Deference Given To Procuring Public Agency Regarding Material Deviation
April 10, 2019 —
David Adelstein - Florida Construction Legal UpdatesDeference will be given to a procuring public agency in a bid protest, particularly when the issue involves whether a bid is non-responsive and constitutes a material deviation from the solicitation. You do not believe me? Perhaps you will after this holding in Biscayne Marine Partners, LLC v. City of Miami, Florida, 44 Fla.L.Weekly D467a (Fla. 3d DCA 2019):
Consequently, no principle of law is clearly established…as to any obligation of the trial court (and, by analogy, an administrative hearing officer) [in a bid protest] to decide or to defer [whether a bid constitutes a material deviation from the solicitation]. If anything, the existing and clearly established principle of law inclines toward judicial deference in public agency competitive bidding disputes when the agency has exercised it discretion absent illegality, fraud, oppression or misconduct.
I do not know about you, but that last underlined sentence is pretty strong language regarding judicial deference!
In this case, Miami (the procuring public agency) issued a Request for Proposals (RFP) for the redevelopment and lease of waterfront property, for the operation of a marina, boatyard, restaurant, wet slips, and a dry storage facility on the property. Miami issued five addenda to the RFP. There were three bidders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Part II: Key Provisions of School Facility Construction & Design Contracts
July 21, 2018 —
David R. Cook - Autry, Hall & Cook, LLPIn
Part I of this article, published in late April, we discussed the performance risk and time risk involved with construction and design contracts, and in Part II, we will cover cost risk and political risk.
Cost Risk
School budgets are limited for many reasons, and the construction budget is no exception. As a result, contracts should guard against unwarranted cost increases and claims. In the absence of a written change order signed by the appropriate officer, the contract should absolutely prohibit additional compensation for changes in the work. It should forbid claims for all events except those within the school authority’s sole control. Even for permitted claims, the contractor must provide written notice so that the authority might alleviate the problem and control its costs. To encourage the contractor to limit costs and claims, the contract could include a shared-savings clause, which grants an incentive payment for completion within the budget.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Ambiguity Kills in Construction Contracting
May 27, 2019 —
Christopher G. Hill - Construction Law MusingsWell, I’m back and hope to have a more consistent publishing schedule moving forward. I appreciate the continued readership through what has been a busy time for my solo construction practice over the last couple of months. Now, back to our program. . .
Here at Construction Law Musings, I have often beaten the drum of a solid contract that leaves as little as possible to chance or the dreaded “grey areas” where we construction lawyers like to make money. An example of the issues that can arise from ambiguity can be found in a case from 2017 in the Western District of Virginia, W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP et al
In this case, English, a general contractor, entered into a contract for Quality Assurance (QA) functions with RK&K, the defendant, on a contract English entered into with the Virginia Department of Transportation (VDOT). Needless to say, because this would not be a post at Musings otherwise, there were issues with the QA performed by RK&K leading to additional costs for English to correct certain work that did not comply with the contract documents between VDOT and English. English sued for breach of contract based upon a term sheet, signed by the parties, from RK&K that required RK&K to indemnify English for claims by VDOT that related to RK&K’s work (the English Term Sheet). RK&K moved to dismiss the complaint based upon a different term sheet, also signed by the parties, which stated that RK&K could not be held responsible for English’s failure to perform pursuant to the contract documents (the RK&K Term Sheet).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Could This Gel Help Tame the California Fires?
November 28, 2018 —
Gordy Megroz - BloombergIn 2009, Jeff Denholm was making a living as an adventure athlete, competing in stand-up paddleboard races and riding giant waves at Mavericks, the famous surf break near his home in Santa Cruz, Calif. Denholm was sponsored by Patagonia Inc., but to generate extra cash—“Adventure athletes don’t make a ton of money,” he says—he had a side gig leasing a fire truck to state and county crews that had run out of equipment battling wildfires.
One firefighting tool that Denholm kept onboard was retardant, which helps tamp down existing fires and can prevent them; he used a type known as a foam suppressant. Last year the U.S. Forest Service spent about $72 million on retardants, but in researching them, Denholm discovered some discouraging information.
