R. Aviles, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Aviles may be contacted at javiles@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
General Contractors Must Plan to Limit Liability for Subcontractor Injury
May 18, 2011 —
Douglas Reiser in the Builders Counsel BlogIt takes more than a hard hat, but safety checks, a good policy and a smart contract might save you some problems.If you are a general contractor, you will want to pay close attention to this article. A new Washington appellate decision showcases a general contractor’s liability to subcontractors who are injured on the job, when security barriers fail. But can a general limit this liability? Will its contract help?
In Wrought Corporation, Inc., Appellant V. Mario Interiano (quick note: this opinion is unpublished, but we are here to talk about an issue that was not determined on appeal – WISHA compliance), a subcontractor was injured when a security barrier failed and he fell into an elevator shaft.
A jury awarded a $1.56 million verdict against the general contractor, and the court of appeals affirmed on the basis that the general contractor has a non-delegable duty to ensure compliance with the Washington Industrial Safety and Health Act of 1973, codified under RCW 49.17 (WISHA).
Read the full story… Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of