Prospective Additional Insureds May Be Obligated to Arbitrate Coverage Disputes
September 07, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesThe Court of Appeal closed out 2019 by ruling that an additional insured can be bound to the arbitration clause in a policy when a coverage dispute arises between that additional insured and the carrier. (Philadelphia Indemnity Ins. Co. v. SMG Holdings, Inc. (2019) 44 Cal. App. 5th 834, 837.)
In 2009, Future Farmers of America (“Future Farmers”) entered into a license agreement with SMG Holdings Incorporated (“SMG”) to use the Fresno Convention Center. As part of the agreement, Future Farmers was required to secure comprehensive general liability (“CGL”) coverage and name SMG and the City of Fresno as additional insureds (“AI”) on its policies.
Future Farmers purchased a general liability policy from Plaintiff Philadelphia Indemnity Insurance Company (“Philadelphia”). Neither SMG nor the City of Fresno were added as AIs, but the policy contained a “deluxe endorsement” which extended coverage to lessors of premises for “liability arising out of the ownership, maintenance or use of that part of the premises leased or rented” to the named insured. The policy also contained an endorsement that extended coverage where required by a written contract for liability due to the negligence of the named insured. Philadelphia’s policy also stated that if the insurance company and insured “do not agree whether coverage is provided . . . for a claim made against the insured, then either party may make a written demand for arbitration.”
A patron to Future Farmer’s event at the Fresno Convention Center was seriously injured after he tripped over a pothole in the parking lot and hit his head. He sued both Fresno and SMG. In turn, Fresno and SMG tendered their defense to Philadelphia. Philadelphia denied coverage finding that the incident did not arise out of Future Farmer’s negligence, and that SMG had the sole responsibility for maintaining the parking lot. Consequently, Philadelphia concluded that neither Fresno nor SMG qualified “as an additional insured under the policy” for the injury in the parking lot.
The coverage dispute continued, and in 2016, Philadelphia issued a demand for arbitration which was rejected by SMG. Philadelphia then petitioned the state court to compel arbitration arguing that SMG could not avoid the burdens of the policy while seeking to obtain policy benefits. SMG used Philadelphia’s conclusion that it did not qualify as an AI under the policy to argue that Philadelphia was “estopped from demanding arbitration”. In other words, SMG argued that it could not be held to the burdens of the policy without being provided with the benefits of the policy.
The trial court sided with SMG finding that there was no arbitration agreement between the parties. The court noted that while third party beneficiaries can be compelled to arbitration there was no evidence that applied here, and Philadelphia could not maintain its inconsistent positions on the policy as its respects SMG.
Disagreeing with the trial court, the Court of Appeal concluded that SMG was a third-party beneficiary of the policy. The AI obligations in the license agreement and the deluxe endorsement in the Philadelphia policy collectively establish an intended beneficiary status. The Court saw SMG’s tender to Philadelphia as an acknowledgement of that status.
Relatedly, the Court found that SMG’s tender to Philadelphia – its demand for policy benefits – equitably estopped them from avoiding the burdens of the policy. The Court stated it defied logic to require a named insured to arbitrate coverage disputes but free an unnamed insured demanding policy coverage from the same requirement. Conversely, the Court found no inconsistency in Philadelphia’s denial of coverage to SMG and its subsequent demand for arbitration. Philadelphia did not outright reject SMG’s status as a potential insured, but rather concluded that there was no coverage because the injury occurred in the parking lot. In other words, the coverage determination turned on the circumstances of the injury not SMG’s status under the policy.
In short, the Court concluded that the potential insured takes the good with the bad. If one seeks to claim coverage as an additional insured, they can be subject to the restrictions of the policy including arbitration clauses even if they did not purchase the policy.
Securing additional insurance has become increasingly more difficult and limited over the years, and this holding presents yet another hurdle to attaining AI coverage. For those seeking coverage, it is important to note that the Court’s ruling may have turned out differently had the carrier outright denied SMG’s AI status, rather than concluding that the injury was not covered.
Your insurance scenario may vary from the case discussed above. Please contact legal counsel before making any decisions. BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 —
Shaun McParland BaldwinThe Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Reverses Summary Judgment Award to Insurer on Hurricane Damage Claim
December 18, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit reversed the district court's grant of summary judgment to the insurer on a property damage claim arising from Hurricane Harvey. Advanced Indicator and Manufacturing, Inc. v. Acadia Ins. Co., 50 F.4th 469 (2022).
After Hurricane Harvey struck southern Texas in 2017, Advanced submitted a claim to Acadia for damage to its building that it claimed was caused by the hurricane's winds. Acadia sent an adjuster, Nick Warren, as well as an engineer, Jason Watson. Watson determined that pre-existing conditions - including ongoing leaks from deterioration and poor workmanship - caused the damage, rather than winds from Hurricane Harvey. Warren adopted these conclusions in his recommendations to Acadia. Acadia denied Advanced's claim based on these reports.
