Where Breach of Contract and Tortious Interference Collide
July 18, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
KONE is Shaking Up the Industry with BIM
January 20, 2020 —
Aarni Heiskanen - AEC BusinessKONE supplies elevators, escalators, autowalks and maintenance and modernization solutions. I sat down with Kenneth Flannigan to discuss how BIM is changing KONE and what it means to the industry.
KONE operates in over 60 countries, has around 1.3 million units in service, and moves over one billion people per day. The company’s mission is “to improve the flow of urban life.” Kenneth Flannigan is the BIM Solution Owner for the company. He acknowledges that even though KONE provides equipment and software innovation, in this day and age that’s not enough.
“We’re a critical path item. How innovative are we if we’re not working on every single project in a shared 3D environment, like our customers?” Flannigan asks.
KONE serves both indirect and paying customers. It works with influencers like architects and with general contractors, builders, and construction managers. It also has a life-cycle relationship with building owners, which is evidenced by the fact that over 30% of the company’s sales come from maintenance.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Mortgage Whistleblower Stands Alone as U.S. Won’t Join Lawsuit
April 28, 2014 —
Jef Feeley and David McLaughlin – BloombergTwo years after Lynn Szymoniak helped the U.S. recover $95 million from Bank of America Corp. and other lenders for mortgage-fraud tied to the housing bubble, the whistle-blower said the government is ignoring a chance to collect more money for identical claims against other banks.
Szymoniak got $18 million when the U.S. Justice Department intervened in her foreclosure-fraud lawsuit. The government negotiated a settlement with five lenders including Bank of America and JPMorgan Chase & Co. (JPM)
The other banks accused of the same behavior, including Deutsche Bank AG (DBK) and HSBC Holdings Plc (HSBA), are still fighting Szymoniak’s suit, saying she isn’t a true whistle-blower. And the U.S., while continuing its crackdown on banks that packaged risky loans for sale as securities, hasn’t joined with her this time, leaving her to fight the banks alone. U.S. District Judge Joseph Anderson in Columbia, South Carolina, today is set to consider their bid to throw the case out.
Mr. Feeley may be contacted at jfeeley@bloomberg.net; Mr. McLaughlin may be contacted at dmclaughlin9@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Jef Feeley and David McLaughlin, Bloomberg
Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
First Look at Long List of AEC Firms Receiving PPP Loans
July 20, 2020 —
Tom Ichniowski & Scott Blair - Engineering News-RecordThousands of construction and design firm from all parts of the U.S. appear on lists of companies that have received federal Paycheck Protection Program forgivable loans, according to federal documents just made public.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record and
Scott Blair, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Mr. Blair may be contacted at blairs@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of Idaho Rules That Substantial Compliance With the Notice and Opportunity to Repair Act Suffices to Bring Suit
July 31, 2018 —
Lian Skaf - The Subrogation StrategistIn Davison v. Debest Plumbing, Inc., 416 P.3d 943 (Ida. 2018), the Supreme Court of Idaho addressed the issue of whether plaintiffs who provided actual notice of a defective condition, but not written notice as stated in the Notice and Opportunity to Repair Act (NORA), Idaho Code §§ 6-2501 to 6-2504, et. seq., substantially complied with the act and if the plaintiffs’ notice was sufficient to bring suit. Section 6-2503 of the NORA states that, “[p]rior to commencing an action against a construction professional for a construction defect, the claimant shall serve written notice of claim on the construction professional. The notice of claim shall state that the claimant asserts a construction defect claim against the construction professional and shall describe the claim in reasonable detail sufficient to determine the general nature of the defect.” Any action not complying with this requirement should be dismissed without prejudice. The court held that the defendant’s actual notice of the defect was sufficient to satisfy the objectives of the NORA and, thus, the plaintiffs’ action complied with the NORA.
In Davison, Scott and Anne Davison hired general contractor Gould Custom Builders (Gould) to remodel a vacation home in McCall, Idaho. Gould subcontracted out the plumbing work to Debest Plumbing (Debest). This work included installing a bathtub. When the Davisons arrived at their home for the first time on July 25, 2013, they noticed a leak from the subject bathtub. The Davisons contacted Gould and, the next morning, Gil Gould arrived with a Debest employee to inspect the home. In addition to inspecting the home, the Debest employee repaired the leak and helped Gould remove some water-damaged material.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams, LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Following Mishaps, D.C. Metro Presses on With Repairs
February 23, 2017 —
Jim Parsons - Engineering News-RecordAn aggressive effort to overhaul the aging Metro system in Washington, D.C., is producing results as it nears the one-year mark, with more than 28,000 cross-ties and nearly two miles of grout pads now replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
Insurer's Motion to Dismiss "Redundant Claims" Denied
June 21, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion to dismiss was more appropriate for an eventual summary judgment motion and was consequently denied. Sivan Lam v. Scottsdale Ins. Co., 2024 U.S. Dist. LEXIS 81262 (M.D. Fla. April 12, 2024).
Lam suffered a loss to her home due to Hurricane Ian. When only a portion of the claim was paid, Lam sued his insurer, Scottsdale, for breach of contract (Count I) and declaratory relief (Count II).
Scottsdale argued that Lam's request for declaratory relief was redundant of her breach of contract claim. The court noted that Rule 12 (b)(6), Fed. R. Civil P., was a vehicle to challenge a claim's sufficiency. Redundancy was not insufficiency, and it was not a ground for dismissal under Rule 12 (b)(6).
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at