You Are on Notice: Failure to Comply With Contractual Notice Provisions Can Be Fatal to Your Claim
September 26, 2022 —
Jenifer B. Minsky - ConsensusDocsImagine your firm is the construction manager on a multi-million-dollar project. At the end of the project you are five million dollars out-of-pocket. You have a stack of claims for additional and extended work which led to the overrun, payment for which will easily cover the shortfall. However, the owner refuses to compensate you until you can satisfactorily answer their inquiry: “Where are the notices that are expressly required under the terms of the contract?” You had a good relationship with the owner’s field representative who was aware you were performing the work and understood that your company was compiling claims. The once cooperative owner, now suffering financial restraints of their own, is resolute in their refusal leaving you no choice but to expend substantial sums of money to litigate the claims, the success of which is far from assured.
What Contract Language Can Be A Trap For An Unwary Contractor?
While courts are generally hesitant to order a forfeiture and some courts disfavor condition precedents, a judge’s hands may be tied by particular contract language requiring the strict enforcement of notice requirements. Such provisions may include: (1) an explicit clause that there be precise compliance with notice requirements; (2) express consequences for noncompliance (e.g., if the required notice is not provided the claim will be waived, forfeited or abandoned); (3) a statement that the notice requirements are a condition precedent to recovery; (4) language such as “if,” “provided that,” “or else” or “on condition that” (e.g., the owner shall review the claim, “provided such claim” was received within the applicable notice period) or (5) prohibition of any waiver of the notice requirement. To the extent the notice provision includes such language, a contractor can be without recourse even when the owner has actual knowledge of the claims or cannot show prejudice by the lack of notice.
Read the court decisionRead the full story...Reprinted courtesy of
Jenifer B. Minsky, Peckar & Abramson, P.C.Ms. Minsky may be contacted at
jminsky@pecklaw.com
Trump Order Waives Project Environment Rules to Push COVID-19 Recovery
June 15, 2020 —
Debra K. Rubin, Mary B. Powers & Jim Parsons - Engineering News-RecordCiting the "national emergency" spurred by the COVID-19 pandemic's economic hit, President Donald Trump has signed an executive order that directs federal agencies to bypass environmental laws to expedite infrastructure projects, including those on federal lands, as a stimulus.
Reprinted courtesy of Engineering News-Record attorneys
Debra K. Rubin,
Mary B. Powers and
Jim Parsons
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Persimmon Offers to Fix Risky Homes as Cladding Crisis Grows
February 22, 2021 —
Olivia Konotey-Ahulu - BloombergPersimmon Plc, the U.K.’s biggest homebuilder, has offered to pay for work on potentially unsafe buildings in the wake of the cladding scandal that arose from London’s Grenfell Tower fire.
The firm has made a provision of 75 million pounds ($104 million) in its 2020 results for any necessary repair work on 26 buildings it developed that may be affected by the issue, it said in a statement Wednesday. It no longer owns the properties and said it would provide support where owners failed to accept their legal responsibilities.
“The concern around now banned cladding is affecting many thousands of homeowners who live in high-rise buildings right across the country,” Chairman Roger Devlin said in the statement. “We believe we have a clear duty to act to address this issue.”
Read the court decisionRead the full story...Reprinted courtesy of
Olivia Konotey-Ahulu, Bloomberg
Avoid Delay or Get Ready to Pay: The Risks of “Time-Is-of-The-Essence” Clauses
August 29, 2018 —
Stephen Orlando - Gordon & Rees Construction Law BlogLike death and taxes, construction delays are inevitable. Even the most cautious, diligent contractor may face subcontractor disputes, supply shortages, or inclement weather which slows down a project. Even if the contractor avoids unexpected problems, the sheer complexity of a job may cause a contractor to exceed the deadlines proposed in a contract.
Fortunately, courts recognize the practical reality of construction projects and the unavoidable delays which may arise. Therefore, as a general rule, a contractor is only liable for delayed completion of a project if the delay resulted from the contractor’s unreasonable performance of his or her work. Reasonable performance will typically serve as a defense to a claim of delayed completion. This defense is a vital asset when a contractor surpasses the project’s expected timeframe.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen Orlando, Gordon & Rees Scully Mansukhani
California Supreme Court Shifts Gears on “Reverse CEQA”
February 23, 2016 —
Garret Murai – California Construction Law BlogThe California Supreme Court has shifted gears on so-called “reverse CEQA” under the California Environmental Quality Act (“CEQA”).
The Supreme Court, in a much-anticipated decision, in California Building Industry Association v. Bay Area Air Quality Management District, Case No. S213478 (December 17, 2015), held that public agencies subject to CEQA are not required to analyze whether existing environmental conditions may impact a proposed project’s future users or residents – also known as “reverse CEQA” or “CEQA in reverse” – as opposed to the more traditional analysis of a proposed project’s impact on the environment, unless:
1. The proposed project risks exacerbating existing environmental hazards – in which case, it is the proposed project’s impact on the environment not the environment’s impact on the proposed project, which compels the evaluation; or
2. A reverse CEQA analysis is already required under statute, for example, on certain airport, school and housing projects.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Disputes Over Arbitrator Qualifications: The Northern District of California Offers Some Guidance
August 10, 2021 —
Justin K. Fortescue - White and WilliamsThe selection of an arbitration panel can often lead to disputes between the parties regarding things like whether a particular candidate is qualified, whether a challenge to an arbitrator’s qualifications can be addressed pre-award and whether a party that names an unqualified arbitrator should lose the opportunity to name a replacement. In Public Risk Innovations v. Amtrust Financial Services, No. 21-cv-03573, 2021 U.S. Dist. LEXIS 129464 (N.D. Ca. July 12, 2021), the court provided answers on all three of these issues.
In Amtrust, the parties filed cross-motions to compel arbitration. Although both parties agreed the dispute was arbitrable, they disagreed about whether Public Risk Innovations, Solutions and Management’s (PRISM) arbitrator was qualified under the terms of the applicable contract. In seeking to have PRISM’s arbitrator disqualified, Amtrust argued that he: (1) was not a “current or former official of an insurance or reinsurance company”; and (2) was not “disinterested.” Amtrust also argued that because PRISM named an unqualified arbitrator (and presumably the time to appoint had passed), PRISM should be deemed to have failed to select an arbitrator as required by the contract and that Amtrust had the right to select a second arbitrator of its choice.
Read the court decisionRead the full story...Reprinted courtesy of
Justin K. Fortescue, White and WilliamsMr. Fortescue may be contacted at
fortescuej@whiteandwilliams.com
Congratulations to BWB&O for Ranking in The U.S. News – Best Lawyers ® as “Best Law Firms”!
November 19, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce the firm has once again been regionally ranked by The U.S. News – Best Lawyers® with a “Best Law Firms” recognition in two practice areas, Family Law and Commercial Litigation. BWB&O is also honored to be included among many elite and extremely impressive groups of law firms! To read the Twelfth Edition of the “Best Law Firms” rankings, please click here.
Best Lawyers has a prominent reputation for being the most respected peer-review publication in the history of the legal profession. The “Best Law Firms” rankings are based on a rigorous evaluation process, which includes a combination of client feedback, information provided on the Law Firm Survey, the Law Firm Leaders Survey, and Best Lawyers peer review.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Suffolk Pauses $1.5B Boston Tower Project for Safety Audit After Fire
April 22, 2024 —
James Leggate - Engineering News-RecordThe team building the $1.5-billion, 51-story South Station Tower in Boston voluntarily shut down the jobsite April 9 for a safety stand down and audit after a small fire broke out, according to contractor Suffolk Construction. No one was injured.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of