Performing Work with a Suspended CSLB License Costs Big: Subcontractor Faces $18,000,000 Disgorgement
September 17, 2015 —
Steven M. Cvitanovic & David A. Harris – Haight Brown & Bonesteel LLPIn what could lead to a draconian result, the Court of Appeal for the First Appellate District held that a contractor who performs work without a valid license can be required to disgorge all payments received, even if the contractor perfectly performed its work. The case, Judicial Council of California v. Jacobs Facilities, Inc. (Ct. of Appeal, 1st App. Dis., Div. One, A140890, A141393), involved an $18,000,000 contract between Jacobs Facilities, Inc. (“Jacobs Facilities”) and the Judicial Council of California (“Judicial Council”). In April 2006, Jacobs Facilities, a wholly owned subsidiary of Jacobs Engineering Group, Inc. (“Jacobs Engineering”) entered into a three year contract with the Judicial Counsel to maintain 121 courthouses and other judicial branch buildings throughout Southern California (the “Contract”). Jacobs Facilities contracted to provide maintenance and oversight services, while retaining subcontractors to perform the actual maintenance and repair work.
In December 2006, as part of a corporate reorganization, Jacobs Engineering started winding up Jacobs Facilities and transferred its employees to Jacobs Engineering and then subsequently to another wholly owned subsidiary called Jacobs Project Management Co. (“Jacobs Management”). The work that was performed by Jacobs Facilities was taken over by Jacobs Management. As part of the windup, Jacobs Facilities’ Contractor’s State License Board license was allowed to lapse and the license expired by operation of law in November 2008. Although Jacobs Management was now performing the work, it was not added as a party to the contract. Although it appears Judicial Council was aware of the corporate changes, it was not until November 2009 that the parties assigned the contract to Jacobs Management.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
David A. Harris, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Harris may be contacted at dharris@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Second Circuit Finds Potential Ambiguity in Competing “Anti-Concurrent Cause” Provisions in Hurricane Sandy Property Loss
November 28, 2018 —
CDJ STAFFThe Second Circuit recently held that competing “anti-concurrent cause” provisions in a commercial property policy present a potential ambiguity that could result in favor of coverage for losses sustained by Madelaine Chocolate after storm surge from Hurricane Sandy combined to cause substantial damage to Madelaine’s property and a resulting loss of income.
Madelaine was insured under an all-risk insurance policy issued by Chubb subsidiary Great Northern Insurance Company. By endorsement, Madelaine’s policy added “windstorm” as a covered peril and defined “windstorm” as “wind… regardless of any other cause or event that directly or indirectly contributes concurrently to, or contributed in any sequence to, the loss or damage.” The policy also included a common flood exclusion that removed coverage for loss or damage caused by or resulting from waves, tidal water, or tidal waves, or the rising, overflowing, or breaking of any natural harbors, oceans, or any other body of water, whether driven by wind or not. Like the windstorm endorsement, the flood exclusion contained concurrency language that broadened the exclusion to any loss to which flood contributed, regardless of any other cause or event that directly or indirectly contributed to the loss.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Tae Andrews, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Andrews may be contacted at tandrews@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
The Little Ice Age and Delay Claims
January 24, 2018 —
Wally Zimolong - Supplemental ConditionsMuch of the Eastern United States is just now emerging from a historic two week cold snap. In much of the Northeast and Mid-Atlantic, the temperature stayed below freezing for 15 days straight. Cities recorded the lowest temperatures in a quarter century. Winter Storm Grayson reeked havoc along the Eastern Coast bringing snow to places like Charleston and a crippling blizzard to Boston.
The record cold snap also impacted the construction industry. Delivery delays, the inability to apply weather sensitive applications (like cast in place concrete), and the unavailability of labor are just a few things that extreme weather can cause on a construction project. If they happen at the wrong time, delays can destroy project schedules and make previous delays even worse. Delays cost money and can mean the difference between a profitable project from both the owner and contractors perspective.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Partner John Toohey and Senior Associate Sammy Daboussi Obtain a Complete Defense Verdict for Their Contractor Client!
December 11, 2023 —
Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that Newport Beach attorneys John Toohey and Sammy Daboussi obtained a complete defense verdict after years-long litigation in favor of their concrete contractor client.
