Negligent Construction an Occurrence Says Ninth Circuit
June 30, 2011 —
CDJ STAFFOne June 27, the US Court of Appeals has rejected an appeal from Mid-Continent Casualty Company. Mid-Continent had appealed a summary judgment granted to Titan Construction Company.
Titan Construction had built condominiums for the Williamsburg Condominium Association, which later filed a construction defect lawsuit against Titan and other defendants. Titan settled with the developer, Kennydale, assigning its rights against Mid-Continent to Kennydale. Mid-Continent filed suit, claiming that “it had no obligation to indemnify or defend Titan, Kennydale, or various other defendants.” The district court found in favor of Mid-Continent, granting a summary judgment, concluding that Titan’s insurance covered “occurrences,” and none had taken place.
On appeal, the court found that the negligent construction of the condominiums constituted an “occurrence” The case was remanded and the district court this time found in favor of Titan, “concluding that Mid-Continent failed to raise a triable issue as to the applicability of the remaining policy exclusions.
The Ninth Circuit Court of Appeals has now affirmed that decision and Titan’s summary judgment stands.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Bill Would Bring Changes to Construction Defects
February 21, 2013 —
CDJ STAFFIf Nevada Senate Republicans get there way, changes are afoot for construction defect law in Nevada. Senate Minority Leader Michael Roberson has introduced a bill that, according to the Las Vegas Sun, “redefines what constitutes a construction defect, reduces the time in which lawsuits can be filed, and removed automatic awarding of attorney fees.” Roberson notes that over the last six years, construction defect claims have more than tripled.
Read the court decisionRead the full story...Reprinted courtesy of
Florida District Court Finds That “Unrelated” Design Errors Sufficient to Trigger “Related Claims” Provision in Architects & Engineers Policy
March 02, 2020 —
Jason Taylor - Traub LiebermanMost professional liability polices include some form of a “related claims” provision that generally provides where two or more claims or wrongful acts are causally or logically related, they will be deemed to constitute a single claim. Importantly, these provisions typically provide that those “claims” are then deemed to have been “first made” at the time the first claim or act was committed for purposes of the policy’s claims-made and reporting requirements. Understandably, these provisions provide insurers and insureds with some clarity over the number and timing of claims that could involve multiple errors or omissions, and potentially aggregate all related claims or acts into a single policy period. While reasonable in principle, application of such provisions, especially involving large scale design and construction projects, is not always so easy.
Nova Southeastern University, Inc. v. Continental Cas. Co., 18-cv-61842 (S.D. Fla. Dec. 27, 2019), involved such an insurance coverage dispute with a design project gone wrong. DeRose Design Consultants, Inc. (“DeRose”) was hired as a structural engineer to design “ice tanks” to store and chill water for an energy efficient air conditioning facility constructed on the campus of Nova Southeastern University (“NSU”). An early water test on one of the tanks determined the walls of the ice tank deflected, leaked, and cracked when the tank was filled with water. DeRose later discovered that the problems with the ice tank were caused by a structural design error.
The first errors were discovered in early 2009, and reported under DeRose’s professional liability policy with Evanston. DeRose then created a remedial design to repair the tanks, which involved strengthening repairs. Additional leaking and an early indication of corrosion involving the Remedial Design arose as early as October 25, 2009. Several field investigation reports were prepared in 2011 and 2012 confirming these issues with the Remedial Design. A third report in February 2012, however, identified a new error involving the concrete slab under the ice tanks also designed by DeRose. The third report concluded that the concreate slab was overstressed and could not handle the loads of the ice tanks. The report also concluded, however, that the design defects in the concrete slab were “unrelated” to the original design defect of the ice tank walls or Remedial Design.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Eighth Circuit Affirms Finding of Bad Faith, Award of Costs and Prejudgment Interest
October 25, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Eighth Circuit affirmed the district court's finding of bad faith and award to the insured of taxable costs and prejudgment interest. Selective Ins. Co. v. Sela, 2021 U.S. App. LEXIS 26062 (8th Cir. Aug. 30, 2021).
The insured suffered two hail storms that damaged his home. In 2010, the first storm caused over half a million dollars in loss. Before submitting a claim to his original insurer or beginning any repairs, the insured secured a new policy with Selective. The policy did not exclude pre-existing damage, it did preclude coverage if the insured "willfully and with intent to defraud, concealed or misrepresented any material fact or circumstance relating to the insurance."
