More (and Simpler) Options Under New Oregon Retention Law
October 21, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCSimilar to the changes made by the Washington Legislature last year, the Oregon Legislature recently changed its retention law. Oregon public works agencies and large commercial project owners are now required to accept surety bonds in lieu of withholding retainage on construction projects. There is also no longer a requirement to deposit retention funds in an interest-bearing escrow account.
The owner or public agency must accept the bond in lieu of retainage unless specific grounds exist. For example, public agencies must find there is “good cause” for rejection of the bond based on the “unique project circumstances. Private owners have less discretion to reject a bond and if the bond meets the statutory requirements, per ORS 701.435(1)(a) “the owner and lender shall accept” the bond “in lieu of all or any portion of the retainage…”
Courts have not analyzed when “good cause” exists for public agencies to reject bonds or exactly what will allow a private owner to reject a bond. However, an agency or owner cannot have a general policy to reject retention bonds. The statute does not provide next steps if the contractor disagrees with a decision to reject the bond. It may be necessary to proceed under the contract’s dispute resolution procedure or it may be more appropriate to take the issue directly to the courts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
Return-to-Workplace Checklist: Considerations and Emerging Best Practices for Employers
July 20, 2020 —
Nancy Conrad & George C. Morrison - White and Williams LLPAs employers plan to return employees to the workplace, they should proceed with careful planning and incorporate best practices and measures to assure a safe, responsible and productive workplace. While there is no "one size fits all" plan, the following checklist will assist in assuring that your work environment includes the key safety components to return to the workplace in the midst of a pandemic.
PREPARING THE WORKPLACE FOR RETURN & GENERAL HEALTH AND SAFETY
- Create a company task force, safety committee or coordinator to oversee implementation of policies that address and enforce practices related to COVID-19.
- Ensure HVAC systems are functional, have been properly cleaned and serviced and tuned to maximize airflow and filtration.
- Review and increase cleaning protocols in coordination with lease terms and cleaning contracts. Ensure regular and thorough office cleanings, with a focus on high-touch surfaces and areas. Document cleaning protocols and schedule.
- Implement social distancing requirements and provide visual markers on floors in compliance with applicable federal, state and local orders.
- Rearrange work spaces, conference rooms and lunchrooms to comply with social distancing requirements.
- Post notices about the number of individuals permitted in elevators, stairwells, rooms and on the premises.
- Restrict movement between departments and floors.
Reprinted courtesy of
Nancy Conrad, White and Williams LLP and
George C. Morrison, White and Williams LLP
Ms. Conrad may be contacted at conradn@whiteandwilliams.com
Mr. Morrison may be contacted at morrisong@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
South Africa Wants Payment From Colluding World Cup Builders
July 23, 2014 —
Kamlesh Bhuckory and Mike Cohen – BloombergSouth Africa’s government is putting pressure on construction companies to make further payments as punishment for rigging contracts to build stadiums for the 2010 FIFA Soccer World Cup and other projects.
Antitrust authorities fined 15 builders, including Murray & Roberts Holdings Ltd. (MUR) and Aveng Ltd., a total of 1.5 billion rand ($141 million) in June 2013, after a probe that spanned almost four years found they colluded to drive up prices.
“The 1.5 billion rand in penalties is not the end of the story with the construction industry,” Economic Development Minister Ebrahim Patel told lawmakers in Cape Town today. “We are now in discussion with the construction industry on a restitution package for their collusion and price fixing.”
Mr. Bhuckory may be contacted at kbhuckory@bloomberg.net; Mr. Cohen may be contacted at mcohen21@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kamlesh Bhuckory and Mike Cohen, Bloomberg
Techniques for Resolving Construction Disputes
September 16, 2019 —
Jason Lambert - Construction ExecutiveWith most construction projects involving dozens, if not hundreds, of companies and individuals, it is no surprise that conflicts arise that are not always able to be resolved on the jobsite. But these conflicts need not always reach the court room or cost thousands (or much more) to resolve. With some planning, contractors can build faster and less expensive dispute resolution options into their project so they can spend more time keeping the project moving and less time arguing over who is right.
