Shifting the Risk of Delay by Having Float Go Your Way
July 05, 2021 —
Christopher J. Brasco & Matthew D. Baker - ConsensusDocsCritical path delay plays a central role in allocating responsibility for project delay. The interrelated concept of concurrency is also frequently determinative of entitlement on a range of claims including by owners for liquidated damages and by contractors for delay damages. What constitutes critical/concurrent delay, however, is hotly debated by scheduling experts. The lack of real consensus regarding how critical/concurrent delay should be determined and analyzed has created significant uncertainty in scheduling disputes. Indeed, courts have adopted differing and at times conflicting theories of concurrency that can produce divergent outcomes for the parties. In an effort to reduce uncertainty, stakeholders have increasingly adopted specialized contractual provisions and scheduling techniques which have significant implications for the evaluation of the companion concepts of criticality and concurrency. One such mechanism is float sequestration. Regardless of whether float sequestration is ultimately in the construction industry’s broader interest, stakeholders must be able to recognize its use and appreciate the implications for delay disputes on their projects.
Simply defined, float is the number of days an activity can be delayed before affecting the project’s critical path (i.e., the longest chain of activities which determines the project’s minimal duration). Typically, only delays affecting the critical path can produce concurrent delay. Consequently, the concept of float is integral to understanding and resolving issues of both criticality and concurrency.
Reprinted courtesy of
Christopher J. Brasco, Watt, Tieder, Hoffar & Fitzgerald, LLP and
Matthew D. Baker, Watt, Tieder, Hoffar & Fitzgerald, LLP
Mr. Brasco may be contacted at cbrasco@watttieder.com
Mr. Baker may be contacted at mbaker@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Case Remanded for Failure to Meet Amount in Controversy
September 14, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court remanded to state court a loss of rent claim because the amount in controversy requirement was not met. Geragos & Geragos Fine Arts Bldg., LLC v. Travelers Indemn. Co., 2020 U.S Dist. LEXIS 127427 (C.D. Cal. July 20, 2020).
Geragos suffered loss of rental income due to the COVID-19 tenant relief measures implemented in Los Angeles. The tenant relief orders would remain in effect for the duration of the emergency period, the end date of which was not presently set.
Geragos submitted a claim for loss of rental income to Travelers. When the claim was denied, Geragos sued in state court. Travelers removed to federal district court. Geragos moved to remand the case back to state court for lack of subject matter jurisdiction.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Concrete Worker Wins Lawsuit and Settles with Other Defendant
December 04, 2013 —
CDJ STAFFHildo De Franca was injured in 2010 while pouring concrete for a residence in Perkasie, Pennsylvania. According to the lawsuit, when a concrete line plugged, the truck operator increased pump pressure, despite this not being the appropriate procedure. Mr. De Franca was injured when the hose snapped back after the clog burst free. Mr. De Franca sued both the Trans-Fleet Concrete Inc. and Albino Concrete Construction. Mr. De Franca was employed by a third party, Girafa Construction Inc., which had been hired by Albino.
Albino Construction settled with Mr. De Franca for $500,000. Trans-Fleet did not settle. The judgment against them was for $2.25 million, of which $2 million was for pain and suffering. As a result of the accident, Mr. De Franca suffered a mild brain injury and a compression fracture in his spine.
Read the court decisionRead the full story...Reprinted courtesy of
ABC Safety Report: Construction Companies Can Be Nearly 6 Times Safer Than the Industry Average Through Best Practices
May 06, 2024 —
Associated Builders and ContractorsWASHINGTON, April 30, 2024 (GLOBE NEWSWIRE) -- Associated Builders and Contractors today announced the findings from its
2024 Safety Performance Report, an annual guide to construction jobsite health and safety best practices. The report is unveiled to coincide with
Construction Safety Week, May 6-10.
The annual safety report also provides a comprehensive understanding of the impact of deploying
ABC's STEP Safety Management System, which enables top-performing ABC members to achieve incident rates 576% safer than the U.S. Bureau of Labor Statistics construction industry average. Established in 1989, STEP provides contractors and suppliers with a robust, no-cost framework for measuring safety data and benchmarking with peers in the industry.
ABC's research on more than 900 million work hours completed by participants in the construction, heavy construction, civil engineering and specialty trades in 2023 identified the following foundations of industry-leading safety best practices:
- Top management engagement: Employer involvement at the highest level of company management produces a 54% reduction in total recordable incident rates, or TRIR, and a 52% reduction in days away, restricted or transferred rates, or DART rates.
- Substance abuse prevention programs: Robust substance abuse prevention programs/policies with provisions for drug and alcohol testing where permitted lead to a 47% reduction in TRIR and a 48% reduction in DART rates.
- New hire safety orientation: Companies that conduct an in-depth indoctrination of new employees into the safety culture, systems and processes based on a documented orientation process experience incident rates that are 45% lower than companies that limit their orientations to basic health and safety compliance topics.
- Frequency of toolbox talks: Companies that conduct daily, 15-to-30-minute toolbox talks reduce TRIR and DART rates by 81% compared to companies that hold them monthly.
The 2024 ABC Safety Performance Report is based on submissions of unique company data gathered from members that deployed during the 2023 STEP term, Jan. 15-Dec. 15. ABC collects each company's trailing indicator data as reported on its annual Occupational Safety and Health Administration Form 300A ("Summary of Work-Related Injuries and Illnesses") and its self-assessment of leading indicator practices from its STEP application. Each data point collected is sorted using statistically valid methodology developed by the BLS for its annual Occupational Injuries and Illnesses Survey and then combined to produce analyses of STEP member performance against BLS industry average incident rates. The report demonstrates that applying industry-leading processes dramatically improves health and safety performance among participants regardless of company size or type of work.
