“I Didn’t Sign That!” – Applicability of Waivers of Subrogation to Non-Signatory Third Parties
September 30, 2019 —
Rahul Gogineni - The Subrogation StrategistIn Gables Construction v. Red Coats, 2019 Md. App. LEXIS 419, Maryland’s Court of Special Appeals considered whether a contractual waiver of subrogation in the prime contract for a construction project barred a third party – a fire watch vendor hired to guard the worksite – from pursuing a contribution claim against the general contractor. The court concluded that the general contractor could not rely on the waiver of subrogation clause to defeat the contribution claim of the vendor, who was not a party to the prime contract. As noted by the court, holding that a waiver of subrogation clause bars the contribution claims of an entity that was not a party to the contract would violate the intent of the Maryland Uniform Contribution Among Tortfeasors Act (UCATA).
When dealing with claims involving construction projects, there may exist multiple contracts between various parties that contain waivers of subrogation. The enforceability of such waivers can be limited by several factors, including the jurisdiction of the loss, the language of the waiver and the parties to the contract.
In Gables Construction, Upper Rock, Inc. (Upper Rock), the owner, contracted with a general contractor, Gables Construction (GCI) (hereinafter referred to as the “prime contract”), to construct an apartment complex. After someone stole a bobcat tractor from the jobsite, Gables Residential Services Incorporated (GRSI), GCI’s parent company, signed a vendor services agreement (VSA) with Red Coats to provide a fire watch and other security services for the project.
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Quick Note: Mitigation of Damages in Contract Cases
October 02, 2018 —
David Adelstein - Florida Construction Legal UpdatesIn an earlier article, I discussed an owner’s measure of damages when a contractor breaches the construction contract. This article discussed a case where the contractor elected to walk off a residential renovation job due to a payment dispute when he demanded more money and the owners did not bite. This case also discussed the commonly asserted defense known as mitigation of damages, i.e., the other party failed to properly mitigate their own damages.
In the breach of contract setting, mitigation of damages refers to those damages the other side could have reasonably avoided had he undertaken certain (reasonable) measures. This is known as the doctrine of avoidable consequences.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Difficult Task for Court to Analyze Delay and Disorder on Construction Project
August 23, 2021 —
David Adelstein - Florida Construction Legal UpdatesOne of my favorites quotes from a case, and I am sure others in the construction industry feel the same way or can relate, is from the District of Columbia Court of Appeals in Blake Construction Co., Inc. v. C.J. Coakley Co., Inc., 431 A.2d 569, 575 (D.C. 1981):
We note parenthetically and at the outset that, except in the middle of a battlefield, nowhere must men coordinate the movement of other men and all materials in the midst of such chaos and with such limited certainty of present facts and future occurrences as in a huge construction project such as the building of this 100 million dollar hospital. Even the most painstaking planning frequently turns out to be mere conjecture and accommodation to changes must necessarily be of the rough, quick and ad hoc sort, analogous to ever-changing commands on the battlefield. Further, it is a difficult task for a court to be able to examine testimony and evidence in the quiet of a courtroom several years later concerning such confusion and then extract from them a determination of precisely when the disorder and constant readjustment, which is to be expected by any subcontractor on a job site, become so extreme, so debilitating and so unreasonable as to constitute a breach of contract between a contractor and a subcontractor.
Do you agree with this sentiment? The reality is that retrospectively analyzing delay on a complicated construction project with numerous moving parts on a day-by-day, hour-by-hour, basis is no easy feat. It is not easy for the parties and certainly not easy for courts to unravel. With every party claiming delay based on a retrospective analysis there will be another party with either a different delay analysis or providing credible cross examination as to flaws with the delay analysis. The same bodes true with loss of productivity / inefficiency claims and the particular case-specific facts are important, preferably with evidence such as photos, videos, notifications, daily reports, manpower reports, etc., supporting the facts. But the facts are complicated, and the delay analysis is complicated, and it is a difficult task for a trier of fact to unravel these facts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Gillotti v. Stewart (2017) 2017 WL 1488711 Rejects Liberty Mutual, Holding Once Again that the Right to Repair Act is the Exclusive Remedy for Construction Defect Claims
June 05, 2017 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. - Chapman Glucksman Dean Roeb & Barger BulletinBackground
In Gillotti v. Stewart (April 26, 2017) 2017 WL 1488711, which was ordered to be published on May 18, 2017, the defendant grading subcontractor added soil over tree roots to level the driveway on the plaintiff homeowner’s sloped lot. The homeowner sued the grading subcontractor under the California Right to Repair Act (Civil Code §§ 895, et seq.) claiming that the subcontractor’s work damaged the trees.
