Is a Text a Writing?
June 10, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCIs a text message a writing? Project communication is constantly evolving, and text messages are an increasingly common way teams share pictures, video, and provide project updates. When texting is part of the communication flow on a project, contractors and owners might text approvals for extra work, notices of changed conditions, or other information that could be a basis for a change order.
In a text exchange about a compensable event, the notice, reply, and approval are all saved on the phone. But contracts often contain specific requirements for a contractor or subcontractor to request changes and authorization to proceed may be specifically required in writing.
For example, the Associated General Contractors of Washington – 2018 Standard Subcontract says the “Subcontractor shall make no claims for extras unless the same shall be agreed upon
in writing by Contractor prior to performance of any such extra work.” (emphasis added).
The AGC subcontract doesn’t define “writing,” so the subcontractor and contractor might wonder if a text message exchange about a potentially compensable event was an “agreement in writing.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
The Status of OSHA’s Impending Heat Stress Standard
May 30, 2022 —
Stephen E. Irving - ConsensusDocsThere has been much talk in the last several months about OSHA’s intent to establish a national standard to prevent heat-related injury and illness. OSHA’s Region VI, covering the states of Texas, Louisiana, Arkansas, Oklahoma, and New Mexico
[1], has had a regional emphasis program dealing with the hazards of heat stress for more than two decades, and much of the talk about a new national standard suggests modeling some aspects of the standard after the Region VI program. Region VI’s long-standing program emphasizes water, rest, and shade; acclimatization; and responding to medical emergencies.
In October 2021, OSHA issued its advance notice of proposed rulemaking (ANPRM) for Heat Injury and Prevention. The ANPRM rulemaking established a new Heat Injury and Illness Prevention Work Group within the National Advisory Committee on Occupational Safety and Health (NACOSH.)
Read the court decisionRead the full story...Reprinted courtesy of
Stephen E. Irving, Peckar & AbramsonMr. Irving may be contacted at
sirving@pecklaw.com
Wilke Fleury Attorneys Featured in 2022 Northern California Super Lawyers and Rising Stars Lists
September 05, 2022 —
Wilke Fleury LLPWilke Fleury is extremely proud that 14 of its incredibly talented attorneys are featured in the Annual List of Top Attorneys in the 2022 Northern California Super Lawyers magazine! Super Lawyers rates attorneys in each state using a patented selection process and publishes a yearly magazine issue that produces award-winning features on selected attorneys. Congratulations to this talented group:
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury LLP
2013 May Be Bay Area’s Best Year for Commercial Building
November 20, 2013 —
CDJ STAFFA tech boom has resulted in something of a commercial building boom for the Bay Area. The region will see about $6 billion in commercial construction projects during 2013. This is better than the totals for 2012, 2011, and 2009. During that period, however, 2010 set a record for the area with $6 billion of construction. Some estimates see 2013 beating that with as much as $6.7 billion in construction by year’s end.
The surge has been attributed to job creation. One Bay-area company, Infoblox, moved into a new office complex, after extensive renovation. The company had 250 employees and now has room to expand to 500 employees.
But 2014 could be even better. Apple is about to begin construction of its new campus, which is expected to cost the company $5 billion.
Read the court decisionRead the full story...Reprinted courtesy of
“Wait! Do You Have All Your Ducks in a Row?” Filing of a Certificate of Merit in Conjunction With a Complaint
January 13, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Barrett v. Berry Contr. L.P., No. 13-18-00498-CV, 2019 Tex. LEXIS 8811, the Thirteenth District Court of Appeals of Texas considered, among other things, the procedural timing requirements of filing a certificate of merit in conjunction with a complaint. The court concluded that the proper reading of the statute requires a plaintiff to file a certificate of merit with the first complaint naming the defendant as a party.
