Construction Litigation Roundup: “I Never Had a Chance”
May 29, 2023 —
Daniel Lund III - Lexology“I never had a chance.”
Such was the plea of a general contractor to a Maryland federal court after having been terminated for failure to perform.
“The Agreement provides no express right to cure,” found the court, weighing in on the contractor’s wrongful termination claim. Indeed, the contract was also very clear on termination, allowing for termination for cause on numerous bases, including a common catchall: if the contractor “persistently fails to perform the provisions of this Agreement.”
In advance of the actual date of termination, the owner wrote to the contractor, in accordance with the contract: “Notice is also given that seven days from the date of this correspondence, [owner] will exercise its [termination] rights under Section 13.2.2.2 of the Contract." The communication from the owner contained no discussion of allowing the contractor an opportunity to cure its alleged default.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
The Quiet War Between California’s Charter Cities and the State’s Prevailing Wage Law
April 20, 2016 —
Garret Murai – California Construction Law BlogBehind the scenes a quiet war is raging.
A war pitting local sovereignty, on one hand, against a Depression-era law intended to help those working on state and local public works projects, on the other.
California’s Prevailing Wage Law
Beginning in 1929 and continuing through the late 1930s, the Great Depression is widely considered to be the longest, most widespread depression of the 20th century. In 1931, the federal government enacted the Davis-Bacon Act to help workers on federal construction projects. The Davis-Bacon Act, also known as the federal prevailing wage law, sets minimum wages that must be paid to workers on federal construction projects based on local “prevailing” wages. The law was designed to help curb the displacement of families by employers who were recruiting lower-wage workers from outside local areas.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
ConsensusDOCS Hits the Cloud
April 02, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed the ConsensusDOCS here at Musings on a few occasions. These relatively new form documents, endorsed by the AGC among other trade organizations, are a great counterpoint to the AIA documents that we all are more than familiar with and as construction attorneys and contractors have likely reviewed on numerous occasions.
Recently, these documents have joined the parade and have taken to the cloud. The folks at ConsensusDOCS made this move to ease the type of collaboration that I have discussed must occur on construction projects among the players. The use of the cloud based technology is one of the first uses of this technology to increase productivity.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
So You Want to Arbitrate? Better Make Sure Your Contract Covers All Bases
August 16, 2021 —
Stephanie Nolan Deviney - ConsensusDocsAs a General Contractor, you may prefer to arbitrate any contractual disputes rather than engage in protracted litigation. Many Courts favor arbitration clauses and will enforce them if there is a sufficient reason to do so. However, there are several issues that a General Contractor should consider when including an arbitration clause in its construction agreement with its client. When an arbitration clause is not properly crafted, questions can arise as to who must arbitrate? Who decides whether to arbitrate? Who selects the arbitrator? What will the subject matter of the arbitration be? A look at a recent case in Pennsylvania highlights the need for properly crafted arbitration clauses.
A Recent Case Highlights The Importance Of Arbitration Clauses
In TEC Construction, LLC v. Greg Rich and Lora Rich filed in the Court of Common Pleas, Allegheny County, Pennsylvania, TEC Construction, LLC (“TEC”) and Greg and Lora Rich (the “Riches”), entered into a Construction Agreement with an arbitration clause. Specifically, the parties to the Construction Agreement, TEC and the Riches, agreed to arbitrate any disputes with the American Arbitration Association. Five subcontractors completed the work under the Construction Agreement but none of the subcontractors agreed to arbitrate.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Nolan Deviney, Fox Rothschild LLP (ConsensusDocs)Ms. Deviney may be contacted at
sdeviney@foxrothschild.com
Traub Lieberman Partner Bradley T. Guldalian Wins Summary Judgment
November 19, 2021 —
Bradley T. Guldalian - Traub LiebermanOn September 14, 2021, Traub Lieberman Partner Bradley T. Guldalian secured summary judgment on behalf of a City which operated a park containing a natural bathing spring in Sarasota County, Florida. The underlying loss occurred when the Plaintiff went to the park, entered the spring without incident, swam for more than an hour, then exited the spring and was returning to the area where she had stored her belongings when she slipped and fell on mud and grass, sustaining an open angulated fracture of her right tibia and fibula. The Plaintiff was rushed to the hospital where she underwent open reduction, internal fixation surgery on her right leg which consisted of implantation of a metal rod into the medullary cavity of her tibia that was secured by two proximal and two distal interlocking screws. She was in the hospital for four days. Upon discharge, the Plaintiff was placed in a walking boot and confined to a wheelchair for several months. The Plaintiff incurred nearly $100,000 in medical expenses. The Plaintiff filed a premises liability action against the City claiming it failed to maintain its premises in a reasonably safe condition. The Plaintiff also alleged that the City failed to warn her that the area where she had stored her belongings had become saturated and slippery proximately causing her fall and resulting injuries.
