Ahead of the Storm: Preparing for Irma
September 07, 2017 —
Stephen H. Reisman – Peckar & Abramson, P.C.While Hurricane Irma boils in the Atlantic and seems to be aiming towards Florida, storm preparations are well underway. As contractors are busy organizing efforts to secure their job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful when the dust finally settles:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements.
- Even if not expressly required at this point in time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that productivity and the progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen H. Reisman, Peckar & Abramson, P.C.Mr. Reisman may be contacted at
sreisman@pecklaw.com
Courthouse Reporter Series: Two Recent Cases Address Copyright Protection for Architectural Works
January 16, 2024 —
Stu Richeson - The Dispute ResolverRecent decisions by the Seventh Circuit and the Eight Circuit have addressed the scope of protection afforded to architectural works under copyright law. The Seventh Circuit case of Design Basics, LLC v. Signature Constr., Inc., 994 F.3d 879 (7th Cir. 2021), took a somewhat narrow view of the copyright protection afforded to the design of an “affordable, multipurpose, suburban, single-family home.” In Designworks Homes, Inc. v. Columbia House of Brokers Realty, Inc., 9 F.4th 803 (8th Cir. 2021), cert. denied, 142 S. Ct. 2888, 213 L. Ed. 2d 1103 (2022) the Eight Circuit held that the publication of floor plans of a house in a real estate listing was not protected from claims of copyright infringement.
Design Basics, LLC v. Signature Constr., Inc., involved a plaintiff that the court described as holding registered copyrights in thousands of floor plans for suburban, single-family homes that are basic schematic designs, largely conceptual in nature, and depict layouts for one- and two-story single-family homes that include the typical rooms: a kitchen, a dining area, a great room, a few bedrooms, bathrooms, a laundry area, a garage, stairs, assorted closets, etc. The court described the plaintiff as a “copyright troll” and noted that litigation proceeds had become the principal revenue stream for the plaintiff. The plaintiff sued a contractor and related businesses contending hat the defendants had infringed plaintiff’s copyrighted floor plans.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
No Coverage Under Property Policy With Other Insurance and Loss Payment Provisions
September 17, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that the other insurance and loss payment provisions relieved the insurer of coverage obligations. Moroney Body Works, Inc. v. Central Ins. Co., 2015 Mass. App. LEXIS 97 (Aug. 6, 2015).
A fire destroyed Moroney's custom-built bookmobile that had just been completed. Moroney had two policies: a commercial property policy issued by Central, and a garage insurance policy issued by Pilgrim Insurance Company. Central denied liability for the bookmobile. Pilgrim covered the cost of repairing the bookmobile. It paid $12,449.82 based on the appraiser's estimate of the repair costs. Moroney thought this amount was inadequate given its own estimate of the repair costs.
Moroney sued both insurers. Pilgrim settled by paying Moroney an additional amount which, when added to Pilgrim's earlier payment, resulted in Moroney receiving more than the repair cost. Moroney and Central both moved for summary judgment. The trial court granted Moroney's motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Mitigating the Consequences of Labor Unrest on Construction Projects
February 14, 2023 —
Cameron Lukas, Alan Winkler & Gregory Begg - ConsensusDocsUntil this past year, we have enjoyed an era of relative labor stability. It’s true, however, that labor unrest frequently coincides with inflationary pressure on prices, something that we are currently experiencing. The recent nationwide rail workers strike was averted only through the extraordinary intervention of the federal government. More recently, thousands of academic workers in the University of California system went on strike. Underscoring this development was a November 2022 New York Times article reporting that polls showed the highest level of support for organized labor since the 1960s. The same article also quoted a professor of labor relations warning that the current economy presents a high potential for strikes. This recalls the sixties and seventies when increased costs due to inflation led to a multitude of strikes.
The construction industry has been historically strike-prone with approximately 22% of all strikes during the 1960s involving construction projects, contrasted with the fact that construction workers themselves accounted for only roughly 5% of the nation’s nonagricultural labor force. Incredibly, in 1969 alone, a record number of nearly 1,000 construction strikes occurred nationwide with 20 million worker days lost, more than five times the lost working time of the rest of the economy.
[1]
Reprinted courtesy of
Cameron Lukas, Peckar & Abramson, P.C,
Alan Winkler, Peckar & Abramson, P.C and
Gregory Begg, Peckar & Abramson, P.C
Mr. Lukas may be contacted at clukas@pecklaw.com
Mr. Winkler may be contacted at awinkler@pecklaw.com
Mr. Begg may be contacted at gbegg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction News Roundup
September 19, 2022 —
Christopher G. Hill - Construction Law MusingsMuch happened in the last week or so in Virginia construction, both legally and otherwise. I thought a quick roundup was in order.
On the green front we has a great article in ENR relating to the liability risk of green building and the great interest in the
AGCVA Green Building Breakfast.
Also, the Virginia courts decided several interesting cases:
The first is Travelers Property Cas. Co. of America a/s/o Covenant Woods v. Premier Project Mgmt. Group LLC v. Haskell Co. a case that reminds everyone that waivers of third party rights under the contract will be enforced in Virginia.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Serving the 558 Notice of Construction Defect Letter in Light of the Statute of Repose
November 06, 2018 —
David Adelstein - Florida Construction Legal UpdatesFlorida Statutes Chapter 558 requires a Notice of Construction Defect letter (“558 Notice”) to be served before a construction defect lawsuit is commenced. This is a statutory requirement unless contractually waived for a completed project when latent defects or post-completion construction or design defects are pursued.
A recent Florida case held that this statutory requirement is NOT intended to bar a lawsuit based on Florida’s ten-year statute of repose for construction defects IF the 558 Notice is timely served within the statute of repose period. After the expiration of the statute of repose period, a construction defect lawsuit can no longer be commenced.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Issue and Claim Preclusion When Forced to Litigate Similar Issues in Different Forums: White River Village, LLP v. Fidelity and Deposit Company of Maryland
October 10, 2013 —
Brady Iandiorio — Higgins, Hopkins, McLain & Roswell, LLC.Often in construction litigation the parties wish to move the case to arbitration. However, there are certain circumstances in which such change of litigation forums should be carefully analyzed. The case of White River Village, LLP v. Fidelity and Deposit Company of Maryland, serves as an example of one of those circumstances.
In March 2013, U.S. District Court Judge Blackburn ruled on a motion for summary judgment filed by Fidelity and Deposit Company of Maryland (“F&D”). The order grants the motion in part and denies it in part. White River Village, LLP (“White River”) was the owner of the project which hired S&S Joint Venture (“S&S”), the contractor, to build two similar developments, directly adjacent to each other. The contracts between Whiter River and S&S for the two projects were so substantially similar that the court referred to them as the S&S Contracts. F&D issued payment and performance bonds guarantying the obligations of S&S under the S&S Contracts.
After S&S defaulted on the construction contracts, F&D, as the surety, undertook to complete performance on the contracts. White River alleged that F&D was liable for construction defects and delays in completing the project, and failed to fulfill its obligations under the performance bonds after it overtook the construction of the projects.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Payment Bond Surety Entitled to Award of Attorneys’ Fees Although Defended by Principal
February 01, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In
Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com