“Other Insurance” and Indemnity Provisions Determine Which Insurer Must Cover
September 01, 2011 —
Tred R. Eyerly - Insurance Law HawaiiA policy’s “other insurance” clause and a contractual indemnity provision were at the root for determining which of two insurers had to cover for injuries at a construction site. Valley Forge Ins. Co. v. Zurich Am. Ins. Co., 2011 U.S.Dist. LEXIS 76061 (N.D. Calif. July 14, 2011).
Hathaway was the general contractor at a demolition and construction project. Hathaway was insured by Zurich. Reinhardt Roofing was the roofing subcontractor. Reinhardt was insured by Valley Forge under a policy which named Hathaway as an additional insured. The subcontract also required Reinhardt to indemnify Hathaway for acts or omissions arising from Reinhardt’s work unless Hathaway was solely negligent.
Four of Reinhardt’s workers were injured when a canopy roof on which they were working collapsed. At the time of the accident, Hathaway’s on-site supervisor was inspecting a gap in the canopy roof, but did not order Reinhardt’s workers to stop working.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Just Hanging Around”
August 14, 2023 —
Daniel Lund III - LexologyA subcontractor asserting a payment bond claim for “standby” time for its equipment on the Cline Avenue bridge project (over Indiana Harbor and Ship Canal in East Chicago, Indiana) received pushback from the payment bond surety.
In fact, the duration of the standby time occurred after the surety’s principal, the general contractor, had been placed in default and terminated on the general contract. According to the surety: “After termination of the contract… it is impossible for labor, materials, and equipment to have been furnished for use in performing the terminated contract.” The surety filed a motion for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Don’t Let Construction Problems Become Construction Disputes (guest post)
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaTo start our week off right, today we have another important article from guest blogger Christopher G. Hill, LEED AP. Chris is a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. He authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals. His practice concentrates on mechanic’s liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals. [His blog was also one of the first construction law blogs I found and followed, even if he is a Duke alum!] Take it away, Chris!
First and foremost, thanks to Melissa for inviting me back to post here at her great blog. She continues to invite me back despite my being a Blue Devil (and I try not to hold her Tar Heel status against her).
So much of discussion relating to construction law and construction lawyers centers on the litigation of disputes. This discussion comes in many forms from avoidance of such litigation through the early intervention of good counsel prior to getting into a project to what sort of resolution mechanism to use. Another branch of this discussion is essentially the right way to pursue your claim (or as some may read it start the dispute ball rolling). Sometimes a payment bond claim is the best method while others a straight up contractual suit is the best way to go.
Of course, all of this discussion presumes that there will be disputes. While I agree to some degree that in the Murphy’s Law riddled world of commercial construction, problems will arise. These problems need not rise to the level of a dispute that requires outside (read court or arbitrator) intervention. A few tips that are easy to write, but admittedly hard to practice at times can hopefully keep problems from blossoming into disputes. I’ve listed three big ones here:
1.Use “in house counsel.” Yes, I know that most of you engineers, architects, commercial general contractors and subcontractors out there aren’t big enough to either want or need a full time attorney on the payroll. What I mean by this is that when problems occur (or preferably before doing so), give your friendly local construction lawyer a call. As I learned from my dad, an ounce of prevention and all that. That 10 minute phone call may help avoid many hours of time and bills from your attorney later down the road.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
The U.S. Tenth Circuit Court of Appeals Rules on Greystone
November 18, 2011 —
Derek J. Lindenschmidt, Higgins, Hopkins, McLain & Roswell, LLCOn November 1, 2011, the Tenth Circuit Court of Appeals ruled on the certified question of whether property damage caused by a subcontractor’s faulty workmanship is an “occurrence” for purposes of a commercial general liability (CGL) insurance policy. In Greystone Const., Inc. v. National Fire & Marine Ins. Co., No. 09-1412 (10th Cir. Nov. 1, 2011), the Tenth Circuit determined that because damage to property caused by poor workmanship is generally neither expected nor intended, it may qualify under Colorado law as an occurrence and liability coverage should apply. Id. at 2.
