California Contractor Tests the Bounds of Job Order Contracting
March 01, 2021 —
Garret Murai - California Construction Law BlogMost contractors have heard of design-bid-build, design-build, construction manager at risk, and even public private partnerships, various project delivery methods, which, at their heart, focus on balancing the interests of the various parties involved in a construction project, from owners, to design professionals, to contractors. There’s one project delivery method you may not be as familiar with though: Job Order Contracting, also known by its acronym JOC.
JOC contracting is a project delivery method used on public works projects and has been authorized to be used by California K-12 school districts, community colleges, CalState universities, and the Judicial Council of California, which, among other things, is responsible for the construction of California state courts. It is intended to be used on smaller, independent, long-horizon project typically involving maintenance, repair and refurbishment. Think periodic maintenance of facilities.
JOC contracts are administered by public entities issuing a request for proposals. The public entity then awards a JOC contract to the lowest responsible bidder. The lowest responsible bidder then enters into a JOC contract with the public entity. JOC contracts typically have a duration of one (1) year and are limited to a total construction value of $4.9 million increased annually based on the Consumer Price Index. When entering into a JOC contract, a JOC contractor agrees to perform work at prices set forth in a Construction Task Catalog also known as a unit price book which includes current local labor, material and equipment costs. Unit prices are then adjusted by a “bid adjustment factor” based on the JOC contractor’s bid. When work is needed, the public entity will then issue a job order to the JOC contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Just Decided – New Jersey Supreme Court: Insurers Can Look To Extrinsic Evidence To Deny a Defense
September 05, 2022 —
Randy J. Maniloff - White and Williams LLPLast week, the New Jersey Supreme Court decided Norman International, Inc. v. Admiral Insurance Company, No. 086155 (N.J. Aug. 11, 2022). At issue was coverage for a work-site injury and the interpretation of a policy exclusion for operations or activities performed by an insured in certain counties in New York. The case is significant in terms of addressing causation for purposes of the application of exclusions. But the more wide-reaching issue has nothing to do with the scope of the exclusion.
The real story from Norman is the New Jersey high court’s pronouncement that an insurer, in certain circumstances, can use extrinsic evidence to deny a defense to its insured. New Jersey duty to defend law has been a jungle land and in need of more supreme court guidance.
Read the court decisionRead the full story...Reprinted courtesy of
Randy J. Maniloff, White and Williams LLPMr. Maniloff may be contacted at
maniloffr@whiteandwilliams.com
4 Ways the PRO Act Would Impact the Construction Industry
October 24, 2021 —
Andrew M. MacDonald - ConsensusDocsThe Protecting the Right to Organize Act (the “PRO Act”) is a proposed law that would dramatically rewrite the National Labor Relations Act (“NLRA”). Breathtakingly broad in scope, the PRO Act targets several longstanding features of existing law perceived by unions and labor activists to be unfair to labor and too favorable to employers. The proposed legislation is essentially a grab-bag of grievances that the labor movement has compiled over decades and sought to change through legislation and before the National Labor Relations Board (“NLRB”) without success in the past.
While the PRO Act would affect virtually all private sector employers, it would alter the labor dynamic in the construction industry in four major ways:
1. Removing the current prohibitions on secondary, jurisdictional, and other forms of picketing. Current law attempts to balance the rights of employers to operate their businesses without unnecessary interference with the rights of unions to protest concerning wages and working conditions. As part of this balancing act, the NLRA prohibits unions from picketing under certain conditions or with certain aims. These restrictions include the prohibition on “secondary” picketing by unions of neutral employers, which are employers with which the union does not have a direct labor dispute, and “jurisdictional” picketing by unions to force an employer to assign certain work to a specific trade or group of employees. The elimination of these restrictions in the PRO Act would have a significant impact on the construction industry.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew M. MacDonald, Fox Rothschild LLPMr. MacDonald may be contacted at
amacdonald@foxrothschild.com
BHA Announces New Orlando Location
September 30, 2019 —
Donald MacGregor - Bert L. Howe & Associates, Inc.Bert L. Howe & Associates, Inc., one of the country’s leading construction forensics and consulting firms has just announced the opening of their second Florida office. Located in Orlando, this new office will join BHA’s existing Miami location, expanding BHA’s presence in the state and increasing the firm’s ability to provide the highest level of services and logistic support to their clients in Central and North Florida, and in particular, the Orlando, Tampa, Jacksonville and Tallahassee markets.
Since 1993, BHA has been an industry leader in providing construction consulting and forensic services and has been a trusted partner with builders and insurance carriers, both large and small, across the United States. In Florida, BHA has been providing construction defect, storm, and general construction-claims related forensic expert services for the past decade with a proven track record of successful results.
With the addition of new offices in Orlando, Bert L. Howe & Associates, Inc. offers the experience of over 20 years of service to carriers, defense counsel, and insurance professionals as designated experts in over 7,000 claims. BHA’s staff encompasses a broad range of Florida-licensed and credentialed experts in the areas of general contracting and specialty trades, as well as architects, and both civil and structural engineers, and has provided services on behalf of carriers, developers, general contractors and sub-contractors alike.
