Construction Delays: Which Method Should Be Used to Calculate Delay?
July 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf you need to prove and allocate construction project delays, you should engage a scheduling consultant qualified with CPM (critical path method) analysis. You should also engage counsel to assist in preserving your rights, as well as presenting and maximing your arguments for delay.
There are numerous methodologies used to quantify and allocate delay. You want to discuss the most effective analysis for your case and facts including whether you want/should use a forward-looking prospective analysis or a backward-looking retrospective analysis that factors in as-built data. In doing so, you want to make sure you understand the pros and cons of each methodology including the bases to attack the methodology that will be subject to cross-examination. The five primary CPM methodologies are as follows:
- As-Planned Versus As-Built. This methodology compares the as-planned baseline schedule to an as-built schedule reflecting progress to assign delay. An as-built schedule that reflects progress includes actual start dates, finish dates, and durations. The actual dates and durations are compared with the as-planned dates and durations on the baseline schedule to determine delay. Under this methodology, the delay impact is determined retrospectively.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
How Philadelphia I-95 Span Destroyed by Fire Reopened in Just 12 Days
July 24, 2023 —
James Leggate - Engineering News-RecordLess than two weeks after a tanker truck crash and fire destroyed an Interstate-95 bridge in northeast Philadelphia, the highway reopened to traffic on a temporary road surface June 23. The hastened work to reopen the highway, which has an average daily traffic count of nearly 160,000 vehicles, including about 13,000 trucks, was the result of collaboration between contractors, material suppliers and union workers with local, state and federal officials, Pennsylvania Gov. Josh Shapiro (D) said.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Parking Garage Collapse May Be Due to Construction Defect
November 07, 2012 —
CDJ STAFFA parking garage under construction at the Doral campus of Miami Dade College collapsed on October 9. Experts state that the collapse may have been due to errors in the construction process, either in the fabrication of the pre-cast components or in their assembly. The Bradenton Herald quotes Mark Santos, a structural engineer, who “would look at erection procedures – that’s probably the one question to ask first.”
During the failure, floors separated from the south wall of the structure. The contractor responsible for the garage, Ajax Building Corp, said there was “no indication of any potential cause.”
Read the court decisionRead the full story...Reprinted courtesy of
Effective October 1, 2019, Florida General Contractors Have a Statutory Right to Recovery of Attorney Fees Against a Defaulted Subcontractor’s Surety
July 01, 2019 —
Warren E. Friedman - Peckar & Abramson, P.C.Florida contractors will soon have a level playing field, at least related to the right to recovery of attorney fees in certain circumstances. Effective October 1, 2019, the Florida statute by which legal fees may be recovered from insurers and sureties was amended to expressly afford that right to contractors.
Florida’s Insurance statute, Chapter 627, affords a right to recovery of attorney fees when a judgment is obtained against an insurer and in favor of any insured pursuant to a policy or contract executed by the insurer. See Fla. Stat. § 627.428. In the construction context, the Florida Legislature has also applied this right to the recovery of attorney fees from sureties, for example in circumstances where suit is brought against a surety under a payment or performance bond. See Fla. Stat. § 627.756.
But there was an oddity to this statute – it specifically provided this right for “owners” and “subcontractors”, but “contractors” were skipped over. For as long as Section 627.756, Florida Statutes has been on the books, the right to recovery of attorney fees against a surety under a payment or performance bond was only afforded to owners, subcontractors, laborers, and materialmen. Specifically, since at least 1977, Section 627.756, Florida Statutes substantially provided as follows (emphasis added):
Section 627.428 applies to suits brought by
owners, subcontractors, laborers, and materialmen against a surety insurer under payment or performance bonds written by the insurer under the laws of this state to indemnify against pecuniary loss by breach of a building or construction contract. Owners, subcontractors, laborers, and materialmen shall be deemed to be insureds or beneficiaries for the purposes of this section.
