What a Difference a Day Makes: Mississippi’s Discovery Rule
November 16, 2023 —
William L. Doerler - The Subrogation StrategistThe discovery rule applies to latent injuries, such that the statute of limitations does not begin to run until the plaintiff knows of or should have known of the injury. In Western World Ins. Group v. KC Welding, LLC, No. 2022-CA-00527-SCT, 2023 Miss. LEXIS 278 (KC Welding), a majority of the justices on the Supreme Court of Mississippi (Supreme Court) affirmed the trial court’s ruling that Western World Insurance Group (Insurer) filed its lawsuit one day late. Thus, the statute of limitations barred Insurer’s lawsuit.
In KC Welding, on July 12, 2018, KC Welding, LLC (KC Welding) sent an employee to Sunbelt Shavings, LLC (Sunbelt) to repair the door of a box containing wood chips. Sunbelt’s employees discovered that KC Welding employees were welding a storage bin that had not been emptied of wood chips and Sunbelt’s employees asked KC Welding’s employees to leave. After that, Sunbelt’s employees attempted to soak the area with water. Later than night, a fire started on Sunbelt’s property, apparently as the result of smoldering wood shavings, a fire that was extinguished on July 13, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Settlement Reached on Troubled Harbor Bridge in Corpus Christi, Texas
November 16, 2023 —
Daniel Tyson - Engineering News-RecordA $400-million settlement was reached between the Texas Dept. of Transportation and general contractor Flatiron/Dragados over Corpus Christi’s Harbor Bridge in mid-October. The accord ends all disagreements and damage claims concerning the cable-stayed bridge, a project halted multiple times.
Reprinted courtesy of
Daniel Tyson, Engineering News-Record
Mr. Tyson may be contacted at tysond@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Insurers' Motion to Void Coverage for Failure to Attend EUO Denied
January 04, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment and disposal of the insureds' claim due to failure to attend an examination under oath (EUO) was denied. Perkins v Syndicate 4242 of Lloyd's of London, 2022 U.S. Dist. LEXIS 196922 (W.D. La. Oct. 28, 2022).
The insureds' home suffered damage from Hurricane Laura on August 27, 2020, and Hurricane Delta on October 9, 2020. The insureds reported damage after Hurricane Laura under the homeowners policy. They filed suit in August 2021, alleging that Lloyds failed to adequately inspect their claims. The court issued a Case Management Order (CMO) that governed initial disclosures and the parties' participation in a streamlined settlement process for hurricane claims. The dispute did not settle, however, so the matter was set for a bench trial.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Burden Supporting Termination for Default
January 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesTerminating a contractor for default is a “‘drastic sanction’ and ‘should be imposed (or sustained) only for good grounds and on solid evidence.’” Cherokee General Corp. v. U.S., 150 Fed.Cl. 270, 278 (Fed.Cl. 2020) (citation omitted). This is true with any termination for default because terminating a contract for default is the harshest recourse that can be taken under a contract. It is a caused-based termination. For this reason, the party terminating a contract for default needs to be in a position to carry its burden supporting the evidentiary basis in exercising the default-based (or caused-based) termination. Stated differently, the party terminating a contract for default needs to justify the reasonableness in terminating the contract for default.
A party looking to terminate a contract for default should smartly work with counsel to best position its justification in exercising the termination for default. Likewise, a contractor terminated for default should immediately work with counsel to best position the unreasonableness or the lack of justification for the default-based termination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
A Year Later, Homeowners Still Repairing Damage from Sandy
October 01, 2013 —
CDJ STAFFThe New York and New Jersey coastal communities are still in the thick of rebuilding and repairing after hurricane Sandy struck almost a year ago. Newsday reports that in the eight months following the October 2012 storm, more than 23,000 building permits were issued in Long Island communities, an 11 percent rise over the previous year. The town of Long Beach, New York has waived fees and hired more staff in order to encourage people to rebuild, in order to rebuild the town’s tax base.
Homeowners aren’t going it alone, New York expects to fund more than $1 billion of rebuilding for homeowners who are unable to afford repairing their homes. At this point, the state is still processing more than five thousand requests for grants. The money is still in the state’s coffers. Other homeowners are still filing insurance claims.
