Show Me the Money: The Good Faith Dispute Exception to Prompt Payment Penalties
March 13, 2023 —
Garret Murai - California Construction Law BlogCalifornia has a number of
prompt payment penalty statutes on the books. Among them is Civil Code section 8800 which requires project owners on private works projects to pay progress payments to direct contractors within 30 days after demand for payment pursuant to contract or be subject to prompt payment penalties of two percent (2%) per month on the amount wrongfully withheld. Like California’s other prompt payment penalty statutes, however, there is an important carve out: If there is a good faith dispute between the project owner and the direct contractor the project owner may withhold up to 150% of the dispute amount and not be subject to prompt payment penalties. And that, my friends, is a higher-tiered party’s “get out of jail free” card.
In a case of first impression, the 1st District Court of Appeals, in
Vought Construction Inc. v. Stock (2022) 84 Cal.App.5th 622, examined whether a project owner’s claim for liquidated damages constitutes a good faith dispute under Civil Code section 8800.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Defective Panels Threatening Profit at China Solar Farms: Energy
January 21, 2015 —
Bloomberg NewsFlaws found in some Chinese solar panels can drastically eat into their efficiency, reducing how much power the panels will produce as the country races to meet aggressive goals to hold the line on fossil fuel emissions.
The defects, found in products set to be used only in China, are in a coating that suppresses reflections on glass, allowing the panels to capture more light. About 23 percent of samples taken from dozens of Chinese companies failed to meet requirements, according to regulators in China. For samples from Jiangsu, the eastern province where much of the glass is made, the rate was as high as 40 percent.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
New Addition to the ASCE/SEI 7-22 Standard Protects Buildings from a 500-year Flood Event
June 05, 2023 —
The American Society of Civil EngineersReston, VA — The
American Society of Civil Engineers (ASCE) released a new update to their most widely used standard today,
ASCE/SEI 7-22 Minimum Design Loads and Associated Criteria for Building and Other Structures. As the increasing frequency of severe storms puts strain on communities across the globe, the design standard's
new flood load provisions will protect against 500-year flood events, which is a significant improvement to the 100-year flood hazard referenced in the previous version. The update — which is available in a supplement as a free download — is a significant revision of the design provisions in Chapter 5 to strengthen building resilience against the flood hazard. The ASCE 7 national loading standard is an integral part of building codes in the United States and around the globe.
"For more than 30 years, the ASCE 7 standard has been the authoritative source for the specification of minimum design loads and related criteria in the civil engineering community," said Tom Smith, ASCE Executive Director. "To ensure structures continue to be safe for the public, it is imperative that the standards we rely on are updated to account for emerging risks to the built environment. This Supplement is the most significant change to the standard's flood load provisions since the inception of ASCE 7 and will improve the safety and reliability of structures across the globe."
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Provides Independant Counsel When Conflict Arises Between Insurer and Insured
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Nevada Supreme Court, responding to certified questions, determined that an insurer must provide independent counsel for its insured when a conflict of interest arises between the insurer and insured. State Farm Mut. Auto. Ins. Co. v. Hansen, 2015 Nev. LEXIS 86 (Nev. Sept. 24, 2015).
The insured struck the vehicle of another driver, Hansen. Hansen sued the insured alleging both negligence and various intentional torts. State Farm agreed to defend under a reservation of rights. The reservation of rights letter reserved the right to deny coverage for liabiltiy resulting from intentional acts and punitive damages.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York High Court: “Issued or Delivered” Includes Policies Insuring Risks in New York
December 20, 2017 —
Bethany Barrese & Samantha Martino - Case Alert BlogOn November 20th, the New York Court of Appeals reinstated a case seeking more than six million dollars in damages against the insurers for DHL Worldwide Express Inc. (“DHL”), originating from a fatal head-on car crash between Claudia Carlson and a truck owned by MVP Delivery and Logistics Inc. (“MVP”), a DHL contractor. The truck, which bore DHL’s logo, was owned by MVP and driven by an MVP employee. The MVP employee was running an errand unrelated to his job at the time of the accident. Mrs. Carlson’s husband sued the employee, DHL, and MVP. The jury award of $20 million was reduced to $7.3 million by the Appellate Division. MVP’s insurer paid Mr. Carlson just over $1 million, and the employee assigned his rights to any other insurance coverage to Mr. Carlson
Mr. Carlson sued DHL and its insurers, seeking the balance of the outstanding judgment pursuant to New York Insurance Law § 3420. The defendants successfully moved to dismiss Mr. Carlson’s claims, which dismissal was affirmed by the Appellate Division on the basis that § 3420 did not apply since the policies in question were not “issued or delivered” in New York; they had been issued in New Jersey and delivered in Washington and Florida. The Court of Appeals was subsequently presented with two questions: (1) whether the DHL policies fell within the purview of Insurance Law § 3420 as policies “issued or delivered” in New York; and (2) whether MVP was an “insured” pursuant to the “hired auto” provisions of DHL’s policies.
Reprinted courtesy of
Bethany Barrese, Saxe Doernberger & Vita, P.C. and
Samantha Martino, Saxe Doernberger & Vita, P.C.
Ms. Barrese may be contacted at blb@sdvlaw.com
Ms. Martino may be contacted at smm@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Architect Blamed for Crumbling Public School Playground
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFThe city School Construction Authority (SCA) in Staten Island, New York, wants Ennead Architects to pay them $1.4 million to repair the playground at the Jerome Parker Educational Complex, according to Silive.com. Ennead Architects, based out of Manhattan, designed the William J. Clinton Presidential Center, and is currently working on the Vietnam Veterans Memorial Education Center in Washington, D. C. In the suit, as reported by Silive.com, SCA alleges, “the pavement has progressively cracked, buckled, become uneven and created pools of standing water, all presenting a safety hazard.” Silive.com stated that “an Ennead spokeswoman did not immediately return a telephone call” when asked to comment.
Read the court decisionRead the full story...Reprinted courtesy of
Personal Guarantor Cannot Escape a Personal Guarantee By…
June 02, 2016 —
David Adelstein – Florida Construction Legal UpdatesIn a prior article, I discussed the point that a
personal guarantor cannot escape a contractual requirement of a
personal guarantee merely by executing the guarantee as a corporate officer.
The recent decision Frieri v. Capital Investment Services, Inc., 41 Fla. L. Weekly D1189a (Fla. 3d DCA 2016) illustrates this point. In this case, a company hired an individual to help grow that company’s business. The contract required the individual to invest $6 Million into a trust in consideration of the company’s president transferring substantial shares of the company into the trust. The objective was that the trust would own the controlling shares of the company. The money was transferred. However, the shares were never placed in the trust and the trust never received controlling interest in the company.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com