Insured's Commercial Property Policy Deemed Excess Over Unobtained Flood Policy
June 10, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion for summary judgment, deciding that there was no breach of the policy for failure to pay for flood damage when the insured failed to obtain a policy under the National Flood Insurance Program (NFIP). 570 Smith St. Realty Corp. v. Seneca Ins. Co. Inc., 2019 N.Y. Misc. LEXIS 1773 (N.Y. Sup. Ct. April 4, 2019).
The insured's property in Brooklyn was insured by Seneca. Included in the policy was flood coverage in the amount of $1 million with a $25,000 deductible. While the policy was in effect, Hurricane Sandy hit, damaging the property. Plaintiffs timely filed a claim seeking reimbursement of up to policy limits. Seneca paid only $35,883 and later made an additional payment of $33,015.
The insured sued for, among other things, breach of the policy for failure to properly indemnify for the losses. Seneca moved for partial summary judgment dismissing the breach of policy claims. Seneca pointed out that the "Other Insurance" provision in the Flood Coverage Endorsement of the policy stated that if the loss was eligible to be covered under a NFIP policy, but there was no such policy in effect, the insurer would only pay for the amount of loss in excess of the maximum limit payable for flood damage under the policy. The maximum NFIP coverage was $500,000. The insured's loss caused by flood was less than $500,000.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Check The Boxes Regarding Contractual Conditions Precedent to Payment
August 21, 2023 —
David Adelstein - Florida Construction Legal UpdatesRemember this: complying with contractual conditions precedent to payment is important. There is a reason why construction contracts include contractual conditions precedent to payment. The contract does not include this language for sh*ts and giggles. This language is included to establish what is required of the payee before payment becomes due. There may be conditions precedent to the payment of progress payments. There may be conditions precedent to the payment of final payment. Payment is not due until the conditions precedent have been satisfied. Do yourself a favor and consider this language in the construction contract, particularly if a dispute arises. If the condition precedent has not or cannot be satisfied, game plan as to the factual reason. The best thing to do is be prepared – check the boxes regarding conditions precedent to ensure you have considered this contractual language.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Avoiding Project Planning Disasters: How to Spot Problem Projects
December 13, 2021 —
James T. Dixon - Construction ExecutiveThe burden of project planning falls first and foremost upon a project owner. Owners have varying levels of sophistication, and the smart ones fill weak spots on their staff by engaging project managers, construction managers and owner’s representatives.
Typically, the owner then delegates the largest part of the project’s plan to the contractor in terms of creation and execution of a critical path method schedule during the construction phase. Before accepting that burden, a wise contractor will evaluate the project to determine if it is on a path to success or disaster. It is guaranteed that an owner’s problems will become the contractor’s problems in one way or another.
There are legendary projects that were also legendary planning failures. The iconic Sydney Opera House is one. The design competition began in 1955. After selecting the architect, the owner implemented a team that involved that architect, a structural engineer and an executive committee of inexperienced politicians. The original plan included a budget of $7 million (Australian) and a completion schedule spread over four years. That executive committee forced the project to start before designs were complete, doubled the number of theaters and then put a strangle-hold on the payment process, eventually causing the architect to quit and return to Europe with the construction drawings. The Opera House opened for its first performance in 1973—14 years late and $98 million over budget.
Reprinted courtesy of
James T. Dixon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
CDJ’s #6 Topic of the Year: Does Colorado Need Construction Defect Legislation to Spur Affordable Home Development?
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFThe question involves whether a Colorado law passed in 2005 has made it too easy for homeowners to sue developers for construction defects, allegedly causing a decline in condominium building in the state. The Construction Defect Journal became a forum for this lively debate with two prominent, Colorado, construction defect attorneys providing their views on the subject:
Jesse Howard Witt, of the Witt Law Firm, published “Colorado Mayors Should Not Sacrifice Homeowners to Lure Condo Developers.”
Read the full story...