While towns are busy issuing building permits, contractors are busy too. Bill Sims of Sims Steel said that his business has changed from commercial construction to raising homes higher to put them above future floods. “There’s probably been more homes raised this last year than in the previous 20 years,” he told Newsday. Another contractor, Pat Gordon said that he is “only taking what we can handle.” He described Long Beach as “a traffic jam of construction trucks that has never been seen before.”
Read the court decisionRead the full story...Reprinted courtesy of
Price Escalation Impacts
August 22, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogThis Bulletin provides guidance to contractors, subcontractors, suppliers, and others to ensure compliance with contractual change order requirements in the event work on a construction project is impacted by price escalation.
Construction projects are being impacted by increased costs for most construction materials. The Producer Price Index shows a 69% increase in the cost of construction materials from March 2020 to March 2022. Many construction contracts do not address escalation or specifically exclude change orders for material escalation, leaving the risk of escalation of construction materials with the contractor, subcontractor, or suppliers.
Bid Protection Tips:
- Keep bids open for less than 30 days with a designated sunset date:
- Keeping your bids open for less than 30 days can help protect you from sudden changes in pricing and help maintain your bids’ competitive status.
- If asked to extend time a bid is open, reconfirm prices before agreeing.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
Insured's Claim for Water Damage Dismissed with Leave to Amend
August 12, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss the insured's claim for water damage under a homeowners' policy, but granted leave to amend. Thompson v. State Farm Gen. Ins. Co., 2024 U.S. Dist. LEXIS 98486 (C.D. Cal. June 3, 2024).
The insureds' first amended complaint alleged they "suffered a sudden and accidental water loss below their slab in their home." A plumber hired by the insureds discovered "a copper pipe burst inside a structural concrete footing between a manifold in the living room and the water heater." The insureds notified their insurer, State Farm.
Claim adjuster Andrea Acevedo conducted a visual inspection. The complaint alleged she did not "inspect or view the pipe, or have a testing conducted on the pipe." Acevedo sent a letter denying the insureds' claim based upon her finding that "because the loss was caused by a slab leak, there is no coverage available for the loss." The letter explained that the hot water supply line under the home failed due to wear, tear, deterioration and/or electrolysis. The predominant cause of loss to the failed pipe was due to one or a combination of rust, electrolysis, corrosion, wear, tear and/or deterioration. The policy did not cover water damage caused by water from below the surface of the ground. Further coverage for wear, tear, deterioration, rot, mold, maintenance, water from below the surface of the ground and a continuous or repeated seepage or leakage of water was excluded.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Newmeyer & Dillion’s Alan Packer Selected to 2018 Northern California Super Lawyers List
July 18, 2018 —
Newmeyer & DillionWALNUT CREEK, Calif. – JULY 10, 2018 – Prominent business and real estate law firm Newmeyer & Dillion LLP is pleased to announce that litigation attorney Alan Packer has been selected to the 2018 Northern California Super Lawyers list. No more than five percent of the lawyers in the state are selected by Super Lawyers each year.
Packer is a partner in the firm's expanding Walnut Creek office. He has practiced law in California for over 30 years, mostly representing parties involved in real estate, home building, commercial construction, and insurance matters. He represents business clients, homebuilders, property owners, and others in a broad range of legal matters.
Packer is a frequent speaker at seminars and in-house training sessions for clients on issues relating to risk management, construction litigation, and insurance.
Earlier this year, Newmeyer & Dillion attorneys in Newport Beach and Las Vegas were also selected to Super Lawyers lists. Packer brings its total to 19 Newmeyer & Dillion attorneys recognized.
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The patented selection process includes independent research, peer nominations and peer evaluations, resulting in a comprehensive and diverse listing of exceptional attorneys.
Alan Packer
Partner
Walnut Creek
Contact
925.988.3200
alan.packer@ndlf.com
Practices
Business Litigation
Construction Litigation
Insurance Law
Real Estate Litigation
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decision
Read the full story...
Reprinted courtesy of