After the close of discovery, Mr. Guldalian filed a Motion for Summary Judgment on behalf of the City arguing the wet grass and mud upon which the Plaintiff fell and injured herself was a byproduct of patrons going in and out of the water and walking to and from the area where they stored their belongings, was open and obvious, and did not constitute a dangerous condition as a matter of law. Citing to case law from the Florida Supreme Court which held that it is common knowledge that walks adjacent to, leading to, or surrounding a bathing area generally have water constantly thrown upon them and are in a slippery condition, as well as deposition testimony from the Plaintiff confirming she had been swimming at the spring for the past eighteen plus years and was “very familiar” with the park, the spring, and the area where she normally stored her belongings, Mr. Guldalian argued that some injury-causing conditions, like wet grass and mud surrounding a swimming area, are simply so open and so obvious that they cannot be held, as a matter of law, to give rise to liability as dangerous conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
Congratulations 2016 DE, NJ, and PA Super Lawyers and Rising Stars
June 02, 2016 —
White and Williams LLPTwenty-one White and Williams lawyers have been named by Super Lawyers as a Delaware, New Jersey, or Pennsylvania "Super Lawyer" while ten received "Rising Star" designations. Each lawyer who received the distinction competed in a rigorous selection process which took into consideration peer recognition and professional achievement. The winners named to this year's Super Lawyer list represent a multitude of practices throughout the firm.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Insurance Law Client Alert: California FAIR Plan Limited to Coverage Provided by Statutory Fire Insurance Policy
February 07, 2014 —
Valerie A. Moore and Chris Kendrick - Haight Brown & Bonesteel, LLPIn St. Cyr v. California Fair Plan Association (No. B243159, filed 1/31/14), a California appeals court held that the state's high risk property insurance plan is not obligated to provide any greater coverage than that mandated for the state's statutory fire insurance policy.
The plaintiff-policyholders lived in high fire risk areas and were insured under the California FAIR Plan, which provides property insurance to the otherwise uninsurable. Following loss of their homes and other property in wildfires, the policyholders were paid the full amount of their policy limits, but contended that they were entitled to additional payments. Specifically, the policyholders alleged that the FAIR plan provided less protection than statutorily mandated by Insurance Code sections 10090 through 10100.2, which spells out the "Basic Property Insurance Inspection and Placement Plan" of the FAIR program.
The policyholders contended that FAIR was required to issue a policy not only in accordance with the standard form fire insurance policy set forth in Insurance Code section 2071, but also the "'Basic Property Insurance' written in the normal market . . . known as the 'HO-3'," referring to the copywrited homeowners policy form promulgated by the Insurance Services Office (ISO).
Reprinted Courtesy of Valerie A. Moore, Haight Brown & Bonesteel, LLP and
Chris Kendrick, Haight Brown & Bonesteel, LLP
Ms. Moore may be contacted at vmoore@hbblaw.com and Mr. Kendrick may be contacted at ckendrick@hbblaw.com.
Read the court decisionRead the full story...Reprinted courtesy of
The Goldilocks Rule: Panel Rejects Proposed Insurer-Specific MDL Proceedings for Four Large Insurers, but Establishes MDL Proceeding for the Smallest
November 16, 2020 —
Eric B. Hermanson & Konrad R. Krebs - White and WilliamsIt is an outcome few people expected. Back in August, the Judicial Panel on Multidistrict Litigation (Panel) refused plaintiffs’ requests to set up a single industry-wide multi-district litigation, which would have consolidated — in a single massive proceeding — all federal lawsuits seeking COVID-related business interruption coverage from insurers. The Panel acknowledged common legal issues, and potential benefits of coordinated management, but it balanced those benefits against the numerous factual differences between policies, carriers, and insureds, and noted that “[t]hese differences will overwhelm any common factual questions.”
Then, after lengthy argument, the Panel ordered further briefing as to whether separate, company-specific MDL proceedings might be appropriate against five specific insurance carriers: specifically, the five carriers against whom the largest numbers of federal claims were pending.
By choosing these five carriers and not others for further argument, the Panel seemed to be suggesting a formula: the larger the carrier, and the greater the number of claims against it, the greater the potential benefit from coordinated management, and the stronger the plaintiffs’ case for pre-trial consolidation.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Hermanson, White and WilliamsMr. Hermanson may be contacted at
hermansone@whiteandwilliams.com