Specific Performance of an Option Contract to Purchase Real Property is Barred Absent Agreement on All Material Terms
December 20, 2017 —
Richard H. Herold - Real Estate Litigation BlogOn November 14, 2017, the Court of Appeals (Division 1), in Offerman v. Granada, LLC, 2017 WL 5352664, reversed a trial court order directing specific performance of an alleged option to purchase real property, holding that the alleged option was too indefinite to be specifically performed because the parties did not agree to all of the material terms of the option.
Tenant-Purchaser Offerman executed a two-year lease with Landlord-Seller Granada, which granted Offerman “the option to purchase [the] property…for a sales price to be determined at that time by an independent appraiser acceptable to both Tenant and Landlord. (Terms and Conditions to be stipulated by both parties at such time).” (emphasis added). Offerman timely advised Granada he intended to exercise the option, asked Granada to name an appraiser, and, when Granada did not respond, Offerman tendered a $240,000 appraisal to exercise the option. Granada did not retain an appraiser but instead simply demanded $350,000 to close the sale. After a bench trial, the Court determined that Offerman was entitled to specific performance, and, as the parties had not agreed to certain terms, held a second evidentiary hearing to resolve the form of judgment, therein naming a title agency to handle the escrow, setting a closing date, allocating the transaction fees between the parties, and ordering Granada to pay for the property inspection.
Read the court decisionRead the full story...Reprinted courtesy of
Richard H. Herold, Snell & WilmerMr. Herold may be contacted at
rherold@swlaw.com
Senior Housing Surplus Seen as Boomers Spur Building Boom
May 19, 2014 —
Brian Louis – BloombergReal estate developers are betting big on U.S. housing for the elderly, preparing for a surge in demand as the population of senior citizens almost doubles in the next 35 years. They may be building too fast.
A jump in supply is forecast to cut growth in senior-housing net operating income to 1.8 percent in 2015 and 1.4 percent in 2016 from 3.3 percent this year, according to Green Street Advisors Inc. The increase may hurt health-care real estate investment trusts and companies including Brookdale Senior Living Inc. (BKD), which is buying competitor Emeritus Corp. (ESC) for about $1.4 billion to become the biggest owner of senior properties, the research firm said.
“Increased supply is always worrisome in any type of commercial real estate,” said Jim Sullivan, a managing director at Newport Beach, California-based Green Street. “In senior housing, new construction has ramped up considerably over the last two years.”
Read the court decisionRead the full story...Reprinted courtesy of
Brian Louis, BloombergMr. Louis may be contacted at
blouis1@bloomberg.net
Workplace Safety–the Unpreventable Employee Misconduct Defense
October 02, 2015 —
Craig Martin – Construction Contractor AdvisorI just attended an Associated Builders and Contractors meeting during which Lueder Construction discussed a fatality on one of its worksite. OSHA fully investigated the incident and did not issue a single citation. This is a testament to the safety plan and training Lueder had in place well before this incident. One defense to an OSHA citation is unpreventable employee misconduct. However, proving this defense requires substantial planning, well before an incident or investigation.
Unpreventable Employee Misconduct Defense
OSHA requires that an employer do everything reasonably within its power to ensure that its personnel do not violate safety standards. But if an employer lives up to that billing and an employee nonetheless fails to use proper equipment or otherwise ignores firmly established safety measures, it seems unfair to hold the employer liable. To address this dilemma, both the Occupational Safety & Health Review Commission and courts have recognized the availability of the unforeseeable employee misconduct defense.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Insurer's Motion for Summary Judgment in Collapse Case Denied
November 10, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court denied the insurer's motion for summary judgment seeking to establish it did not breach the policy when denying coverage for the collapse of basement walls. Belz v. Peerless Ins. Co., 2016 U.S. Dist. LEXIS 118900 (D. Conn. Sept. 2, 2016).