The short history of the Greystone case is as follows. In Greystone Const., Inc. v. National Fire & Marine Ins. Co., 649 F. Supp. 2d 1213 (D. Colo. 2009), two contractors and one of their insurers brought an action against a second insurer after the second insurer refused to fund the contractors’ defense in construction defect actions brought by separate homeowners. Id. at 1215. The U.S. District Court for the District of Colorado, relying on General Sec. Indem. Co. of Arizona v. Mountain States Mut. Cas. Co., 205 P.3d 529 (Colo. App. 2009), granted summary judgment in favor of the second insurer on the basis that the homeowners’ complaints did not allege accidents that would trigger covered occurrences under the second insurer’s policies. Id. at 1220. Notably, the Greystone, General Security, and other similar decisions prompted the Colorado General Assembly to enact C.R.S. § 13-20-808, which was designed to provide guidance for courts interpreting perceived coverage conflicts between insurance policy provisions and exclusions. The statute requires courts to construe insurance policies to favor coverage if reasonably and objectively possible. C.R.S. § 13-20-808(5).
The Tenth Circuit began its analysis by determining whether C.R.S. § 13-20-808, which defines the term “accident” for purposes of Colorado insurance law, would have a retroactive effect, and thereby settle the question before the court. The Tenth Circuit gave consideration to several Colorado district court orders issued since the enactment of C.R.S. § 13-20-808 which have suggested that the statute does not apply retroactively, including Martinez v. Mike Wells Constr., No. 09cv227 (Colo. Dist. Ct., Mar. 1, 2011), and Colo. Pool. Sys., Inv. V. Scottsdale Ins. Co., No. 09cv836 (Colo. Dist. Ct., Oct. 4, 2010). The Tenth Circuit also attempted to ascertain the General Assembly’s intent behind the term “all insurance policies currently in existence...” Greystone, No. 09-1412, at 12. The Tenth Circuit determined that the General Assembly would have more clearly stated its intentions for the term if it was supposed to apply retroactively to expired policies, rather than those still running. Id. at 12-13. Ultimately, the Tenth Circuit decided that C.R.S. § 13-20-808 did not apply retroactively, but noted that “the retrospective application of the statute is not necessarily unconstitutional.” Id. at 9, 11-14. As such, the Tenth Circuit advised that it was required to decide the question presented in the appeal under the principles of Colorado insurance law. Id. at 15.
Read the full story…
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. Lindenschmidt can be contacted at lindenschmidt@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Appellate Court Holds Insurers May Suffer Consequences of Delayed Payment of Energy Company Property and Business Interruption Claims
March 16, 2020 —
Syed S. Ahmad & Geoffrey B. Fehling - Hunton Andrews KurthA New York appellate court recently held that renewable bio-diesel fuel manufacturer BioEnergy Development Group LLC may pursue tens of millions of dollars in damages from its insurers under two all-risk insurance policies, including amounts in excess of the policy limits, where the insurers refused to pay claims in a timely manner.
BioEnergy purchased two all-risk property policies from Lloyd’s to provide coverage for its manufacturing plant in Memphis, Tennessee. A fire destroyed the Memphis plant in March 2016, eliminating BioEnergy’s production capacity and sole source of revenue. BioEnergy made claims under the policies and sought to rebuild its plant. The insurers acknowledged coverage and eventually made approximately $8 million in interim payments, but the parties disagreed over the value of the total property damage claim, which BioEnergy contended was in excess of $24 million. The disputed claim was submitted to appraisal, which resulted in the insurers agreeing to pay the full business interruption limit of $15.1 million.
The insurers filed a declaratory judgment lawsuit, however, seeking to limit BioEnergy’s recovery to the policy limits of $15.1 million. BioEnergy alleged that the insurers failed to make interim payments in a timely manner after the fire and, as a result, the company suffered increased losses because it could not rebuild without the insurance proceeds. BioEnergy sought actual and consequential damages, plus attorneys’ fees, arising from the delayed payments, including payment of its business interruption losses in excess of the policy limits.
