The Heat Is On
June 13, 2022 —
Christopher Durso - Construction ExecutiveEvery year, NASA and the National Oceanic and Atmospheric Administration (NOAA) team up to assess global temperatures and climate trends. (Yes, that NASA. A big part of the space agency’s mission is focused on Earth science, with the goal of better understanding the planet’s interconnected systems.) The two groups released their findings for 2021 this past January, with several predictably alarming highlights:
- 2021 was the sixth-warmest year on record, with the average global surface temperature about 1.5°F over the 20th-century baseline periods that the agencies use for comparison and nearly 2°F higher than in the late-19th century.
- The surface temperature in the Northern Hemisphere was also the sixth-highest on record, at nearly 2°F over baseline, with the land temperature exceeding the baseline by 2.8°F.
- Extreme climate events included an above-average Atlantic hurricane season, with 21 storms, and a severe heat wave in the northwestern United States and western Canada in June during which Canada recorded its highest temperature ever, at 121°F.
Reprinted courtesy of
Christopher Durso, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
2017 Legislative Changes Affecting the Construction Industry
November 21, 2017 —
Melinda S. Gentile – Peckar & Abramson, P.C.Originally published by CDJ on July 13, 2017
The 2017 Florida Legislative Session recently concluded, and a number of important construction-related House Bills (HB) and Senate Bills (SB) were presented during the Session, most notably SB 204/HB 377. These Bills may impact General Contractors and Construction Managers in a number of ways, not the least of which is the period of time that a cause of action may be initiated for the design, planning or construction of an improvement.
The following construction-related Bills passed in both the House and Senate and will become law if approved by the Governor.
Senate Bill (SB) 204/House Bill (HB) 377: Relating to the Statute of Repose for causes of action based on design, planning or construction of an improvement to real property. This bill passed both the House and the Senate and was approved by the Governor on June 14, 2017. This bill becomes effective on July 1, 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Melinda S. Gentile, Peckar & Abramson, P.C.Ms. Gentile may be contacted at
mgentile@pecklaw.com
New Jersey Law Firm Sued for Malpractice in Construction Defect Litigation
July 23, 2014 —
Beverley BevenFlorez-CDJ STAFFBerman Sauter Record & Jardim PC are facing a New Jersey state legal malpractice suit. According to Law 360, condominium associations claimed the law firm “didn't properly name subcontractors as defendants in the associations' complaint over various construction defects, thus blocking them from obtaining damages despite a $1.2 million settlement.”
Law 360 reported that the “suit seeks compensatory damages, with interest and costs; reimbursement of attorneys' fees and litigation costs and expenses for both the instant and underlying complaints; and further relief.”
The law firm is no longer active, according to Law 360.
Read the court decisionRead the full story...Reprinted courtesy of
Are COVID-19 Claims Covered by Builders Risk Insurance Policies?
May 04, 2020 —
Jason M. Adams, Gibbs Giden Locher Turner Senet & Wittbrodt LLP and Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.If you are an attorney, insurance broker, or other professional representing developers and contractors, then your clients have likely reached out with concerns about losses related to COVID-19. One common question is whether there is potential coverage under builders risk insurance policies.
The short answer is: It depends. As with most questions pertaining to insurance coverage, the answers depend on the specific policy language and underlying facts required to trigger coverage. Builders risk policies are even more fact specific due to the lack of uniformity of base policy forms and endorsements between insurance carriers.
The first step in any analysis is to gather facts and carefully document any impending and potential damages or delays. The facts are crucial because the coverage analysis may vary depending on the specific reason the project was shut down. For example, the analysis would be different if the project was shut down as a result of an express government order, such as those in Northern California and Washington, versus the project shutting down as a result of workers testing positive for COVID-19. Properly analyzing builders risk coverage involves a granular account of the facts and damages, and can require a great deal of hair splitting with respect to specific policy language.
Regardless of the strength of the insured’s facts and damages, or the breadth of its policy language, the policyholder still likely faces an uphill battle in finding coverage for COVID-19 related claims. The unfortunate reality of most builders risk policies is that they are property policies that require some evidence of physical loss or damage to trigger coverage. Whether or not COVID-19 claims constitute property damage will be the subject of great debate and litigation over the coming months and years. The outcome will likely depend on how the insured’s jurisdiction ultimately rules on the litany of COVID-19 cases that have already been filed – specifically, how broadly each court interprets the meaning of “physical loss or damage.”
Although these key issues have yet to be clearly defined by the courts, some policies are better than others and there are specific variables that could affect the likelihood of coverage. For example, some of the more policyholder-friendly insurance programs may contain coverage extensions for delay in completion, business interruption, loss of rental income, or civil authority that may not be tied to the property damage requirement, and which would tend to support coverage for COVID-19 claims.
Even if the insured crosses the initial threshold and can demonstrate a covered claim, the following common endorsements and exclusions may require additional analysis depending on the facts.
- Virus or Pandemic Exclusions: Virus or pandemic exclusions are not as common on builders risk policies as they may be on other forms of coverage. However, they do exist and, if present, result in a significant barrier to coverage. As with the policy itself, every endorsement is different and should be analyzed in terms of the express language contained in the endorsement and the facts.
- Abandonment or Cessation of Work: Most builders risk policies include provisions that preclude coverage in the event of the abandonment of the project or a lengthy cessation of work. As a result, the insured should take steps to articulate to the carrier that the project has not been abandoned, and that there exists an intent to return as soon as possible. The insured should also maintain a record of ongoing project oversight and protection efforts taken during the period when construction operations are suspended.
- Security and Safety Requirements: Many builders risk policies contain provisions requiring the insured to maintain protective safeguards and security protocols throughout the pendency of the project. Safety fencing, lighting and security guards are common examples. The policy should be analyzed to ensure that the policyholder can meet any such requirements during a COVID-19 related shutdown. For example, can the insured continue to staff a security guard? If not, arrangements will likely need to be made with the carrier depending on the language of the policy.