The Belzes purchased their home in 2001. Prior to the purchase, they were aware of notable cracking in the basement walls. An engineer was hired to inspect the cracking and determined the cracks did not threaten the structural integrity of the home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Musk Says ‘Chicago Express’ Tunnel Project Could Start Work in Months
August 14, 2018 —
Jeff Yoders – Engineering News-RecordTechnology guru Elon Musk beat three other construction proposals on June 14 to win the exclusive right to negotiate a design-build-operate-maintain contract with the City of Chicago to provide a high-speed underground passenger transport system between the downtown Loop area and O’Hare Airport. He proposes a one-way trip of about 12 minutes at 150 mph compared with the current 40-minute average by rail or car.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Yoders, ENRMr. Yoders may be contacted at
yodersj@enr.com
Issue and Claim Preclusion When Forced to Litigate Similar Issues in Different Forums: White River Village, LLP v. Fidelity and Deposit Company of Maryland
October 10, 2013 —
Brady Iandiorio — Higgins, Hopkins, McLain & Roswell, LLC.Often in construction litigation the parties wish to move the case to arbitration. However, there are certain circumstances in which such change of litigation forums should be carefully analyzed. The case of White River Village, LLP v. Fidelity and Deposit Company of Maryland, serves as an example of one of those circumstances.
In March 2013, U.S. District Court Judge Blackburn ruled on a motion for summary judgment filed by Fidelity and Deposit Company of Maryland (“F&D”). The order grants the motion in part and denies it in part. White River Village, LLP (“White River”) was the owner of the project which hired S&S Joint Venture (“S&S”), the contractor, to build two similar developments, directly adjacent to each other. The contracts between Whiter River and S&S for the two projects were so substantially similar that the court referred to them as the S&S Contracts. F&D issued payment and performance bonds guarantying the obligations of S&S under the S&S Contracts.
After S&S defaulted on the construction contracts, F&D, as the surety, undertook to complete performance on the contracts. White River alleged that F&D was liable for construction defects and delays in completing the project, and failed to fulfill its obligations under the performance bonds after it overtook the construction of the projects.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Smart Construction and the Future of the Construction Industry
October 11, 2021 —
Caroline A. Harcourt, James W. McPhillips & Adam J. Weaver - Gravel2Gavel Construction & Real Estate Law Blog“Smart Construction” is a loose term but generally refers to the development and use of processes and applications that improve construction planning and the management of projects (thereby potentially streamlining costs of construction).
The increased deployment of collaboration tools (e.g., Zoom, Microsoft Teams, WebEx) and other cloud-based technology solutions during the COVID-19 pandemic will invariably result in more efficient project management in construction going forward. These type of efficiencies are sorely needed, especially as the industry is trying to recover from supply chain issues, lockdown challenges and social distancing requirements resulting from the pandemic.
However, smart construction goes well beyond those basic business efficiency and collaboration tools. For example, drones are regularly used on construction projects to monitor site conditions, detect problems, and assess conditions safely. Meanwhile, newer technologies such as “programmable” cement, “self-healing” concrete, and autonomous and robotic machinery are increasingly being deployed in construction projects. And yet, these current technology solutions are just the tip of the iceberg as researchers continue to look for new ways machines and technology can be used to solve complex engineering challenges.
Reprinted courtesy of
Caroline A. Harcourt, Pillsbury,
James W. McPhillips, Pillsbury and
Adam J. Weaver, Pillsbury
Ms. Harcourt may be contacted at caroline.harcourt@pillsburylaw.com
Mr. McPhillips may be contacted at james.mcphillips@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Is Privity of Contract with the Owner a Requirement of a Valid Mechanic’s Lien? Not for GC’s
July 05, 2021 —
Christopher G. Hill - Construction Law MusingsAs any reader of this construction law blog knows, mechanic’s liens make up much of the discussion here at Construction Law Musings. A recent case out of Fairfax County, Virginia examined the question of whether contractual privity between the general contractor and owner of the property at issue is necessary. As a reminder, in most situations, for a contract claim to be made, the claimant has to have a direct contract (privity) with the entity it sues. Further, for a subcontractor to have a valid mechanic’s lien it would have to have privity with the general contractor or with the Owner.
The Fairfax case, The Barber of Seville, Inc. v. Bironco, Inc., examined the question of whether contractual privity is necessary between the general contractor and the Owner. In Bironco, the claimant, Bironco, performed certain improvements for a barbershop pursuant to a contract executed by the two owners of the Plaintiff. We wouldn’t have the case here at Musings if Bironco had been paid in full. Bironco then recorded a lien against the leasehold interest of The Barber of Seville, Inc., the entity holding the lease. The Plaintiff filed an action seeking to have the lien declared invalid because Brionco had privity of contract with the individuals that executed the contract, but not directly with the corporate entity.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at