In Barrett, after sustaining injuries while working at a refinery, David Barrett (Barrett) filed suit against Berry Contracting, LP and Elite Piping & Civil, Ltd. on July 6, 2016. In Barrett’s first amended complaint, which he filed on August 23, 2016, Barrett added Govind Development, LLC (Govind) as another defendant. Barrett subsequently filed a second amended complaint (omitting Govind) and, on December 27, 2017, shortly before the statute of limitations ran, a third amended complaint (reasserting claims against Govind). On January 28, 2018, after the statute of limitations period ran, Barrett filed a certificate of merit. Govind filed a motion to dismiss the claim, asserting that Barrett violated the statute that required a certificate of merit to be filed with the complaint, Tex. Civ. Prac & Rem. Code §150.002.
Tex. Civ. Prac. & Rem. Code §150.002(a) states,
In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, a claimant shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect or registered professional land surveyor…
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Insurer's Attempt to Strike Experts in Collapse Case Fails
February 03, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's efforts to exclude two of the insured's experts in a collapse case were unsuccessful. Hudon Specialty Ins. Co. v. Talex Enterprises, LLC, 2019 U.S. Dist. LEXIS 150148 (S.D. Miss. Sept. 4, 2019).
The insureds' building collapsed. The remaining portions of the building required immediate stabilization. The insureds hired Mr. Laird, an engineer, to prevent further property destruction. The insured designated Mr. Laird as a non-retained expert for trial. Mr. Laird's report claimed that the collapse was caused because the building had been re-roofed many times without removal of the degraded underlying roofing materials, thereby adding additional weight to the roof structure.
The insureds also designated Steve Cox as a non-retained expert. Mr. Cox was an architect who owned property neighboring the building that collapsed. He opined that the building collapsed because of the condition of very old mortar and not because of water standing on the building roof or because of roof repairs.
Hudson sought to strike these two experts because their opinions were inconsistent with the admitted facts. A document produced by the insureds stated that a large amount of rainwater had collected on the roof and the weight of the rainfall was the proximate cause of the collapse. Hudson claimed that this statement qualified as a judicial admission, removing the question of causation from contention. The court disagreed that the statement was a judicial admission because it did not form any part of the pleadings. The statement may have been an evidentiary admission that could be controverted or explained by the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
OSHA Issues COVID-19 Guidance for Construction Industry
July 13, 2020 —
Garret Murai - California Construction Law BlogThis past month, after remaining relatively quiet following the coronavirus outbreak, OSHA began issuing industry-specific guidance on how to deal with the coronavirus in the workplace.
Until this month, the only construction industry specific guidance issued by OSHA was an OSHA Alert entitled COVID-19 Guidance for the Construction Workforce, a one page document providing little more guidance than that workers should stay home if sick, wear masks and frequently wash hands to prevent spreading and catching the coronavirus, and to sanitize tools and work areas.
Early this month, OSHA issued more comprehensive guidance for the construction industry. The guidance, as noted in the preface by OSHA is simply guidance, “is not a standard or regulation” and “creates no legal obligations. The guidance supplements general guidance applicable to all workplaces issued earlier by OSHA.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Have the Feds Taken Over Arbitration?
September 25, 2023 —
Christopher G. Hill - Construction Law MusingsAll of us in construction have run into mandatory arbitration clauses in our contracts. These clauses are more or less desirable based upon the size of project and other factors that will provide a topic for another post here at Musings or in my class at Solo Practice University (and likely both).
In drafting and considering the usefulness of these clauses, make sure that you keep in mind that the Federal Arbitration Act applies to actions in federal court. In short, the FAA gives parties to a contract containing an arbitration clause the absolute right to a stay of a law suit pending arbitration.
While this seems obvious, a recent U. S. Supreme Court decision expanded the universe of people that can demand such a stay. In Arthur Andersen LLP v. Carlisle, et. al., the Court stated that any person who is allowed to enforce a contract under state law can obtain such a stay. In short, if a person can make an argument that they have some sort of right to enforce a contract’s terms, that person can get a stay, at least until a court says otherwise.
Read the court decisionRead the full story...Reprinted courtesy of