Even for modest-sized projects, a multi-tiered approached to dispute resolution can be helpful. As a first level of dispute resolution, consider requiring the relevant parties to attend informal or formal mediation. The benefits of even an informal mediation is that it can get stalemated parties to the table to talk again. Formal mediation adds the benefit of a neutral third-party who can help get talks moving or help antagonistic parties communicate.
Further, mediation allows each side an opportunity to hear what the other side is looking for to resolve the dispute. Not only is this valuable in reaching a compromise, but it also gives each side an idea of what the other will bring to the table in any subsequent litigation. Finally, there are many ways to implement these procedures. General contractors can require pre-suit mediation with their subcontractors to resolve one-on-one disputes but should also consider requiring subcontractors to use pre-suit mediation to resolve disputes between subcontractors or between subcontractors and sub-subcontractors or material suppliers if the dispute threatens the progress at the project.
Reprinted courtesy of
Jason Lambert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Bid Protests: The Good, the Bad and the Ugly (Redeux)
September 17, 2014 —
Garret Murai – California Construction Law BlogThis past week I gave a presentation on a panel entitled “Bid Protests: The Good, the Bad and the Ugly” before my local bar association. Thanks to those who attended, my co-presenters and the bar association for sponsoring.
Rather than letting my notes gather dust I thought I would share some of the highlights.
What is a bid protest?
A bid protest is the procedure by which a bidder protests the rejection of its bid or award of a public works contract to another bidder.
A bid protest may occur in one of two situations: (1) A public entity rejects the bid of an apparent low bidder and the apparent low bidder protests the rejection; or (2) A public entity awards the contract to the apparent low bidder and another bidder protests the award.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
EPA Announces that January 2017 Revised RMP Rules are Now Effective
February 06, 2019 —
Anthony B. Cavender - Gravel2GavelOn December 3, the Environmental Protection Agency (EPA) published a Federal Register notice advising the regulated community that EPA’s controversial Clean Air Act (CAA) stationary source Risk Management Program (RMP) rules are effective as of December 3, 2018 – the Final Rule: Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act (83 FR 62268). The initial package of the RMP rules was promulgated in 1996, but a series of chemical explosions prompted the development of new rules, whose process safety, third party auditing, emergency response, preparedness and information sharing provisions were designed to confront these challenges.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Florida Appellate Court Holds Four-Year Statute of Limitations Applicable Irrespective of Contractor Licensure
June 22, 2016 —
Clay Whittaker – Florida Construction Law UpdateIn Brock v. Garner Window & Door Sales, Inc.,[1] Florida’s Fifth District Court of Appeal rejected a novel attempt to circumvent Florida’s well-established four-year statute of limitations for all actions founded on the construction of an improvement to real property. Plaintiff filed a lawsuit alleging breach of contract as a result of water intrusion damage following the installation of windows.[2] It was undisputed that Plaintiff commenced the litigation more than four years following the discovery of the allegedly latent defect in the window installation.[3] Plaintiff’s counsel argued that the window contractor could not rely on the four-year statute of limitations because the window subcontractor was not a licensed contractor and, therefore, the five-year statute of limitations for actions founded on written contracts should apply.
Read the court decisionRead the full story...Reprinted courtesy of
Clay Whittaker, Cole, Scott, & Kissane, P.A.Mr. Whittaker may be contacted at
clay.whittaker@csklegal.com
Public Contract Code Section 1104 Does Not Apply to Claims of Implied Breach of Warranty of Correctness of Plans and Specifications
October 30, 2023 —
Garret Murai - California Construction Law BlogIt’s the classic tale of two cities. One city is occupied by architects and engineers. The other, by contractors. And while the cities typically co-exist relatively peacefully together, at times, they do not, such as when a defect arises that can either be a design or construction defect.
Sometimes, project owners are pulled into these fights as well. There is a common law rule that when contracting with a contractor the owner impliedly warrants to the contractor that the plans and specifications are sufficiently accurate and correct.
And, if you work on local public works projects, you may be familiar with Public Contract Code section 1104 which provides that, with the exception of design-build projects, local public entities cannot require a bidder to assume responsibility for the completeness and accuracy of architectural or engineering plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at