“Good Faith” May Not Be Good Enough: California Supreme Court to Decide When General Contractors Can Withhold Retention
March 22, 2018 —
Erinn Contreras and Joy O. Siu – Construction & Infrastructure Law BlogIt is industry standard in California for owners of a construction project to make monthly payments to a contractor for work it has completed, less a certain percentage that is withheld as a guarantee of future satisfactory performance. This withholding is called a retention. Contractors generally pass these withholdings on to their subcontractors via a retention clause in the subcontract. Under such clause, if a subcontractor fails to complete its work or correct deficiencies in its work, the owner and the general contractor may use the retention to bring the subcontractor’s work into conformance with the requirements of the contract.
When and how retention payments must be released are governed by, among other statutes, Civil Code section 8800
et seq. Specifically, Civil Code section 8814, subdivision (a), states that a direct contractor must pay each subcontractor its share of a retention payment within ten days after the general contractor receives all or part of a retention payment. Failure to make payments in accordance with Section 8814 can subject an owner or a contractor to a (1) two percent penalty per a month on the amount wrongfully withheld, and (2) claim for attorney’s fees for any litigation required to collect the wrongfully withheld retention payments. (Civ. Code, § 8818.)
Reprinted courtesy of
Erinn Contreras, Sheppard, Mullin, Richter & Hampton LLP and
Joy Siu, Sheppard, Mullin, Richter & Hampton LLP
Ms. Contreras may be contacted at econtreras@sheppardmullin.com
Ms. Siu may be contacted at jsiu@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Include Materials Price Escalation Clauses in Construction Clauses
December 26, 2022 —
Robert Alfert Jr. - Construction ExecutiveThe construction sector has been in a bull market for an unprecedented period of time. With the novel impacts from the coronavirus—and all the associated side effects, such as government moratoria, shipping delays and materials availability—we are now in a market of extreme volatility in pricing, inflation and increasing capital finance rates. And yet the construction sector continues to plow forward despite uncertainty, producing critical infrastructure, and much necessary housing, among other projects. The signs are that this trend will continue at least through Q1 of 2023, and likely beyond that, especially when you factor into the equation the many billions of dollars being placed into the market through the Bipartisan Infrastructure Law.
It is not surprising, therefore, that the number one issue in construction contracts in 2022 is how parties handle inflation and materials cost escalations in existing contracts and in the negotiations for new contracts. There is no other issue more heavily negotiated, often disputed and hotly debated in the construction sector today.
Reprinted courtesy of
Robert Alfert Jr., Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Alfert may be contacted at
robert.alfert@nelsonmullins.com
NYC Landlord Accused of Skirting Law With Rent-Free Months Offer
October 15, 2024 —
Natalie Wong - BloombergThe opening of Tower 28, one of the tallest residential towers in New York City outside Manhattan, brought rent-stabilized units to Long Island City roughly seven years ago, adding affordable listings to a neighborhood where soaring prices were increasingly squeezing out many renters.
Now, three tenants at the 58-story building have filed a class-action lawsuit alleging the landlord sought to evade New York City rent regulations in order to raise prices even higher over time.
The lawsuit against the limited liability company tied to 42-12 28th St. in Queens claims that the property owner recorded initial rents with the New York State Division of Housing and Community Renewal that were higher than what the first tenant was actually charged and paid. In doing so, any future rent increases were based off a higher figure, according to the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Natalie Wong, Bloomberg
Hennigh Law Corporation Wins Award Against Viracon, Inc In Defective Gray PIB Case
July 11, 2022 —
Scott Hennigh - Hennigh Law CorporationLOS ANGELES, July 08, 2022 (GLOBE NEWSWIRE) -- Hennigh Law Corporation has announced that, after an over four-year battle in and out of court, a three arbitrator panel issued a 93-page interim award in finding Viracon, Inc., liable for $13,682,840 in direct damages for defrauding the owner of the premier office building in Burbank, California, The Pointe. The matter now enters the second phase, where the arbitration panel will rule on the amount of punitive damages to assess, as well as attorney fees and interest.
Scott Hennigh, trial attorney, states, "The California construction industry is very robust with high standards. The arbitration panel appears to have recognized that California law does not tolerate large out-of-state companies misleading customers. They appear poised to send a message to Viracon about its lack of corporate responsibility."
