Statutory Time Limits for Construction Defects in Massachusetts
November 27, 2013 —
CDJ STAFFConstruction defect claims are governed by a section of the Massachusetts laws and allow for three years after the work was completed, unless the defect is “inherently unknowable,” according to a post by John Shaffer on the web site of his firm, Marcus, Errico, Emmer & Brooks, a New England law firm that specializes in condominium law. Those “inherently unknowable” defects fall into the six-year statute of repose.
If, for example, a roof doesn’t show “significant water leakage” until after the end of the statutory period, “the association is out of luck and the responsible parties are off the hook,” writes Mr. Shaffer. “Even if the association could prove conclusively that the roof was improperly constructed and caused significant damage, the association’s claim will be barred.”
One problem condominium associations can face is that defects in the earliest phases of building can sometimes become apparent while the developer still controls the board. “While a developer in control of a board has the same fiduciary obligation as owner-elected trustees to protect the association’s interests, it is probably safe to assume that few developers will be inclined to sue themselves.” Here, Mr. Shaffer notes that owners can join together and either “hasten the transition to owner control of the association” or “convince them to correct the identified deficiencies.”
Mr. Shaffer notes that some questions concerning the statute of repose haven’t been answered by the Massachusetts courts. He does assure readers that “developers will no doubt argue that the statute of limitations has expired on defects because the association discovered or ‘should have discovered’ their existence more than three years before the lawsuit was started.” He advises condominium associations to calculate “their filing deadlines as conservatively as possible.”
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Independent Third-Party Spoliation Of Evidence Claim
June 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesIn an earlier posting I discussed the difference between first-party spoliation of evidence and third-party spoliation of evidence.
There is NO independent cause of action for first-party spoliation of evidence because that can be dealt with directly in the underlying lawsuit. This deals with the assertion that an actual party to a lawsuit spoiled evidence.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
What You Need to Know to Protect the Project Against Defect Claims
October 28, 2024 —
Scott L. Baker - Los Angeles Litigation BlogIf a property owner claims there is a construction defect, that not only brings the project’s integrity into question but also your business’s reputation. So, how can you take steps to prevent these claims from causing such damage?
Here are three things to know before beginning a project to effectively protect it and
manage construction defect claims.
1. Documentation is key
California and Los Angeles County require certain permits and documents in order for a construction project to move forward. Los Angeles County
will also conduct plan checks to ensure everything is up to code. Detailed documentation will be important while making your plans.
However, keeping notes throughout every step of the project will also be essential. Documenting all aspects of the project helps you:
- Stay updated and aware of the project’s progress
- Proactively catch and handle issues that could result in disputes
- Create a record of evidence that can help manage defect claims
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
Rancosky Adopts Terletsky: Pennsylvania Supreme Court Sets Standard for Statutory Bad Faith Claims
September 28, 2017 —
John Anooshian & Sean Mahoney - White & Williams LLPEarlier today, in a case of first impression, the Pennsylvania Supreme Court adopted the Terletsky two-part test for proving a statutory “bad faith” claim under 42 Pa. C.S.A. § 8371, which requires that a plaintiff present “clear and convincing evidence (1) that the insurer did not have a reasonable basis for denying benefits under the policy and (2) that the insurer knew of or recklessly disregarded its lack of a reasonable basis.” Rancosky v. Washington National Insurance Company, No. 28 WAP 2016 (Pa. Sept. 28, 2017). The court further ruled that proof of an insurer’s “subjective motive of self-interest or ill-will,” while potentially probative of the second prong of the test, is not a requirement to prevail under § 8371. Evidence of an insurer’s “knowledge or reckless disregard for its lack of a reasonable basis” for denying a claim alone, according to the court, is sufficient even in cases seeking punitive damages.
Reprinted courtesy of
John Anooshian, Saxe Doernberger & Vita, P.C. and
Sean Mahoney, Saxe Doernberger & Vita, P.C.