Before issuing the policy, Selective appraised the property and assigned a $1.6 million value to the home. The insured then filed a claim with his original insurer and received $510,787.23 for actual cash value of his loss. Neither the terms of this settlement nor this new policy with Selective required the insured to repair all of the 2010 damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Consider Short-Term Lease Workouts For Commercial Tenants
August 17, 2020 —
Steven Ostrow, C. Jason Kim & Patrick Haggerty - White and WilliamsThe COVID-19 pandemic is adversely affecting commercial real estate as it continues to wreak havoc in industries throughout the economy. For many years, the primary declining CRE sector has been brick and mortar retail stores. However, the retail sector is no longer suffering alone, as the COVID-19 outbreak is hurting most other CRE sectors: office, hospitality, multifamily, restaurant, personal services, entertainment and construction.
Federal, state and local governments have ordered business shutdowns and social and travel restrictions limiting most social and commercial activities. As a result, commercial tenants throughout the country are going out of business, temporarily closing, curtailing operations, laying off employees and suffering sharply declining revenues.
Short-Term Leasing Workouts of Tenant Defaults
Thousands of tenants are partially operating or temporarily closed and lack sufficient cash flow or access to additional working capital to pay some or all of their rent. How should a landlord address a distressed tenant's default and request for rent relief, taking into account the landlord's own responsibilities to pay maintenance costs, real estate taxes and debt service on the property?
Reprinted courtesy of White and Williams attorneys
Steven Ostrow,
C. Jason Kim and
Patrick Haggerty
Mr. Ostrow may be contacted at ostrows@whiteandwilliams.com
Mr. Kim may be contacted at kimcj@whiteandwilliams.com
Mr. Haggerty may be contacted at haggertyp@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
HHMR is pleased to announce that David McLain has been selected as a 2020 Super Lawyer
June 29, 2020 —
David M. McLain – Colorado Construction LitigationDavid McLain is a founding member of Higgins, Hopkins, McLain & Roswell. Mr. McLain has over 22 years of experience and is well known for his work in the defense of the construction industry, particularly in the area of construction defect litigation. He is a member of the Executive Committee of the CLM Claims College - School of Construction, which is the premier course for insurance, industry, and legal professionals. Law Week Colorado recently named Mr. McLain as the 2019 People’s Choice for Best Construction Defects Lawyer for Defendants.
HHMR is highly regarded for its expertise in construction law and the litigation of construction-related claims, including the defense of large and complex construction defect matters. Our attorneys provide exceptional service to individuals, business owners, and Fortune 500 companies. The firm is experienced in providing legal support throughout trials and alternative dispute resolution such as mediations and arbitrations.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
No Coverage For Construction Defects Under Alabama Law
September 14, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found there was no coverage for alleged defects caused by the insured homebuilder. Canal Indem. Co. v. Carbin, 2017 U.S. Dist. LEXIS 126662 (N.D. Ala. Aug. 10, 2017).
Carbin Construction filed suit against Aaron and Sherry Ford, asserting mechanic's and materialman's liens, and seeking sums allegedly due for work performed under a construction contract. The Fords filed a counterclaim, alleging that over a year had passed since Carbin was to complete construction, and that Carbin refused to do any further work on the house until he was paid an additional $11,771.43. The Fords further contended that Carbin had walked off the job after receiving 96.6 percent of the money owed under the contract although only 88 percent of the construction work had been completed. Carbin tendered the counterclaim to Canal. Canal then filed suit seeking a declaration that it had no duty to defend.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Eight Ways to Protect a Construction Company Before a Claim Is Filed
November 04, 2019 —
Mary Bacon - Construction ExecutiveClaims are inevitable in the construction industry. They can take on a life of their own and come with the burden of legal fees, wasted executive time and a possible judgment. Too often the only winners are the lawyers.
TIPS FOR PROTECTING MANAGEMENT AND THE BUSINESS BEFORE A CLAIM IS FILED
- Respect the business entity’s corporate structure. First and most importantly, respect the business entity’s corporate form. Legal entities have certain formalities like filing an annual list of officers, maintaining separate bank accounts, conducting certain meetings and following bylaws, etc. Respect these formalities. Failure to follow them exposes the owner to personal liability for company debts. And while a business claim has the potential to wipe out a business, owners should not risk having their personal assets on the line as well.
- Get a good contract. In most instances, a contract governs what happens and who is responsible for payment associated when a certain issue or dispute arises. A clear, well-written contract can often avoid a dispute or liability for a dispute. Actively participate in the contract negotiation and drafting process to make sure each party’s role and responsibilities are clearly accounted for.
- Make friends with clients. While it is true that “business is business,” people are often fairer and more willing to work towards a solution for people they are friends with. In most cases, friends will help friends in ways that people would not help mere business associates. When encountering a problem on a job, a friend may be willing to help achieve a more favorable outcome.
Reprinted courtesy of
Mary Bacon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Bacon may be contacted at
mbacon@spencerfane.com