Summary Judgment for Insurer on Construction Defect Claim Reversed
January 07, 2025 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit reversed the district court's granting of summary judgment to the insurer on a construction defect claim asserted against the insured. TIG Ins. Co. v. Woodsboro Farmers Cooperative, 2024 U.S. App. LEXIS 24003 (5th Cir. Sept. 20, 2024).
In March 2013, Woodsboro Farmers Cooperative contracted with E.F. Erwin, Inc. to construct two Brock 105' diameter grain silos. Erwin hired subcontract AJ Constructors, Inc. (AJC) to construct the silos. Erwin was responsible for supervising the work.
Brock silos were kits shipped by the manufacturer and then assembled according to the manufacturer's manuals and specifications. The silos are constructed section by section. AJC began erecting the silos in May 2013 and completed its work in June or early July. Erwin occasionally inspected the work and found the silos were structurally sound and not defective. AJC left the job site after completing the assembly.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
From the Ashes: Reconstructing After the Maui Wildfire
November 27, 2023 —
Grace Calengor - Construction ExecutiveOn Tuesday, Aug. 8, a wildfire on the Hawaiian island of Maui ravaged the town of Lahaina, killing nearly 100 people and stranding thousands of survivors, many of whom remain displaced today. The loss of life makes this the deadliest American wildfire on record, while the material cost in property damage has been estimated at upwards of $5 billion.
The response to the disaster has involved firefighters and other emergency personnel—and also engineering and construction professionals. One of them is Tam Kim, director of operations for West Maui Construction Inc., a civil contractor on the island. Originally from Oregon, Kim fell in love with Hawaii when he visited on a surfing vacation; eventually he took his technology background and helped found a startup company on Maui in 2008. Eight years later, the startup relocated to Oahu, but Kim stayed on Maui to forge a different path, one that would lead him somewhere he never imagined.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Tetzloff Elected As Newmeyer & Dillion Managing Partner
June 03, 2019 —
Newmeyer & Dillion LLPNewmeyer & Dillion LLP, a prominent business and real estate law firm, selected Paul Tetzloff as the firm's Managing Partner. His term began on January 1, 2019. A business litigator, Tetzloff will now oversee the firm's strategic plan and manage the firm's day-to-day business affairs.
"The Firm is incredibly fortunate to have Paul stepping into the role as Managing Partner. His energy, intelligence, leadership, and drive make him uniquely qualified to lead this Firm for years to come," said former Managing Partner Jeff Dennis. "I am excited to watch where the Firm is headed – we have such an amazing opportunity to continue to develop to even greater heights, and Paul will be a huge part of making that happen."
Active in his community, Tetzloff sits on the board for HomeAid Orange County and the Marine Raider Association.
Tetzloff is succeeding Dennis, who served in the role from 2012 to 2018. "Jeff was our managing partner for seven years and he did an outstanding job. We owe Jeff a debt of gratitude for his service," said Tetzloff of his predecessor. "I'm looking forward to continuing to build on the groundwork laid to help the firm reach new levels in the years to come."
Dennis' leadership allowed the firm to grow substantially under his tenure, including opening a Las Vegas, Nevada office and establishing thriving practice areas throughout various industries. Dennis will focus his energy on overseeing the firm's growing Privacy and Data Security practice.
Paul Tetzloff
paul.tetzloff@ndlf.com
Practice Areas
Business Litigation
Construction Litigation
Real Estate Litigation
About Newmeyer & Dillion
For almost 35 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
The Proposed House Green New Deal Resolution
February 27, 2019 —
Anthony B. Cavender - Gravel2GavelA Resolution has been proposed to the House for consideration that would recognize the Federal Government’s duty “to create a Green New Deal.” It sets forth a very ambitious 10-year program to mobilize and transform every aspect of American life to combat the threats of climate change by transitioning to an economy based upon 100% clean and renewable energy.
