Claim Against Broker Survives Motion to Dismiss
January 25, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's complaint against its broker for failure to secure adequate coverage survived a motion to dismiss. Broecker v. Conklin Prop., LLC, 2020 N.Y. App. Div. LEXIS 7399 (Dec. 2, 2020).
Conklin Property, LLC purchased real property and entered into a contract with JJC Contracting, Inc. for construction and renovation of the property. The broker, Total Management Corp. (TMC) was retained by Conklin to secure insurance for the construction phase of the renovation project. During the renovation, an employee of JJC was injured at the property and died. The employee's estate then sued Conklin. US Underwriters, the insurer, disclaimed coverage pursuant to an exclusion for bodily injury to contractors and subcontractors and their workers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Little Ice Age and Delay Claims
January 24, 2018 —
Wally Zimolong - Supplemental ConditionsMuch of the Eastern United States is just now emerging from a historic two week cold snap. In much of the Northeast and Mid-Atlantic, the temperature stayed below freezing for 15 days straight. Cities recorded the lowest temperatures in a quarter century. Winter Storm Grayson reeked havoc along the Eastern Coast bringing snow to places like Charleston and a crippling blizzard to Boston.
The record cold snap also impacted the construction industry. Delivery delays, the inability to apply weather sensitive applications (like cast in place concrete), and the unavailability of labor are just a few things that extreme weather can cause on a construction project. If they happen at the wrong time, delays can destroy project schedules and make previous delays even worse. Delays cost money and can mean the difference between a profitable project from both the owner and contractors perspective.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
BWB&O Expands to North San Diego
December 09, 2019 —
Bremer Whyte Brown & O’MearaBremer Whyte Brown & O’Meara is excited to announce our expansion to North San Diego County. Our new office location in Encinitas is strategically located between our Newport Beach and Downtown San Diego offices. The new North San Diego office will provide further resources to better serve our clients.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
SEC Approves New Securitization Risk Retention Rule with Broad Exception for Qualified Residential Mortgages
November 26, 2014 —
Neil P. Casey & Lori S. Smith – White and Williams LLPThe Securities and Exchange Commission (SEC) and five other federal agencies recently approved a joint rule (the “Risk Retention Rule”) mandating that sponsors of certain types of securitizations retain a minimum level of credit risk exposure in those transactions and prohibiting such sponsors from transferring or hedging against that retained credit risk.[i]The final Risk Retention Rule will be effective one year after its publication in the Federal Register for securitizations of residential mortgages, and two years after publication for securitizations of all other asset types. The SEC vote was 3-2, with sharp dissents from Commissioners Gallagher and Piwowar concluding that the adopting agencies had missed a prime opportunity to rein in risky mortgage lending practices that had precipitated the 2008 financial crisis.
Background
Following the meltdown of the securitization markets in 2007 (particularly subprime residential mortgage-backed securities), and the resulting global financial crisis, the Dodd-Frank Act mandated that the U.S. federal banking, securities and housing agencies adopt and implement rules to require sponsors of most new securitizations to retain not less than five percent of the credit risk of any assets that the securitizer, through the issuance of an asset-backed security, transfers, sells or conveys to a third party. It was thought that requiring securitization sponsors to keep “skin in the game” would align the interests of the sponsors with the interests of investors and thereby incentivize the sponsors to ensure the quality of the assets underlying the securitization through appropriate due diligence and underwriting procedures when selecting assets for securitization. Although the Dodd-Frank Act explicitly exempted securitizations of certain types of mortgage loans called “qualified residential mortgages” (or “QRMs”) from this risk retention requirement, it invited the rulemaking agencies to define that key term, provided that their definition could be no broader than the definition of “qualified mortgage”adopted by the Consumer Financial Protection Bureau (CFPB) pursuant to the Truth in Lending Act.[ii] In considering how to define QRM, the rulemaking agencies were directed by the Dodd-Frank Act to take into consideration “underwriting and product features that historical loan performance data indicate result in a lower risk of default.”[iii]
Reprinted courtesy of
Neil P. Casey, White and Williams LLP and
Lori S. Smith, White and Williams LLP
Mr. Casey may be contacted at caseyn@whiteandwilliams.com; Ms. Smith may be contacted at smithl@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
U.K. Puts Tax on Developers to Fund Safer Apartment Blocks
March 08, 2021 —
Emily Ashton & Olivia Konotey-Ahulu - BloombergThe U.K. announced an extra 3.5 billion pounds ($4.8 billion) toward the cost of stripping dangerous cladding from apartment blocks in England, with a new tax on developers from next year to help cover the costs.
