New Jersey Federal Court Examines And Applies The “j.(5)” Ongoing Operations Exclusion
October 07, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn PJR Construction of N.J. v. Valley Forge Insurance Company, 2019 U.S. Dist. LEXIS 127973 (D.N.J. July 31, 2019) (PJR Construction), a New Jersey federal court held that the “j.(5)” “Ongoing Operations Exclusion” applied to bar coverage for property damage to property on which a construction company allegedly performed faulty work. The court’s opinion follows prior New Jersey state court precedent, including Ohio Casualty Insurance Company v. Island Pool & Spa, Inc., 12 A.3d 719 (N.J. Super. Ct. App. Div. 2011) (Island Pool), but also provides additional guidance on the elements which can make the Ongoing Operations Exclusion applicable to exclude coverage.
In PJR Construction, a commercial property owner engaged a construction company to build a 26,000 square foot swim club and related 3,000 square foot pavilion building in New Jersey. After about 75% of the work was completed, the property owner fired the construction company and denied it access to the property. The owner later sued the construction company in New Jersey state court alleging “shoddy workmanship” in, among other things, sealants, flashing, water resistant barriers, masonry and the handicap ramps. The construction company sought coverage from its CGL insurer, which denied coverage based on, among other things, the j.(5) Ongoing Operations Exclusion. After the denial of coverage, the company sued the insurer in New Jersey federal court seeking a declaration of coverage.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Withdrawal Liability? Read your CBA
July 10, 2018 —
Wally Zimolong – Supplemental Conditions Withdrawal liability is a huge issue facing unionized employers. According to Bloomberg, 93% of the Top 200 largest pension plans are underfunded by a combined $382 billion. Contractors that withdraw from a multi-employer pension plan can face hundreds of thousands or millions of dollars in assessed withdrawal liability. However, employers may be able to avoid that liability, plus the legal and consulting fees to fight it, by simply reading their collective bargaining agreement.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Sixth Circuit Affirms Liability Insurer's Broad Duty to Defend and Binds Insurer to Judgment Against Landlord
September 07, 2020 —
Michael V. Pepe & Janie Reilly Eddy - Saxe Doernberger & VitaIn a victory for policyholders, the Sixth Circuit affirmed that a landlord’s insurer owed a duty to defend the landlord in a bodily injury claim arising out of a fire that killed three and injured one. The Court held that the insurer breached its duty to defend and was bound to the insured’s $3 million consented judgment.
Transition Investments LLC, an owner of three properties in the Detroit area, purchased a general liability insurance policy with Hamilton Specialty Insurance Company to insure its properties. At one of the properties, a faulty stove started a fire, destroying the building, injuring one person and killing three others. The estates of the deceased and the injured party sued Transition in Michigan state court. In their complaint, the plaintiffs contended that Transition failed to provide a habitable premise and neglected to maintain the property’s stove, which allegedly caused the fire. The plaintiffs argued that Transition’s negligent maintenance of the property led to the fire and the resulting injuries. Transition subsequently tendered the claim to Hamilton. Hamilton claimed that the insurance policy did not cover the fire’s damages and refused to participate in the state court litigation. Ultimately, Transitions entered into a consent judgment with the plaintiffs for $3 million.
Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & Vita and
Janie Reilly Eddy, Saxe Doernberger & Vita
Mr. Pepe may be contacted at mvp@sdvlaw.com
Ms. Eddy may be contacted at jre@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
MBIA Seeks Data in $1 Billion Credit Suisse Mortgage Suit
June 26, 2014 —
Chris Dolmetsch and Jody Shenn – BloombergMBIA Inc. (MBI) asked a judge to order Credit Suisse Group AG (CSGN) to turn over internal records that the bond insurer says bolster its contention the bank lied about how it processed loans packaged into mortgage-backed securities.
MBIA said in a court filing today that Credit Suisse has withheld evidence about how the bank’s actual practices diverged from its representations -- including documents identified as exhibits in other lawsuits based on the same allegations.
The bond insurer asked Justice Shirley Werner Kornreich in New York State Supreme Court in Manhattan to force the bank to search documents and e-mails on its policies and practices including those related to loan underwriting and origination, due diligence and post-acquisition quality-control review.
Mr. Dolmetsch may be contacted at cdolmetsch@bloomberg.net; Ms. Shenn may be contacted at jshenn@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Chris Dolmetsch and Jody Shenn, Bloomberg
New Jersey Law Firm Sued for Malpractice in Construction Defect Litigation
July 23, 2014 —
Beverley BevenFlorez-CDJ STAFFBerman Sauter Record & Jardim PC are facing a New Jersey state legal malpractice suit. According to Law 360, condominium associations claimed the law firm “didn't properly name subcontractors as defendants in the associations' complaint over various construction defects, thus blocking them from obtaining damages despite a $1.2 million settlement.”
Law 360 reported that the “suit seeks compensatory damages, with interest and costs; reimbursement of attorneys' fees and litigation costs and expenses for both the instant and underlying complaints; and further relief.”
The law firm is no longer active, according to Law 360.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Miller Act Bond Claims Subject to “Pay If Paid”. . . Sometimes
November 04, 2019 —
Christopher G. Hill - Construction Law MusingsThe Federal Miller Act is a great tool that subcontractors and suppliers on Federal projects can use for collection of wrongfully withheld amounts due. However, as a recent federal case from the Eastern District of Virginia points out, the construction contract’s terms affect when a subcontractor or supplier can use this great collection tool and how much it can recover.
In Aarow v Travelers the Court looked at the interaction between a typical termination clause, a “pay when paid” clause, and the Miller Act. The key facts are these. The general contractor on the project at issue, Syska, did not get paid some disputed amounts by the owner and subsequently did not pay Aarow, the plaintiff and a subcontractor on the project. Aarow then refused to continue work and was terminated by Syska who then took over the completion of the work. Aarow sued, seeking damages for the value of its work prior to the termination. Travellers, the surety defended stating that, if Aarow was properly terminated for cause by Syska, then Aarow was not entitled to payment under the contract until such time as the work was completed and accepted by the owner. The termination clauses are set out in the linked opinion.
The Court agreed with Travelers, stating that the pay when paid clause created a situation whereby Aarow could not stop work merely because of a non-payment by Syska attributed to non-payment by the owner. The Court was clear in stating that the Miller Act trumps “pay when paid” in instances where the only cause for non-payment is non-payment by an owner. The Court then reasoned that it is the interaction between the termination and “pay when paid” provisions, and not the “pay when paid” clause itself, that exonerated Travelers because it created the default by Aarow due to its refusal to continue work. In short, Aarow was properly terminated for cause because it left the job without justification and therefore Travelers was not liable.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Real Estate & Construction News Roundup (10/18/23) – Zillow’s New Pilot Program, Production Begins at Solar Panel Plant in Georgia, and More Diversity on Contracts for Buffalo Bills Stadium
November 27, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, Netflix announces plans to open brick-and-mortar locations, NYU develops a way to examine buildings using drones, robots and AI, distressed U.S. commercial real estate hits a 10-year high, and more!
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team