Any company can participate in STEP. Visit abc.org/step to begin or continue your safety journey.
Read the court decisionRead the full story...Reprinted courtesy of
Gru Was Wrong About the Money: Court Concludes that Lender Owes Contractor “Contractually, Factually and Practically”
November 07, 2022 —
Matthew DeVries - Best Practices Construction LawThis weekend was all about
The Rise of Gru. I love Gru so much that when my children ask for money, my best Gru-like voice belts back: “Now, I know there have been some rumors going around that the bank is no longer funding us….In terms of money, we have no money.” And that’s precisely what many lenders say on distressed projects when the owner fails to make final payment and the contractor looks to the bank for funding: “We have no money for you contractor!”
In
BCD Associates., LLC v. Crown Bank, CA No. N15c-11-062 (Super. Ct. Del, May 2, 2022), the trial court found that when a bank pays a contractor directly, it can create a legally binding relationship subject to the terms of the construction loan agreements with the owner.
The project involved a $13m construction loan between the lender and the owner to renovate a hotel. The owner and contractor entered into an AIA Contract for the construction management services. During construction the contractor would submit payment applications to the lender, who would review and approve the invoices for payment. The lender then would pay 90% of the approved payment application and hold back the remaining 10% as retainage. The contractor was supposed to be paid the final retainage upon completion, which it did not receive in accordance with the terms of the AIA Contract.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Mass Timber Reduces Construction’s Carbon Footprint, But Introduces New Risk Scenarios
March 04, 2024 —
Michael Bruch & Franck Fumat - Allianz CommercialMass timber has the potential to be a critical building component for the cities of the near future given the need for the construction sector to reduce its reliance on concrete and steel to lower its Co2 emissions. However, as this market grows and mass timber buildings evolve to greater heights, the construction risk landscape will also be transformed, bringing risk management challenges for companies, according to the new Emerging Risk Trend Talk
report from Allianz Commercial.
“The emergence of mass timber as a sustainable construction alternative represents a significant opportunity for the building sector to reduce its carbon footprint while also satisfying a demand for a material that is more cost-efficient but as durable as steel and concrete,” says Michael Bruch, Global Head of Risk Advisory Services at Allianz Commercial. “However, in any industry, deployment of new materials or processes can result in new risk scenarios, potential defects, or unexpected safety consequences, as well as bringing benefits, and mass timber is no different. Given this market’s expected future growth, companies should do all they can to develop a greater understanding of their exposures including fire, water damage, repetitive loss scenarios and even termite infestation, and ensure they have robust loss prevention measures in place to combat these.”
The need for mass timber
The building and construction sector is among the largest contributors to Co2 emissions, accounting for over 34% of energy demand and around 37% of energy and process related Co2 emissions in
2021 [1]. Given emissions reduction is essential to meet climate change commitments around the world, the need for more sustainable solutions in the built environment has become increasingly important, driven by growing investor and consumer concerns, and legislation, regulation and reporting requirements evolving quickly in many jurisdictions around the world.
Read the court decisionRead the full story...Reprinted courtesy of
Allianz Commercial
Preliminary Notices: Common Avoidable But Fatal Mistakes
August 26, 2019 —
William L. Porter - Porter Law GroupIn the California building and construction industry, service of a “Preliminary Notice” is a prerequisite for Subcontractor and Supplier claims for payment through the Mechanics Lien, Stop Payment Notice and Payment Bond Claim process. Without proper drafting and service of a Preliminary Notice, these extremely valuable claims cannot be protected. Unfortunately, despite the vital importance of the Preliminary Notice, Subcontractors and Suppliers often make common self-defeating mistakes that make their Preliminary Notice efforts completely ineffective, resulting in loss of their claims rights. The purpose of this article is to list some of these common mistakes in the hope that the reader will avoid such mistakes, preserve the integrity of the Preliminary Notice, and protect the claims rights it makes available:
Not Sending out the Preliminary Notice Within 20 Days After Supplying Labor or Materials:
The protection of a Preliminary Notice begins 20 days before it sent out. This means that if a Subcontractor or Supplier claimant delivered $100,000 in materials on February 1, that same claimant must serve the Preliminary Notice on or before February 21 (the sooner the better), or the claimant will not be able to pursue an enforceable Mechanics Lien, Stop Payment Notice or Payment Bond claim for that $100,000. There are very few exceptions. Best practice: A Subcontractor or Supplier must send out the Preliminary Notice as soon as an agreement to provide work or materials to a California construction project is in place (See California Civil Code 8204).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Render Unto Caesar: Considerations for Returning Withheld Sums
January 18, 2021 —
William E. Underwood Partner, Jones Walker LLP - ConsensusDocsWithholding sums during a dispute can be an effective and perfectly legitimate means to protect against the harms caused by another party’s breach. However, withholding too much money during a dispute can turn a position of strength into one of weakness.
“Why should I fund the other side’s litigation war chest?” and “Isn’t this just a display of weakness?” are common questions raised by contractors when this issue is discussed. Often, the contractor is well within its contractual or legal rights to withhold money from a breaching subcontractor (another topic for another day). But it may not always be in a contractor’s best interest to withhold every single penny available.
This article addresses some of the long-term implications for failing to return withheld sums, including the potential to recover attorneys’ fees, possible bad faith, accruing interest, and overall litigation costs. Admittedly, it can be hard to give money back in the middle of a dispute. But sometimes it can positively impact the overall outcome of the case.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLP (ConsensusDocs)Mr. Underwood may be contacted at
wunderwood@joneswalker.com