In response, James M. Mulligan of Snell & Wilmer, LLP presented his perspective in, “Are Construction Defect Laws Inhibiting the Development of Attached Ownership Housing in Colorado?”
Read the full story...
The city of Lakewood did not wait for the state, but instead passed its own ordinance, which “gives developers and builders a ‘right to repair’ defects before facing litigation and would require condominium association boards to get consent from a majority of homeowners — rather than just the majority of the board — before filing suit,” according to John Aguilar’s piece in The Denver Post.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Supreme Court Grants the Petition for Writ of Certiorari in Vallagio v. Metropolitan Homes
June 22, 2016 —
David M. McLain – Colorado Construction LitigationWe have previously reported on the Vallagio v. Metropolitan Homes case, in which the Colorado Court of Appeals upheld a provision in an association's declaration of covenants, conditions, and restrictions, which required declarant consent before an arbitration provision could be amended out of the document. To read the past articles on the case, please review
Vallagio v. Metropolitan Homes: The Colorado Court of Appeals' Decision Protecting a Declarant’s Right to Arbitration in Construction Defect Cases and
The Vallagio HOA Appeals the Decision from the Colorado Court of Appeals.
Today, the Colorado Supreme Court granted the association's petition for writ of certiorari, en banc, on the following reframed issues:
Whether the court of appeals erred by holding as a matter of first impression that Colorado’s Common Interest Ownership Act (“CCIOA”) permits a developer-declarant to reserve the power to veto unit owner votes to amend common interest community declarations.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McClain, Higgins, Hopkins, McLain & Roswell, LLCMr. McClain may be contacted at
mclain@hhmrlaw.com
Building Safety Month Just Around the Corner
May 07, 2015 —
Beverley BevenFlorez-CDJ STAFFFor every week in May, the International Code Council (ICC) will spotlight a specific area of building safety. The theme this year is “Resisient Communities Start with Building Codes.” ICC’s first week focus is “Don’t Get Burned – Build to Code,” and the second week the focus changes to “Bounce Back Faster from Disaster – Build to Code.” Next, the ICC will present “Water Safe, Water Smart – Build to Code,” and conclude with “$save Energy – Build to Code.”
Read the court decisionRead the full story...Reprinted courtesy of
Inability to Confirm Coverage Supports Setting Aside Insured’s Default Judgment on Grounds of Extrinsic Mistake
January 21, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Mechling v. Asbestos Defendants (No. A150132, filed 12/11/18), a California appeals court affirmed the trial court’s grant of an insurer’s motion to set aside default judgments entered against its defunct insured pursuant to the trial court’s inherent, equitable power to set aside defaults on the ground of extrinsic mistake, thereby allowing the insurer to intervene and defend its own interests in the case.
In Mechling, Fireman’s Fund insured Associated Insulation of California, which was named as a defendant in asbestos litigation filed in 2009. Associated had ceased operating in 1974, but was somehow successfully served with the complaint and defaulted, leading to default judgments of several million dollars. Notice of the judgments was served on Associated but not Fireman’s Fund.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How Retro-Commissioning Can Extend the Life of a Building—and the Planet
July 10, 2023 —
Matthew Zweibruck - Construction ExecutiveSustainability initiatives in the built environment need not be limited to new construction or other large expenditures. Aging facilities have the potential to extend their years of service while also combating greenhouse gas emissions. But what is the best course of action? From building design initiatives such as net zero and electrification to renewables and green building certifications, it can be a complicated and overwhelming field to navigate.
Building owners and property managers may question if they are pursuing the correct programs to minimize their organization’s negative impacts on the environment. With all the initiatives, buzzwords and fancy awards surrounding these initiatives, there are energy-efficiency strategies available to buildings that cut through this noise—strategies that are cost effective, quick to implement, widely abundant and result in an immediate reduction in a building’s impact on climate change.
Reprinted courtesy of
Matthew Zweibruck, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of