Read the court decisionRead the full story...Reprinted courtesy of
Warren E. Friedman - Peckar & Abramson, P.C.Mr. Friedman may be contacted at
wfriedman@pecklaw.com
How to Build a Coronavirus Hospital in Ten Days
April 20, 2020 —
Elaine Lee - Gravel2Gavel Construction & Real Estate Law BlogIf the coronavirus pandemic continues to spread in the United States as it has in other countries, drastic expansions of hospital and quarantine facility capacity are likely to be necessary. In the hard-hit Seattle area, several temporary facilities are already under construction, including a 200-bed temporary quarantine and isolation center built on a soccer field. China’s response to the initial outbreak in the city of Wuhan demonstrates how rapidly authorities can add capacity in an emergency.
As thousands of citizens became ill with COVID-19, China built two hospitals in Wuhan over the span of just days. Time-lapse videos such as this one show how remarkably quickly the hospitals were built. Construction on the Huoshenshan Hospital (shown in the prior linked video) began on January 23 and finished eight days later. A second hospital, Leishenshan Hospital, began construction on January 25 and finished 12 days later. Square footage information on both hospitals has been inconsistently reported, but Huoshenshan Hospital has a capacity for 1,000 beds, while Leishenshan Hospital has a capacity for 1,600 beds.
Read the court decisionRead the full story...Reprinted courtesy of
Elaine Lee, PillsburyMs. Lee may be contacted at
elaine.lee@pillsburylaw.com
In Hong Kong, You Can Find a Home Where the Buffalo Roam
September 17, 2014 —
Shai Oster – BloombergTo city dwellers worried about mice and rats, spare a thought for Hong Kongers confronting half-ton feral beasts.
A few miles from some of the most densely populated neighborhoods in the world, more than 1,000 cows and buffalo from abandoned farms roam the countryside. Development now is pushing them into harm’s way and onto roads.
Hong Kong represents an extreme example of the task many communities face of balancing conservation and growth. Wolves sniff near the suburbs of Paris, bears roam Lake Tahoe and moose stumble across the roads of Halifax. There’s a new word to describe how undomesticated animals adapt to man-made environments: synurbanization.
Read the court decisionRead the full story...Reprinted courtesy of
Shai Oster, BloombergShai Oster may be contacted at
soster@bloomberg.net
Nondelegable Duties
June 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you heard the expression “nondelegable duty”? The issue of a nondelegable duty comes into play when a party hires an independent contractor and the independent contractor commits negligence, primarily in the personal injury context. In other words, a plaintiff wants to hold a defendant liable for the injuries caused by the defendant’s independent contractor.
A nondelegable duty is one that “may be imposed by statute, contract, or the common law. In determining whether a duty is nondelegable, the question is whether the responsibility at issue is so important to the community that an employer should not be allowed to transfer it to a third party.” Garcia v. Southern Cleaning Service, Inc., 360 So.3d 1209, 1211 (Fla. 3d DCA 2023) (internal citation omitted).
When it comes to CONTRACTUAL duties:
[S]pecifically the principle that one who undertakes by contract to do for another a given thing cannot excuse himself to the other for a faulty performance by showing that he hired someone else to perform the task and that other person was the one at fault. In other words, where the contracting party makes it her or his duty to perform a task, that party cannot escape liability for the damage caused to the other contracting party by the negligence of independent contractors hired to carry out the task.
Gordon v. Sanders, 692 So.2d 939, 941 (Fla. 3d DCA 1997).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Part II: Key Provisions of School Facility Construction & Design Contracts
July 21, 2018 —
David R. Cook - Autry, Hall & Cook, LLPIn
Part I of this article, published in late April, we discussed the performance risk and time risk involved with construction and design contracts, and in Part II, we will cover cost risk and political risk.
Cost Risk
School budgets are limited for many reasons, and the construction budget is no exception. As a result, contracts should guard against unwarranted cost increases and claims. In the absence of a written change order signed by the appropriate officer, the contract should absolutely prohibit additional compensation for changes in the work. It should forbid claims for all events except those within the school authority’s sole control. Even for permitted claims, the contractor must provide written notice so that the authority might alleviate the problem and control its costs. To encourage the contractor to limit costs and claims, the contract could include a shared-savings clause, which grants an incentive payment for completion within the budget.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com