BHA’s new Orlando office is located in the Regions Bank Tower, 111 North Orange Avenue, Suite 800, Orlando FL, 32801.
Read the court decisionRead the full story...Reprinted courtesy of
Donald MacGregor, Bert L. Howe & Associates, Inc.Mr. MacGregor may be contacted at
donm@berthowe.com
The Job is Substantially Complete, the Subcontract was Never Signed, the Subcontractor Wants to be Paid—Now What?
July 28, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCA recent case in North Carolina illustrates the types of problems created when a general contractor accepts a subcontractor’s bid and then allows the subcontractor to perform the work without obtaining a signed subcontract.[i] In this case, the general contractor (Choate Construction Company – “Choate”) accepted a bid from a foundation subcontractor (Southeast Caissons, LLC – “SEC”). Choate sent the subcontract to SEC. SEC provided its changes in a “Proposed Addendum” to the subcontract stating, “[SEC] hereby accepts the terms of the attached Subcontract, subject to and conditioned upon Choate[’s] acceptance of the terms set forth in this Addendum[.]” After that, Choate called SEC and exchanged emails concerning the subcontract terms, but did not reach an agreement. SEC then performed its subcontract and sought payment, and acknowledged it had not signed the subcontract. Choate agreed it owed SEC something, but refused to pay because SEC did not have a signed subcontract, asserting the subcontract was not binding on Choate.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
St. Petersburg Florida’s Tallest Condo Tower Allegedly Riddled with Construction Defects
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFIn a new lawsuit, the Signature Place Condominium Association claims "it is spending ‘large sums' of money to repair problems ranging from cracks in exterior walls to improper fire wall installation to excessive noise from air-conditioning and heating systems,” according to the Tampa Bay Times.
The lawsuit also stated that “some of the alleged defects were hidden by building components and finishes and thus were not discovered by owners "until after the purchase and occupancy of the unit,” reported the Tampa Bay Times.
The association “seeks damages in excess of $15,000, cites more than 100 other alleged construction and design defects.”
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Clean Air, Clean Water, Citizen Suits and the Summer of 2022
November 01, 2022 —
Anthony B. Cavender - Gravel2GavelThis is a selection of significant environmental and regulatory law cases decided by the federal courts after the Supreme Court’s 2021 Term concluded.
The U.S. Court of Appeals for the DC Circuit
National Association of Broadcasters v. Federal Communications Commission
On July 12, 2022, the DC Circuit held that an order of the FCC requiring radio broadcasters to follow a prescribed five-step process to verify the identity of program sponsors was not authorized by the Communications Act. According to the court, the FCC “decreed a duty that the statute does not require, and that the statute does not empower the FCC to impose.” Here, the agency failed to identify the statutory authority it needed to authorize the issuance of such an order. While certainly not as significant as the Supreme Court’s ruling in West Virginia v. EPA, decided only a few days before this decision was released, it is a strong reminder that the courts want to know if a challenged rule is authorized by law.
Humane Society of the U.S., et al., v. U.S. Department of Agriculture
On July 22, 2022, the court decided a case involving the steps the Administrative Procedure Act and the Federal Register Act require to be taken before a final agency rule is legally promulgated. Customarily, when there has been a change in Presidential administrations, the incoming administration “quietly” withdraws rules awaiting Federal Register publication without much ceremony. The majority of this panel agreed that public notice should have been provided to the regulated community to comment on the new administration’s action to pull back a new rule which had been made available for public inspection before Federal Register publication that would have strengthened the protections afforded “show horses,” as now required by law. The court noted that “it seems clear that filing with the Federal Register constituted promulgation of a regulation even though publication may not occur until a later date.” Circuit Judge Rao filed a strong dissent. “By cutting off agency discretion at public inspection, the majority imposes judicial burden on agency procedures that conflicts with circuit precedent, the statutory framework and a longstanding regulation permitting withdrawals prior to publication.” There could be a further review of this unique ruling.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Court of Appeals Finds Arbitration Provision Incorporated by Reference Unenforceable
September 20, 2021 —
Garret Murai - California Construction Law BlogSubcontractors have gotten accustomed to incorporation clauses in their contracts. While an incorporation clause can incorporate any document, most typically, it’s the prime contract between the general contractor and the project owner. Subcontractors will sometimes even accept these documents sight unseen which can be a recipe for disaster. But not in the next case.
In Remedial Construction Services, LP v. AECOM, Inc., Case No. B303797 (June 15, 2021), the 2nd District Court of Appeal examined whether a subcontractor was bound to an arbitration provision contained in a prime contract that was incorporated by reference into the subcontractor’s contract. In this case, it was the prime contractor who was in for a surprise.
The Remedial Construction Case
In 2015, Shell Oil Products US, LLC entered into a prime contract with AECOM Technical Services, Inc. for the demolition, remediation and restoration of the Gaviota oil terminal in Goleta, California. AECOM in turn entered into a subcontract with Remedial Construction Services, LP to perform portions of the work. When AECOM refused to pay Remedial for delay costs asserted by Remedial, Remedial filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at