- Insurable Limits: Builders risk policies are typically underwritten based upon the total completed value of the structure, including materials and labor. The insured will need to analyze the policy to consider whether increased material or labor costs as a result of COVID-19 will alter the terms of coverage, trigger any escalation clauses, or result in an increase in premium due. If increased cost projections become apparent, the insured should report these changes to the carrier immediately.
- Extensions of Coverage: The insurance industry was facing a hard market even before the COVID-19 pandemic, which resulted in higher premiums and limited coverage options. The COVID-19 pandemic has only exacerbated these issues and it may be difficult to obtain coverage extensions on projects that have been shut down. The insured should work with its risk management team (risk manager, insurance broker and lawyer) to engage the carriers to negotiate any necessary coverage extensions resulting from COVID-19 related project delays.
To summarize, builders risk coverage for COVID-19 claims is far from certain, but not impossible. Insureds should provide notice of a claim to all potentially applicable carriers in order to preserve their rights. The insured should also report increased construction cost and articulate its intent to return to the project to preserve their escalation clause and avoid arguments that they have abandoned the project. The insured should continue to document its claims and damages, and be ready to substantiate its claims and push back on any coverage denial. Throughout the entirety of this process, the insured should work with its risk management team to get out in front of any extensions it may need to complete the project. In a climate where insurance carriers are receiving an insurmountable number of claims, the insured should be prepared to fight for coverage and not simply throw up its hands in the face of a denial. Given the intense social, legislative and executive pressure to cover COVID-19 claims, there may be a tendency for the courts to find coverage in gray areas, particularly if the insured was fortunate enough to have purchased one of the broader coverage forms referenced above.
About the Authors
Jason M. Adams, Esq. (jadams@gibbsgiden.com) is a partner at Gibbs Giden representing construction professionals in the areas of Construction Law, Insurance Law and Risk Management and Business/Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Jason represents developers, contractors, public entities, investors, lenders, REITs, design professionals, and other construction professionals at all stages of the construction process. Jason is a published author and sought-after speaker at seminars across the country regarding high level construction risk management and insurance topics. Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms.
Cheryl L. Kozdrey, Esq. (clk@sdvlaw.com) is an associate at Saxe Doernberger & Vita, P.C., a national insurance coverage law firm dedicated exclusively to policyholder representation and advocacy. Cheryl advises insurance brokers, risk managers, and construction industry professionals regarding optimal risk transfer strategies and insurance solutions, including key considerations for Builder’s Risk, Commercial General Liability, D&O, and Commercial Property policies. She assists clients with initial policy reviews, as well as renewals and modification(s) of existing policies to ensure coverage needs are satisfied. Cheryl also represents policyholders throughout the claims process, and in coverage dispute litigation against insurance carriers. She is currently working on some of the largest construction defect cases in the country. Cheryl is a published author and is admitted to practice in the State of California and all federal district courts within the State.
Read the court decisionRead the full story...Reprinted courtesy of
Caterpillar Said to Be Focus of Senate Overseas Tax Probe
March 26, 2014 —
Richard Rubin and Jesse Drucker - BloombergA U.S. Senate investigative panel is examining Caterpillar Inc. (CAT) and whether the company improperly avoided U.S. taxes by moving profits outside the country, said three people familiar with the inquiry.
The Senate’s Permanent Subcommittee on Investigations will hold a hearing in early April, said two of the people. They spoke on condition of anonymity before an official announcement.
Rachel Potts, a spokeswoman for Caterpillar, declined to comment. Two staff members for the subcommittee declined to comment.
In 2009, Daniel Schlicksup, an employee who had worked on tax strategy, alleged in a lawsuit in federal court that Caterpillar used a “Swiss structure” to shift profits to offshore companies and avoid more than $2 billion in U.S. taxes. He also alleged that Caterpillar used a “Bermuda structure” involving shell companies to return profits to the U.S. without paying required taxes.
Mr. Rubin may be contacted at rrubin12@bloomberg.net; Mr. Drucker may be contacted at jdrucker4@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Richard Rubin and Jesse Drucker, Bloomberg
CDJ’s Year-End Review: The Top 12 CD Topics of 2015
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFAs a new year begins, Construction Defect Journal has put together the most important issues and topics relating to the construction defect industry in 2015. New cases have arisen to challenge Right to Repair laws and other construction-related claim procedures, some states have made legislative or code changes, as well as other intriguing topics have been discussed in board rooms and over conference calls. We hope you enjoy the look-back at 2015, and we wish you and yours a prosperous 2016.
Read the court decisionRead the full story...Reprinted courtesy of
The Registered Agent Advantage
October 22, 2014 —
Christopher G. Hill – Construction Law MusingsIn the Commonwealth of Virginia, as in most states, all corporations, LLC’s or other corporate style entities are required to have a registered agent if they are to do business in the Commonwealth. The reasons for the requirement are many, but the main ones are taxation, service of process and communication from the Virginia State Corporation Commission (the “SCC”). Without such a registered agent, many rights, for example the right to prosecute a lawsuit, are not available to the unregistered entity.
As a construction company that I hope is incorporated (if you aren’t you should do take this step), your registered agent can be an officer of the company, a company that meets the requirements of the SCC that allow it to act as a registered agent, or an attorney licensed in the Commonwealth of Virginia. It is this last category that you should carefully consider.
Why do I think that a Virginia construction attorney is the best candidate for use as the registered agent of either a local or out of state contractor or subcontractor? As you might imagine from the title of this post, I’ll let you know.
Read the court decisionRead the full story...Reprinted courtesy of