This lawsuit arises from a claim made by Plaintiff for construction defects in a high-end single-family home. Our client was hired to perform concrete work on the foundations of the home. It was alleged that the home’s foundation was incorrectly built. It was further alleged that the construction defects/errors led to delays and substantial expenses. We argued that our client relied on the certifications provided to them by design professionals and the City. We further argued that our client, like any reasonable concrete/foundation subcontractor, has no responsibility or obligation, contractual or otherwise, to review and recheck the work completed by a licensed professional.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
North Carolina Court Rules In Favor Of All Sums
July 13, 2020 —
Lorelie S. Masters & Patrick M. McDermott - Hunton Andrews KurthA North Carolina court recently ruled in favor of all sums allocation. Duke Energy Carolinas, LLC v. AG Insurance SA/NV, No. 17 CVS 5594 (N.C. Sup. Ct.). In that case, Duke Energy is seeking coverage for “liabilities linked to coal combustion residuals (‘CCRs’), i.e., coal ash, at fifteen Duke-owned power plants in North and South Carolina.” In a recent summary judgment decision, the court resolved a dispute between Duke and TIG Insurance Company, as successor to Ranger Insurance Company, about whether all sums allocation or pro rata allocation applied.
The court found that “the non-cumulation provisions make plain” that all sums allocation applied. It also noted that “a large majority of the courts in other jurisdictions that have considered this issue have recognized that non-cumulation provisions such as those here compel all sums rather than pro rata allocation.” The decisions to the contrary, according to the court, had ruled “done so on public policy grounds” and not based on “the application of the rules of contract interpretation.”
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Patrick M. McDermott, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. McDermott may be contacted at pmcdermott@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
It’s Too Late, Lloyd’s: New York Federal Court Finds Insurer Waived Late Notice Defense
June 05, 2023 —
Latosha M. Ellis & Janine A. Hanrahan - Hunton Insurance Recovery BlogA New York federal judge recently ruled that an insurer waived its late notice defense because a generic reservation of rights was insufficient to preserve it. As a result, the policyholder’s claim was preserved despite being submitted more than three months after the loss—a delay which would ordinarily be fatal under New York law. The decision underscores the importance both of timely submission of claims and careful attention to reservation of rights letters.
Background
Mave Hotel Investors LLC (“Mave”) owns a small hotel in Manhattan that was insured by Certain Underwriters at Lloyd’s, London (“Lloyd’s”). From October 2017 to October 2020, Mave contracted with a housing network to temporarily house homeless families and their children in the hotel. When the contract with the housing network terminated in October 2020, Mave alleged that the rooms were severely damaged and that it had to pay $1.4 million to repair them.
Reprinted courtesy of
Latosha M. Ellis, Hunton Andrews Kurth and
Janine A. Hanrahan, Hunton Andrews Kurth
Ms. Ellis may be contacted at lellis@HuntonAK.com
Ms. Hanrahan may be contacted at jhanrahan@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
The Final Nail: Ongoing Repairs Do Not Toll the Statute of Repose
November 07, 2022 —
Kyle Rice - The Subrogation StrategistIn Venema v. Moser Builders, Inc., 2022 PA Super. 171, 2022 Pa. Super. LEXIS 414, the Superior Court of Pennsylvania (Superior Court) upheld an award of judgment on the pleadings from the Court of Common Pleas of Chester County (Trial Court). The Superior Court found that Pennsylvania’s 12-year Statute of Repose for improvements to real property (Statute of Repose) began to run upon the issuance of the certificate of occupancy following original construction of the home in 2003—not from the completion of repairs to the home that continued through 2008.
The underlying cause of action involved a home constructed by Moser Builders, Inc. (Moser) in 2003. The certificate of occupancy for the home was issued on August 13, 2003. Matthew Venema and Liza Squires (collectively, Venema) purchased the property from the original owners in 2004.
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
You Cannot Arbitrate Claims Not Covered By The Arbitration Agreement
March 16, 2020 —
David Adelstein - Florida Construction Legal UpdatesRegardless of the type of contract you are dealing with, “[a]rbitration provisions are contractual in nature, and therefore, construction of such provisions and the contracts in which they appear is a matter of contract interpretation.” Wiener v. Taylor Morrison Services, Inc., 44 Fla. L. Weekly D3012f (Fla. 1st DCA 2019). This means if you want to preserve your right to arbitrate claims you want to make sure your contract unambiguously expresses this right. Taking this one step further, if you want to make sure an arbitrator, and not the court, determines whether the claim is arbitrable if a dispute arises, you want to make sure that right is expressly contained in the arbitration provision.
For example, in Wiener, a homeowner sued a home-builder for violation of the building code – a fairly common claim in a construction defect action. The homeowner’s claim dealt with a violation of building code as to exterior stucco deficiencies. The home-builder moved to compel the lawsuit to arbitration based on a structural warranty it provided to the homeowner that contained an arbitration provision. The structural warranty, however, was limited and did not apply to non-load-bearing elements which, per the warranty, were not deemed to have the potential for a major structural defect (e.g., a structural defect to load-bearing elements that would cause the home to be unsafe or inhabitable). The trial court compelled the dispute to arbitration pursuant to the arbitration provision in the structural warranty.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at