After the jury found the subcontractor was not negligent, the trial court entered judgment in favor of the subcontractor. The homeowner appealed, arguing that the trial court improperly construed the Right to Repair Act as barring a common law negligence theory against the subcontractor and erred in failing to follow Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98. The Third District Court of Appeal disagreed and affirmed the trial court’s judgment in favor of the subcontractor.
Impact
This is the second time the Third District Court of Appeal has held that Liberty Mutual (discussed below) was wrongly decided and held that the Right to Repair Act is the exclusive remedy for construction defect claims. The decision follows its holding in Elliott Homes, Inc. v. Superior Court (Hicks) (2016) 6 Cal.App.5th 333, in which the Court of Appeal held that the Right to Repair Act’s pre-litigation procedures apply when homeowners plead construction defect claims based on common law causes of action, as opposed to violations of the building standards set forth in the Right to Repair Act. Elliott is currently on hold at the California Supreme Court, pending the decision in McMillin Albany, LLC v. Superior Court (2015) 239 Cal.App.4th 1132, wherein Liberty Mutual was rejected for the first time by the Fifth District. CGDRB continues to follow developments regarding the much anticipated McMillin decision closely, as well as all related matters.
Discussion
The Right to Repair Act makes contractors and subcontractors not involved in home sales liable for construction defects only if the homeowner proves they negligently cause the violation in whole or part (Civil Code §§ 911(b), 936). As such, the trial court in Gillotti instructed the jury on negligence with respect to the grading subcontractor. The jury found that while the construction did violate some of the Right to Repair’s building standards alleged by the homeowner, the subcontractor was not negligent in anyway. After the jury verdict, the trial court found in favor of the grading subcontractor.
The homeowner moved for a judgment notwithstanding the verdict or a new trial on the grounds that the trial court improperly barred a common law negligence theory against the grading subcontractor. The trial court denied the motions on the grounds that “[t]he Right to Repair Act specifically provides that no other causes of action are allowed. See Civil Code § 943.” The trial court specifically noted that its decision conflicted with Liberty Mutual, in which the Fourth District Court of Appeal held that the Right to Repair Act does not eliminate common law rights and remedies where actual damage has occurred, stating that Liberty Mutual was wrongly decided and that the Liberty Mutual court was naïve in its assumptions regarding the legislative history of the Right to Repair Act.
In Gillotti, the Third District Court of Appeal stated that the Liberty Mutual court failed to analyze the language of Civil Code § 896, which “clearly and unequivocally expresses the legislative intent that the Act apply to all action seeking recovery of damages arising out of, or related to deficiencies in, residential construction, except as specifically set forth in the Act. The Act does not specifically except actions arising from actual damages. To the contrary, it authorizes recovery of damages, e.g., for ‘the reasonable cost of repairing and rectifying any damages resulting from the failure of the home to meet the standards....’ ([Civil Code] § 944).”
The Court also disagreed with Liberty Mutual’s view that because Civil Code §§ 931 and 943 acknowledge exceptions to the Right to Repair Act’s statutory remedies, the Act does not preclude common law claims for damages due to defects identified in the Act. The Court stated: “Neither list of exceptions, in section 943 or in section 931, includes common law causes of action such as negligence. If the Legislature had intended to make such a wide-ranging exception to the restrictive language of the first sentence of section 943, we would have expected it to do so expressly.”
Additionally, the Court of Appeal rejected the argument that Civil Code § 897 preserves a common law negligence claims for violation of standards not listed in Civil Code § 986. It explained that the section of Civil Code § 897, which provides, “The standards set forth in this chapter are intended to address every function or component of a structure,” expresses the legislative intent that the Right to Repair Act be all-encompassing. Anything inadvertently omitted is actionable under the Act if it causes damage. Any exceptions to the Act are made expressly through Civil Code §§ 931 and 934. The Court concluded in no uncertain terms that the Right to Repair Act precludes common law claims in cases for damages covered by the Act.
The homeowner further argued that she was not precluded from bringing a common law claim because a tree is not a “structure,” and therefore the alleged tree damage did not fall within the realm of the Right to Repair. The Court of Appeal also rejected this argument, holding that while the tree damage itself was not expressly covered, the act of adding soil to make the driveway level (which caused the damage) implicated the standards covered by the Right to Repair Act. The Court explained that since under the Act a “structure” includes “improvement located upon a lot or within a common area” (Civil Code § 895(a)), as the driveway was an improvement upon the lot, the claim was within the purview of the Right to Repair Act. As the soil, a component of the driveway, caused damage (to the trees), it was actionable under the Act.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New American Home Construction Nears Completion Despite Obstacles
January 29, 2014 —
Beverley BevenFlorez-CDJ STAFFConstruction of the New American Home in Las Vegas, Nevada, to be completed for the 2014 International Builders’ Show, has faced enormous challenges, according to Jennifer Goodman writing for Big Builder. Josh Anderson, owner of Element Building Co., told Goodman “he couldn’t have imagined what lay ahead when he signed on in fall 2012 to the project, which is co-sponsored by BUILDER and the NAHB.”