Mr. Anooshian may be contacted at anooshianj@whiteandwilliams.com
Mr. Mahoney may be contacted at majoneys@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Exclaims “Enough!” To Homeowner Who Kept Raising Wrongful Foreclosure Claims
April 01, 2015 —
Krsto Mijanovic and Annette F. Mijanovic – Haight Brown & Bonesteel LLP“There are no free houses,” began the decision issued by the Court of Appeal on March 23, 2015 in Boyce v. T.D. Service Company (B255958). Examining three years of litigation in bankruptcy court, unlawful detainer court, and the superior court, and each of their respective appellate courts, the Court of Appeal held that the plaintiff’s wrongful foreclosure claims were barred by res judicata and collateral estoppel.
Plaintiff was a borrower who purchased a home subject to a deed of trust. After plaintiff defaulted on the loan, nonjudicial foreclosure proceedings were initiated. To avoid foreclosure, plaintiff engaged in a series of stall tactics, including filing an emergency bankruptcy petition, appealing the bankruptcy court’s decision to grant the trustee relief of stay, refusing to leave the property following the trustee’s sale thereby causing an unlawful detainer action to be filed, and appealing the granting of summary judgment in favor of the defendants in the unlawful detainer action. Once evicted, plaintiff sued all the entities involved in the foreclosure process for wrongful foreclosure, declaratory relief, violation of Unfair Practices Act, and quiet title. When the trial court sustained the defendants’ demurrers on the grounds of res judicata/collateral estoppel, plaintiff naturally appealed.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel LLP and
Annette F. Mijanovic, Haight Brown & Bonesteel LLP
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Ms. Mijanovic may be contacted at amijanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
In Midst of Construction Defect Lawsuit, City Center Seeks Refinancing
October 02, 2013 —
CDJ STAFFThe owners of the City Center complex in Las Vegas are going through with a refinancing of their $1.8 of debt while they still seek to demolish the Harmon Tower. The cost of building City Center was $8.5 billion, making it the most expensive development on the Las Vegas strip. Unfortunately for the owners, the Harmon Tower isn’t the only empty space in the complex.
MGM Resorts is currently in the midst of a construction defect lawsuit against the builder of the Harmon Tower. The judge in the case has given a go-ahead to tear down the building.
Read the court decisionRead the full story...Reprinted courtesy of
Governor Inslee’s Recent Vaccination Mandate Applies to Many Construction Contractors and their Workers
September 13, 2021 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCThis month Governor Jay Inslee enacted COVID vaccination requirements that apply to certain construction contractors and their workers in Washington state. Inslee’s vaccine proclamation becomes effective October 18, 2021 and requires construction contractors, subcontractors, and their workers to be fully vaccinated to perform work onsite on certain covered projects.
The following are types of covered projects where the vaccine mandate applies:
- State agencies: All contractors working at projects for Washington state agencies (including WSDOT, DES, DNR, etc.) if the work is required to be performed in person and onsite, regardless of the frequency or whether other workers are present. The vaccine mandate applies to indoor and outdoor settings and there is no exemption even if social distancing requirements can be met.
- Education/Higher Education/Child Care: All contractors performing work onsite for K-12, higher education (community colleges, technical colleges, and 4-year universities), child care and other facilities where students or persons receiving services are present. New and unoccupied projects are exempt but it does apply to public and private projects.
- Medical facilities: All contractors performing work at a “healthcare setting” where patients receiving care are present. “Healthcare setting” is defined as any public or private setting that is primarily used for the delivery of in-person health care services to people. “Healthcare setting” includes portions of a multi-use facility, but only the areas that are primarily used for the delivery of health care, such as a pharmacy within a grocery store. Additional information is on the state’s Q&A page.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
Vegas Hi-Rise Not Earthquake Safe
July 12, 2011 —
CDJ STAFFIf an earthquake hit Las Vegas, the Harmon Tower would not withstand it. A report from Weidlinger Associates told MGM Resorts that “in a code-level earthquake, using either the permitted or current code specified loads, it is likely that critical structural members in the tower will fail and become incapable of supporting gravity loads, leading to a partial or complete collapse of the tower.” The inspection came at the request of county officials, according to the article in Forbes.
According to Ronald Lynn, directory of the building division in the county’s development services division, “these deficiencies, in their current state, make the building uninhabitable.” The county is concerned about risks to adjacent buildings.
MGM Resorts is currently in litigation, separate from the stability issues, with Perini Corp., the builders of Harmon Tower.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of