Read the court decisionRead the full story...Reprinted courtesy of
Gordy Megroz, Bloomberg
EPA Fines Ivory Homes for Storm Water Pollution
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFF“Utah’s largest home builder [Ivory Homes] has agreed to a $250,000 fine and to take several steps…to comply with Clean Water Act requirements to control pollution associated with storm-water runoff from construction sites,” reported The Salt Lake Tribune.
David Broadbent, Ivory Homes’ chief operating officer, stated in an email to The Salt Lake Tribune: “We are proud of our environmental record, particularly our storm-water compliance record. We are the first and the only home builder in Utah to implement a robust, companywide program to safeguard against sediment from entering Utah waters as a result of home-building activities.” Furthermore, Broadbent declared that the “inspections that led to the violations notices” did not yield any evidence that their “home-building practices resulted in any sediment discharge in any amount, let alone harm, to Utah waters.”
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Finds that When it Comes to Intentional Interference Claims, Public Works Projects are Just Different, Special Even
April 20, 2017 —
Garret Murai - California Construction Law BlogEarlier, we reported on a California Court of Appeals decision – Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc. – which held for the first time that a second-place bidder on a public works contract could sue a winning bidder who failed to pay its workers prevailing wages, under the business tort of intentional interference with prospective economic advantage.
Fast forward nearly two years, several amicus briefs, and “one doghouse”* later and the California Supreme Court has . . . reversed.
The Roy Allan Slurry Seal Case
To catch you up, or rather, refresh your recollection . . .
Between 2009 and 2012, American Asphalt South, Inc. was awarded 23 public works contracts totaling more than $14.6 million throughout Los Angeles, Orange, San Bernardino and San Diego counties. Two of the losing bidders on those projects – Roy Allan Slurry Seal, Inc. and Doug Martin Contracting, Inc. – sued American in each of these counties for intentional interference with prospective economic advantage as well as under the Unfair Practices Act (“UPA”) (Bus. & Prof. Code §§ 17000 et seq.) and the Unfair Competition Law (“UCL”) (Bus. & Prof. Code §17200).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Data Is Critical for the Future of Construction
April 19, 2022 —
Raghi Iyengar - Construction ExecutiveAccording to a
recent study, real-time visibility and access to critical data and insights are vital for rapid construction decision-making. Notably, inaccurate and missing data cost the industry almost $2 trillion in 2020. Even more surprising, construction companies often don’t know if they’ve made or lost money until the job is complete or if they’re on schedule until they start falling behind. These findings portray an important reality for the industry: Construction needs to establish and optimize data strategies to ensure it has the visibility control, and transparency needed to improve efficiency and productivity on projects.
Luckily, while historically slow to change, the construction industry has begun to adopt technologies that help firms improve efficiency and productivity on projects. With this technology, contractors can establish and optimize data strategies to ensure they have visibility, control and transparency.
Embracing data is a game changer as the industry continues to expand. In fact, the report from Autodesk and FMI cited above found that the construction companies using data technologies and strategies saw
fewer project delays, less rework and fewer change orders.
Reprinted courtesy of
Raghi Iyengar, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up (10/05/22) – Hurricane Ian, the Inflation Reduction Act, and European Real Estate
October 24, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up features Hurricane Ian’s effect on the construction labor pool, the Inflation Reduction Act’s projected impact on the real estate and construction industry, Europe’s real estate market, and more.
- The Inflation Reduction Act (IRA), designed to reduce the nation’s carbon footprint by jump-starting innovation and adoption of cleaner energy sources, also contains large segments aimed at real estate and construction. (Chava Gourarie, Commercial Observer)
- Damage caused by Hurricane Ian’s massive storm surge, flooding and winds is projected to hike demand for experienced construction workers. (Zachary Phillips, Construction Dive)
- According to the National Multifamily Housing Council’s monthly construction survey released Sept. 29, 2022, almost all developers are experiencing construction delays. (Paul Bergeron, Globest)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team