Challenges began during the “design phase” when Anderson “was troubled by the sitting of the house on its lot in the tony Sky Terrace subdivision.” Furthermore, he “balked at the floor plan, which encompassed a traditional design aesthetic and opulent touches.” The project’s architect, Barry Berkus, passed away in late 2012, and his son, Jeffrey Berkus, took over for him.
After the plans were “complete and approved by the city,” a labor shortage in Las Vegas made it “particularly difficult to find skilled framers.” The shortage also increased labor costs. Anderson also contended with weather anomalies: “Over the summer, the area set a record for the most consecutive wet days in 30 years. Winds blew sawdust and rain into the open structure, ruining 350 sheets of drywall and slowing down construction,” according to Big Builder.
The “mammoth project” is close to completion. Anderson told Big Builder, “I’ve always been a sucker for a challenge.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Dispute Governed by Contract Disputes Act not yet Suited to being a "Suit"
June 25, 2019 —
William S. Bennett - Saxe Doernberger & Vita, P.C.The Southern District of California recently held that a series of demands for a general contractor to investigate and repair several construction defects at a U.S. Army facility did not constitute a “suit” within the meaning of the general contractor’s commercial general liability (“CGL”) policy.
In Harper Construction Co., Inc. v. Nat’l Union Fire Ins. Co. of Pittsburgh, Pa., the U.S. Government hired Harper Construction Company (“Harper”) to construct a U.S. Army training facility for the Patriot Missile System in Fort Sill, Oklahoma. No. 18-cv-00471-BAS-NLS (S.D. Cal. Mar. 28, 2019). During the project, Harper hired Harper Mechanical Contractors (“Harper Mechanical”), an independent company, as a subcontractor “to perform demolition, grading, and other work at the Project.”
After Harper completed the project, the government informed Harper of property damage at the project, “including, but not limited to, gypsum wallboard cracks and binding doors.” Harper attempted to repair the issues, but the problems continued. The issues were apparently the result of Harper Mechanical’s grading work. Subsequently, the government sent two letters requesting an investigation and asking Harper to “propose a plan to correct the issues.” As Harper undertook an investigation spanning multiple years, the government became increasingly frustrated with the delays. The government threatened to initiate “formal administrative recourse” and to demolish the project, forcing Harper to re-build from the ground up. It also sent Harper another letter requesting Harper submit a formal proposal to correct the issues.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Climate-Proofing Your Home: Upgrades to Weather a Drought
January 03, 2022 —
Todd Woody - BloombergClimate-driven drought is making the once unthinkable foreseeable. Amid water shortages, your faucets could run dry, as has been a possibility in Marin County, California. Violate mandatory water restrictions and you might face steep fines or even a cutoff of service.
With the western United States in the grip of an extreme drought, rivers and reservoirs are at record lows and some water utility districts in California have asked residents to curtail consumption by as much as 40%. A 2019 study found regions across the nation could face water shortages in the coming decades in part due to climate change.
That puts a premium on making homes more resilient to drought by maximizing efficiency and minimizing waste through technologies that monitor consumption and recycle and capture water that would otherwise be lost.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Woody, Bloomberg
Infrastructure Money Comes With Labor Law Strings Attached
July 25, 2022 —
Cheryl Behymer, Patrick M. Dalin & Collin Cook - Construction ExecutiveThe federal government has committed to spending $1 trillion under the Infrastructure Investment and Jobs Act on nationwide construction, alteration and repair projects. Billions of dollars have already been deployed on projects to improve highways, bridges, airports, electrical infrastructure and drinking water distribution, and the government is poised to spend the remaining funds on a massive infrastructure build-out over the next five years. While federal government contracts may provide a lucrative and reliable stream of revenue for construction companies, contractors must be prepared to comply with special requirements, particularly under the labor and employment laws enforced by the U.S. Department of Labor (USDOL).
1. The Davis Bacon Act Requires Payment of Prevailing Wages and Fringe Benefits
The Davis Bacon Act (DBA) applies to most federally funded and federally assisted projects for construction, alteration or repair work. This law requires all contractors and subcontractors on a covered project to pay all “laborers or mechanics” the wages and fringe benefits that “prevail” in the locality where the work is being performed. The USDOL determines what the prevailing wages and fringe benefits are for each trade and publishes them in wage determinations that should be issued to all contractors on the project.
Reprinted courtesy of
Cheryl Behymer, Patrick M. Dalin & Collin Cook, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of