Housing Secretary Robert Jenrick said the new cash will add to a previously announced 1.6 billion-pound “safety fund” to remove the material, which was blamed for the deaths of 72 people in a catastrophic fire at London’s Grenfell Tower in 2017.
A new tax will be introduced for U.K. residential developers in 2022 to raise at least 2 billion pounds over the next decade to ensure homebuilders “make a fair contribution” to solving the problem, Jenrick told the House of Commons on Wednesday.
Reprinted courtesy of
Emily Ashton, Bloomberg and
Olivia Konotey-Ahulu, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Florida Extends Filing Time for Claims Subject to the Statute of Repose
June 13, 2018 —
William L. Doerler - The Subrogation StrategistUnder Florida’s construction-related statute of repose, Fla. Stat. § 95.11, actions based on the design, planning or construction of an improvement to real property are barred if not commenced within 10 years after the later of several possible dates, including the date of actual possession by the owner and the date of the issuance of a certificate of occupancy. The Florida Legislature recently amended the statute to extend the time within which defendants subject to a suit filed close to the end of the 10-year period can file claims. Under the revised law, a defendant can file “counterclaims, cross-claims and third-party claims up to 1 year after the pleading to which such claims relate is served.” Regardless of when the cause of action at issue accrued, the law applies to actions commenced on or after July 1, 2018, except that any action that would not have been barred under Fla. Stat. § 95.11(3)(c) prior to the amendment may be commenced before July 1, 2019.
The revised law provides relief to defendants because, under the prior law, they had to file claims against other potentially responsible third parties before the expiration of the statute of repose. Under the new law, defendants can bring third parties into the action after the expiration of the 10-year statute of repose period.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Palm Beach Billionaires’ Fix for Sinking Megamansions: Build Bigger
June 14, 2021 —
Prashant Gopal & Amanda L. Gordon - BloombergThomas Peterffy became one of the world’s richest people by mastering risk on Wall Street. Building his Mediterranean-style mansion seven years ago on a vulnerable stretch of Florida’s Palm Beach Island was a matter of seeing the odds clearly once again. The consequences of climate change will play out over decades, and Peterffy is 76 years old.
“I don’t have a care about it at all,” he said over lunch at Mar-a-Lago earlier this year, just down the street from his home. The founder of Interactive Brokers Group has a fortune of more than $21 billion, according to the Bloomberg Billionaires Index.
“If something needs to be done to save it,” he added, “it’s not going to be my problem.”
The town of Palm Beach is busy adapting to the risks of a warming planet, even if there appear to be fewer worriers among the buyers and speculative builders on the island. Some of the lowest-lying properties in the U.S. are seeing the highest-flying prices. The real estate website Zillow estimates the value of Peterffy’s home at $52 million. This year a new nine-bedroom mansion with toes-in-the-sand views sold to financier Scott Shleifer for a record-breaking price in excess of $122 million.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal & Amanda L. Gordon, Bloomberg
California Court of Appeal Adopts Horizontal Exhaustion Rule
June 28, 2013 —
Tred Eyerly, Insurance Law HawaiiIn a long running suit regarding thousands of asbestos bodily injury claims brought against Kaiser Cement and Gypsum Corporation, the California appellate court held that the excess carrier's indemnity obligation did not attach until all collectible primary policies were exhausted. Kaiser Cement and Gypsum Corp. v. Ins. Co. of the State of Pennsylvania, 215 Cal. App.4th 210 (Cal. Ct. App. April 8, 2013).
Kaiser manufactured a variety of asbestos-containing products from 1944 through the 1970's. Truck Insurance Company provided primary insurance to Kaiser from 1964 to 1983, through four CGL policies covering 19 annual policy periods. The policy in effect from 1974 to 1981 contained a $500,000 "per occurrence" liability limit. Kaiser was insured by three other primary carriers between 1947 and 1987. ICSOP issued a first layer excess policy to Kaiser from 1974 through 1976.
Kaiser tendered numerous claims for bodily injury to Truck. By October 2004, Truck's indemnity payments exceeded $50 million and included at least 39 claims that resulted in payments in excess of $500,000. For claims alleging bodily injury in 1974, Kaiser selected Truck's 1974 policy to respond to each of the claims.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com