Reprinted courtesy of
Syed S. Ahmad, Hunton Andrews Kurth and
Geoffrey B. Fehling, Hunton Andrews Kurth
Mr. Ahmad may be contacted at sahmad@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
With Wildfires at a Peak, “Firetech” Is Joining Smart City Lineups
October 21, 2024 —
James P. Bobotek - Gravel2Gavel Construction & Real Estate Law BlogThe
threat of extreme wildfires has doubled in the past 20 years, with almost 20,000 fires blazing across the United States in 2024 alone. These high-intensity fires can be deadly, expensive, and create lingering health and environmental consequences. While we are used to seeing firefighters on the frontlines, researchers hope that next-generation smart technology, augmented by artificial intelligence (AI), will also play a key role in battling these conflagrations. Many municipalities, particularly those near wildfire-prone forests, are beginning to incorporate fire-focused advances (or “firetech”) into their smart city ecosystems.
“Smart cities” are urban centers enhanced by utilities, emergency services,
traffic signals and more that are linked through information and communications technology. Though the concept can spark cybersecurity-related concerns, many locales are gradually implementing many different kinds of smart tech. Following the 2023 wildfire that devastated Maui, for example, Hawaii installed a network of
cloud-based fire and wind sensors that use AI to detect wildfires in real time. Smart tools like these can aid in predicting and discovering fires, streamlining emergency alert protocols, calculating vital analytics and improving firefighter safety. The National Fire Protection Association (NFPA) is
actively studying these innovations, particularly in terms of environmental (smart buildings or robotics), operational (communications) and personnel (PPE sensors or biometrics). Below are a few of the key technologies to watch in this emerging field:
- Smart Sensors. A total of 80 sensors (64 wildfire sensors and 16 wind sensors) were placed throughout Hawaii starting in March of 2024. Attached to existing utility poles, they detect heat in the air, and then engage AI and smart learning to distinguish smoke particles and gases produced by fires from those commonly found in Hawaii’s atmosphere—such as volcanic ash and ocean salt. Positioned in “strings,” the sensors “talk” to each other and send text messages to officials when they find a problem.
Read the court decisionRead the full story...Reprinted courtesy of
James P. Bobotek, PillsburyMr. Bobotek may be contacted at
james.bobotek@pillsburylaw.com
Construction Contract Basics: No Damages for Delay
May 06, 2024 —
Christopher G. Hill - Construction Law MusingsAfter WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts. In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses. In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the owner or general contractor, is an extension of time to complete the work.
These types of clauses generally make it impossible for a subcontractor (if found in a Subcontract) or Contractor (if found in a Prime Contract) that is delayed through no fault of its own to recover any damages relating to the expenses that are inevitably caused by such delays. Such expenses/damages could include additional supervisory time (including more high-dollar superintendent payments), acceleration costs, demobilization/mobilization costs, and other related expenses. These can add up to real money. Couple that with the inevitable liquidated damages or delay damages that will occur should a contractor or subcontractor cause any delay, and this becomes a very one-sided proposition.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
"On Second Thought"
October 28, 2024 —
Daniel Lund III - LexologyRehearing requests are seldom granted by courts, and when they are, there’s usually something uniquely compelling in the request and the granting.
So is the case in a matter involving monies deposited in the registry of the federal court in New Orleans related to work performed on cleanup after Hurricanes Maria and Irma in the U.S. Virgin Islands. The party depositing monies – which represented subcontract sums paid to it by the general contractor – held back several hundred thousand dollars based on withholding provisions in the various contracts in play. The Court was tasked with evaluating not only a pay-when-paid provision in the subcontract of the claiming party, but also incorporation of the terms of a higher tiered contract which allowed for the withholding.
The Court initially granted summary judgment allowing the monies to be withheld. However, on request for rehearing, it was pointed up that while monies could be retained for purposes of covering attorney’s fees and costs related to litigation initiated by the plaintiff subcontractor’s vendors, there was a particular process for that withholding – and an assertion that the process was not followed.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com