In doing so, millions of new jobs would be created, and everyone who wants a job would be guaranteed a job. The sponsors’ talking points declare that there is no time to lose, that Americans love a challenge, and “this is our moonshot.” The obvious goal is to eliminate the generation and use of fossil fuel and nuclear energy—they are simply not part of the solution.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
NYC Supertall Tower Condo Board Sues Over Alleged Construction, Design 'Defects'
October 04, 2021 —
James Leggate - Engineering News-RecordThe condominium board at a 1,396-ft-tall residential tower on New York City’s Billionaires’ Row has sued the building’s developers, claiming to have identified more than 1,500 construction and design defects in common areas alone.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
New York Assembly Reconsiders ‘Bad Faith’ Bill
May 31, 2021 —
Copernicus T. Gaza, Robert S. Nobel, Craig Rokuson, Eric D. Suben - Traub LiebermanThe New York State Assembly is considering A07285, which creates a private right of action for bad faith “if the insurer unreasonably refuses to pay or unreasonably delays payment without substantial justification.” The bill was first introduced in 2013 but was reintroduced on May 3, 2021 and has received some recent attention. According to the bill, an insurer acts unreasonably when it (among other things):
- Fails to provide the claimant with accurate information regarding policy provisions relating to the coverage at issue; or
- Fails to effectuate in good faith a prompt, fair, and equitable settlement of a claim or portion of a claim and where the insurer failed to reasonably accord at least equal or more favorable consideration to its insured's interests as it did to its own interests, and thereby exposed the insured to a judgment in excess of the policy limits or caused other damage to a claimant; or
- Fails to provide a timely written denial of a claimant's claim, or portion thereof, with a full and complete explanation of such denial, including references to specific policy provisions wherever possible; or
- Fails to act in good faith by compelling such claimant to initiate a lawsuit to recover under the policy by offering substantially less than the amounts ultimately recovered in such suit; or
- Fails to timely provide, on request of the policy holder or the policy holder's representative, all reports or other documentation arising from the investigation of a claim; or
- Refuses to pay a claim without conducting a reasonable investigation prior to such refusal.
Reprinted courtesy of
Copernicus T. Gaza, Traub Lieberman,
Robert S. Nobel, Traub Lieberman,
Craig Rokuson, Traub Lieberman and
Eric D. Suben, Traub Lieberman
Mr. Gaza may be contacted at cgaza@tlsslaw.com
Mr. Nobel may be contacted at rnobel@tlsslaw.com
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Mr. Suben may be contacted at esuben@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Makes an Unsettling Inference to Find that the Statute of Limitations Bars Claims Arising from a 1997 Northridge Earthquake Settlement
April 15, 2015 —
David W. Evans and Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Britton v. Girardi (No. B249232 – Filed 4/1/2015), the Second Appellate District upheld the trial court’s dismissal due to the statute of limitations based on an inference it drew from a letter attached to the complaint, while reaffirming its prior application of the limitations period in Probate Code section 16460 for fraud claims in the related case of Prakashpalan v. Engstrom, Lipscomb & Lack (2/27/2014) 223 Cal.App.4th 1105.
In Britton, just as in Prakashpalan, the plaintiffs sued the attorneys who had represented them in connection with claims against their insurer arising out of the Northridge earthquake. In 1997, the attorneys had settled that litigation for more than $100 million. The plaintiffs allege that the attorneys breached their fiduciary duty by (1) failing to provide an accounting for the settlement, (2) failing to obtain their informed consent to the settlement, and (3) concealing their misappropriation of the settlement funds. They claim that they did not discover this wrongdoing until nearly fifteen years later, in 2012, when the Prakashpalans contacted them about their settlement. Significantly, the plaintiffs attached as an exhibit to the complaint a page of the November 3, 1997 letter to the Prakashpalans (rather than the plaintiffs), which stated that a retired judge who presided over the settlement had determined the allocations and the attorneys could not distribute the proceeds until the plaintiffs signed the “Master Settlement Agreement” by which the plaintiffs agreed to its terms and to give up all claims against the insurer.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractor Not Estopped from Enforcing Lien Not Listed In Bankruptcy Petition
March 01, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPIn Stock Building Supply, Inc. v. Platte River Insurance Co.,[1] the Court of Appeals dealt with issues of judicial estoppel, bankruptcy, retroactive application of statutory lien amendments, and the full payment defense.
The owner, Madison Retail-Suwanee, LLC (“Madison”) hired Cannon/Estapa General Contractors, Inc. (“Cannon”) to be the general contractor for the construction of a shopping center (“the Project”). Cannon subcontracted with Stock Building Supply (“Stock”) to supply labor, materials, and services for the Project. Cannon failed to complete the project and Madison had yet to pay Cannon the full contract price. In 2007, Stock timely filed a lien on the Project and obtained a judgment against Cannon for the amount due under the subcontract. Platte River Insurance Company (“Platte”), the surety, issued a bond to discharge Stock’s lien. Consequently, Stock pursued an action against Platte to collect the judgment in the amount of $93,865.27.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com