Advanced sued Acadia, alleging breach of contract and bad faith. Advanced filed a motion to remand to state court which was denied. Acadia moved for summary judgment arguing that it did not breach the policy and that Advanced could not segregate any damages caused by hurricane from pre-existing damage. The district court granted Acadia's motion, finding that Acadia's denial of Advanced's claim was based on "extensive consideration of the evidence." Further, Advanced failed to carry its burden of showing that covered and non-covered damages could be segregated as required by Texas's concurrent causation doctrine. Finally, the bad faith claim was dismissed because there was no breach of contract.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Duty to Defend Under Pollution Policy
February 11, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found there was no duty to defend or indemnify under a pollution policy for claims arising from a building fire. URS Corp. v. Zurich Am Ins. Co., 2014 N.Y. Misc. LEXIS 222 (N.Y. Sup. Ct. Jan. 16, 2014).
Two firemen were killed while fighting a fire at the Deutsch Bank building in New York City. The owner of the building, URS, was sued by the estates of the two deceased firemen and other firemen who were injured by the fire.
URS was an additional insured under a contractors pollution liability policy issued by Hudson Specialty Insurance Company. The policy promised to pay for damages to the insured "if the damages result from a pollution condition." "Pollution condition" was defined as "the discharge, dispersal, release or escape of smoke, vapors, fumes, acids, alkalis, toxic chemicals, [etc.]" The policy explicitly noted that it did not provide commercial general liability coverage. Hudson denied coverage and URS sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contractor Sentenced to Seven Years for Embezzling $3 Million
July 20, 2020 —
Garret Murai - California Construction Law BlogMichael Medeiros was not a good guy. Ok, on a scale of 1 to 10, maybe not a 9 or 10 (when you’re including guys like Charles Manson), but a solid 6 or 7 at least.
The next case, People v. Medeiros, Case No. A155648, 1st District Court of Appeals (March 26, 2020), is less important for its legal holding than as a reminder that while most legal disputes on construction projects end up with one party owing the other party money, sometimes, when a party’s conduct has been really bad, it can end in a loss of liberty (i.e., jail time) as well.
People v. Medeiros
Medeiros was a painting contractor operating under the name Professional Painting Company, Inc. In the early 1990s, Medeiros met Susan Lambert, who served as the property manager for a homeowners’ association, Woodlake Association, in Hayward, California.
Lambert was an alcoholic. Following a series of surgeries in 2005 and 2007 she became addicted to opiates as well. She also had a gambling problem. As a result, Lambert regularly found herself in financial difficulty.
And this is where Lambert and Medeiros found that they shared common ground. At some point, Medeiros confided to Lambert that he was having cash flow and tax problems.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Condo Developers Buy in Washington despite Construction Defect Litigation
October 22, 2014 —
Beverley BevenFlorez-CDJ STAFFMarc Stiles writing for Puget Sound Business Journal stated that “[t]he belief that contractors have been scared off by the legal liabilities that come with [condo] projects doesn't seem to hold water.” He interviewed Suzi Morris, of Lowe Enterprises, who plans on building a new condo tower in Seattle this November.
Morris stated that they didn’t have any problems getting construction bids for the 24-story tower. According to the Puget Sound Business Journal, “The development team is trying to head off construction defect claims by planning and documenting with photos their work.”
Stiles did admit that an unnamed “source in Seattle who consults on condo projects knows of two large general contracting companies that won't bid on condo projects because of” potential construction defect litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Toronto Contractor Bondfield Wins Court Protection as Project Woes Mount
May 27, 2019 —
Scott Van Voorhis - Engineering News-RecordA Toronto area contractor at the center of a series of delays to major projects in Ontario, including a $139-million hospital expansion, has won court protection from its creditors. The Ontario Superior Court earlier this month granted Bondfield Construction Co.’s application for protection, court records show.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENR
The ARC and The Covenants
May 30, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Mike Collignon. Mike is a co-founder of the Green Builder Coalition. The Green Builder® Coalition amplifies the voice of green builders and professionals to drive advocacy and education for more sustainable building practices.
As we start to see signs of a housing recovery, slow as it may be, I feel the industry is in a great position. All the effort put in by so many to improve our energy codes, green building programs & rating systems will finally be able to bear fruit. We can start to build homes that are much more environmentally responsible. Sure, we can have a lengthy debate about implementation and adoption rates, but you’ve got to walk before you can run. Unfortunately, I can see that progress getting shackled by an unexpected impediment: the architectural review committee (ARC; sometimes called “architectural committee” or “architectural control authority”) and the covenants of a homeowners’ association.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com