The premier Class-A office building in Burbank, California, The Pointe, serves high-end tenants in entertainment industries such as Warner Brothers. Constructed in 2009, the 13 exterior curtain wall of the 13-story building is encased in seamless glass panels.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Hennigh, Hennigh Law CorporationMr. Hennigh may be contacted at
Scott.hennigh@hennighlaw.com
Settling with Some, But Not All, of the Defendants in a Construction Defect Case
March 28, 2018 —
David Adelstein – Florida Construction Legal UpdatesConstruction defect lawsuits can be complex multi-party disputes, especially when the plaintiff is doing what is necessary to maximize recovery. This means the plaintiff may sue multiple defendants associated with the defects and damage. For example, the owner (e.g., plaintiff) may sue the contractor, subcontractors, design professionals, etc. due to the magnitude of the damages. In many instances, the plaintiff is suing multiple defendants for overlapping damages. The law prohibits a plaintiff from double-recovering for the same damages prohibiting the windfall of a plaintiff recovering twice for the same damages. Perhaps this sentiment is straight common sense, but this sentiment is a very important consideration when it comes to settling with one or more of the defendants, while potentially trying the construction defect case as to remaining defendants.
Analysis and strategy is involved when settling with some but not all of the defendants in a construction defect case (and, really, for any type of case). Time must be devoted to crafting specific language in the settlement agreements to deal with this issue. Otherwise, the settlement(s) could be
set-off from the damage awarded against the remaining defendants.
The recent decision in
Addison Construction Corp. v. Vecellio, 43 Fla.L.Weekly D625(a) (Fla. 4th DCA 2018) details the analysis and strategy required when settling with some but not all of the defendants in a construction defect case, and the concern associated with a trial court setting-off the settlement amount from the damage awarded against the remaining defendants.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
COVID-19 Business Interruption Lawsuits Begin: Iconic Oceana Grill in New Orleans Files Insurance Coverage Lawsuit
April 20, 2020 —
Jeffrey J. Vita & William S. Bennett - Saxe Doernberger & Vita, P.C.On Monday, the iconic New Orleans restaurant, Oceana Grill, filed the first Coronavirus-related business interruption insurance coverage lawsuit in a US jurisdiction. The declaratory judgment action styled Cajun Conti, LLC, et. al. d/b/a Oceana Grill v. Certain Underwriters at Lloyd’s, London was filed in Louisiana state court for the Parish of Orleans. As a direct result of the government-mandated closures and restrictions on public gatherings implemented by the City of New Orleans and State of Louisiana, Oceana Grill’s petition anticipates a significant loss of business income.
Based on allegations in the petition, there are several aspects of Oceana Grill’s policy that make this a good test case for business interruption coverage stemming from the Coronavirus. Although the specific policy language is not quoted in the petition, coverage provisions are categorically identified throughout.
As a preliminary matter, the policy at issue appears to be written on an “all risks” basis, meaning the insuring agreement of the policy would likely be triggered generally by all risks of “physical loss or damage” unless specifically excluded. This basis for coverage, which is common in property policies, is advantageous to policyholders, as it limits the insured’s burden of proof to establishing that there was physical loss or damage while leaving the burden of applying any more specific exclusion to the insurance company.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
William S. Bennett, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at jjv@sdvlaw.com
Mr. Bennett may be contacted at wsb@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Anticipatory Repudiation of a Contract — The Prospective Breach
July 05, 2021 —
David Adelstein - Florida Construction Legal UpdatesThere are instances where a party can engage in the anticipatory repudiation of their obligations under a contract. In essence, this is basically a party prospectively breaching the contract by repudiating their obligations in the contract.
A prospective breach of contract occurs where there is absolute repudiation by one of the parties prior to the time when his performance is due under the terms of the contract. Such a repudiation may be evidenced by words or voluntary acts but the refusal must be distinct, unequivocal, and absolute. Moreover, repudiation can be shown where one party makes additional demands not included in the initial agreement:
The law is clear that where one party to the contract arbitrarily demands performance not required by the contract and couples this demand with a refusal to further perform unless the demand is met, the party has anticipatorily repudiated the contract, which anticipatory repudiation relieves the non-breaching party of its duty to further perform and creates in it an immediate cause of action for breach of contract.
24 Hr Air Service, Inc. v. Hosanna Community Baptist Church, Inc., 46 Fla. L. Weekly, D1344a (Fla. 3d DCA 2021) (quotations and citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Montrose III: Vertical Exhaustion Applies in Upper Layers of Excess Coverage
May 18, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Montrose Chemical Corp. of Cal. v. Superior Court (No. S244737, filed 4/6/20) (Montrose III), the California Supreme Court held that, as between excess insurers at differing levels of coverage, a rule of “vertical exhaustion” or “elective stacking” applies, whereby the insured may access any excess policy once it has exhausted other excess policies with lower attachment points in the same policy period. The Court limited the rule to excess insurance, stating that “[b]ecause the question is not presented here, we do not decide when or whether an insured may access excess policies before all primary insurance covering all relevant policy periods has been exhausted.”
Montrose manufactured the insecticide DDT in Torrance from 1947 to 1982. In 1990, the state and federal governments sued Montrose for environmental contamination and Montrose entered into partial consent decrees agreeing to pay for cleanup. Montrose claimed to have expended in excess of $100 million doing so, and asserted that its future liability could exceed that amount.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of