Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Georgia Legislature Passes Additional Procurement Rules
May 30, 2018 —
David R. Cook Jr. - Autry, Hall & Cook, LLPOn May 3, 2018, Governor Nathan Deal signed HB 899 into law, officially making it Act 389. Act 389 modifies O.C.G.A. § 13-10-4 and § 36-91-23 relating to public works bidding and contracts of state and local governments, respectively. Both sections are modified in the same bill because they contain the same language. The bill prohibits the disqualification of bidders based upon lack of previous experience with the project’s desired construction delivery method.
Before the modifications, the code protected a contractor from disqualification only for lack of previous experience on a job of comparable size. After the modification, the law expands to prohibit disqualification based on lack of previous experience with comparable job size and lack of previous experience with the construction delivery method.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
CDJ’s #9 Topic of the Year: Nevada Supreme Court Denies Class Action Status in Construction Defect Case
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Sean Whaley of the Las Vegas Review-Journal, “The Nevada Supreme Court has rejected a request for class action status for claims of damaged stucco from faulty construction by Del Webb Communities involving nearly 1,000 Sun City Summerlin residents.” However, “the court upheld the award of damages to 71 homeowners following a jury trial in Clark County District Court in 2008.” Whaley reported that this construction defect case was touted as the largest in Nevada history.
Read the court decisionRead the full story...Reprinted courtesy of
Novation Agreements Under Federal Contracts
November 29, 2021 —
Hal Perloff - Construction ExecutiveA unique aspect of doing business with the federal government is the built-in limits on a contractor’s right to assign the contract or the right to payment under the contract to third parties. The Anti-Assignment Act (41 U.S.C. § 6305) prohibits the transfer of a government contract or interest in a government contract to a third party. An assignment of a contract in violation of this law voids the contract except for the government’s right to pursue a breach of contract remedies.
What’s a contractor to do when it is acquired/merged with another firm, is restructured or goes through a variety of other types of corporate transaction? The Federal Acquisition Regulations recognize that firms involved in government contracts get bought and sold from time to time and includes procedures for the novation of contracts in certain situations to avoid a potential violation of the Anti-Assignment Act.
What Is a Novation?
A novation is a three-party agreement between the United States, the original contractor and the new contractor offering to assume the government contract. The purpose the novation is to allow the government to recognize a new contractor as the successor-in-interest to a government contract and avoid a violation of the Anti-Assignment Act.
Reprinted courtesy of
Hal Perloff, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Perloff may be contacted at
hal.perloff@huschblackwell.com
Just Because You Allege There Was an Oral Contract Doesn’t Mean You’re Off the Hook for Attorneys’ Fees if you Lose
March 28, 2022 —
Garret Murai - California Construction Law BlogThere’s certain things in life you shouldn’t mix. Like drinking and driving. Bleach and ammonia. Triple dog dares and frozen poles. And angry lawyers and litigation.
In Spahn v. Richards, Case No. A159495 (November 30, 2021), angry lawyer Jeffrey Spahn sued general contractor Dan Richards claiming that Richards orally agreed to build Spahn’s million dollar plus house for $515,000. Not only did Spahn not recover anything from Richards, he ended up owing Richards $239,171 in attorney’s fees and costs, after he denied a request for admission asking that he admit that there was no oral contract.
The Spahn Case
In 2017, Spahn filed suit against Richards for breach of oral contract, breach of implied covenant of good faith and fair dealing, and promissory estoppel. According to Spahn, he met Richards in June 2015 and the two reached an agreement whereby Richards agreed to demolish Spahn’s house for $12,500 and build a new one for $515,000. Further according to Spahn, Richards agreed to this “fixed price” “oral contract” in June 2015, and then, on July 1, 2015, Richards “confirmed and agreed that he would perform the construction project” for $515,000 and would complete construction by May 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Ex-Turner Exec Gets 46 Months for Bloomberg Construction Bribes
July 11, 2021 —
Eydie Cubarrubia - Engineering News-RecordA third New York City-based construction executive was sentenced to federal prison June 15, receiving 46 months, as part of the $15-million bribery scheme involving interiors work for financial giant Bloomberg LLP at its Manhattan headquarters.
Reprinted courtesy of
Eydie Cubarrubia, Engineering News-Record
Ms. Cubarrubia may be contacted at cubarrubiae@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Banks Rejected by U.S. High Court on Mortgage Securities Suits
January 12, 2015 —
Greg Stohr – BloombergThe U.S. Supreme Court dealt a blow to Royal Bank of Scotland Group Plc and Nomura Holdings Inc. (8604), refusing to derail federal government lawsuits that seek billions of dollars over the sale of risky mortgage-backed securities.
The justices today turned away an appeal by four banks, including units of RBS and Nomura, in a case stemming from the collapse of two credit unions that owned more than $1.7 billion in those securities.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Stohr, BloombergMr. Stohr may be contacted at
gstohr@bloomberg.net
Sometimes it Depends on “Whose” Hand is in the Cookie Jar
January 21, 2015 —
Roger Hughes – California Construction Law BlogIn a lengthy and somewhat detailed decision, the California Court of Appeal for First District, in Pittsburg Unified School District v. S.J. Amoroso Construction Company, Inc., Case No. A138825 (December 22, 2014), held that a public entity could unilaterally withdraw retention funds during a pending legal dispute without the court first finding that the contractor had defaulted on the public works project.
Background
In 2008, general contractor S.J. Amoroso Construction Company, Inc. (“S.J. Amoroso”) entered into a construction contract with the Pittsburg Unified School District (“District”) for the reconstruction and modernization of a high school in Pittsburg, California.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at