Subsequent Owners of Homes Again Have Right to Sue Builders for Construction Defects
October 07, 2016 —
Mark L. Parisi – White and Williams LLPOwners of homes with damage from construction defects have long had the standing to sue the builders of their homes using the legal theories of 1) breach of contract, 2) breach of implied warranty, and 3) breach of Pennsylvania’s consumer fraud statute, the Unfair Trade Practices and Consumer Protection Law (UTPCPL).
Before the 2014 decision of the Pennsylvania Supreme Court in Conway v. Cutler, even owners who were not the original purchasers of their homes, so-called subsequent owners, had a right to sue the builder of their homes using implied warranty as the legal theory. But the Supreme Court in Conway said in 2014 that even though an implied warranty theory is not based on a written contract, it is a quasi contract theory and because subsequent owners never had a contractual relationship with the builder of their home, the implied warranty cause of action was not available. Subsequent purchasers were thus left without a remedy for damage from defective construction in their homes and builders had a second safe harbor from claims regarding homes they built. The first safe harbor is Pennsylvania’s Statute of Repose. If the home was completed more than 12 years before a lawsuit was filed, the Statute of Repose bars the claim. But after Conway, if the home was sold, this also cut off a builder’s potential liability for construction defects in the home.
ENTER THE UTPCPL
On July 26, 2016 the Pennsylvania Superior Court in the case of Adams v. Hellings Builders issued a non-published (and therefore non-precedential) decision in a stucco construction defect case that held that subsequent purchasers could sue their home’s builder under the UTPCPL because the Act had no requirement that the purchaser of a product, or home, be the original purchaser. The decision cites several other appellate cases not involving construction defect claims that held that the UTPCPL was a valid legal theory for claims regarding products purchased second hand by the plaintiffs in those other cases. The court in Adams held that there was no reason that a suit regarding construction defects in a home should be treated any differently.
Read the court decisionRead the full story...Reprinted courtesy of
Mark L. Parisi, White and Williams LLPMr. Parisi may be contacted at
parisim@whiteandwilliams.com
Hawaiian Electric Finalizes $2 Billion Maui Fire Settlement
November 18, 2024 —
Mark Chediak - BloombergHawaiian Electric Industries formalized a $2 billion agreement to settle damage claims from a wildfire that razed the historic town of Lahaina and killed more than 100 people.
The utility-owner had reached a tentative agreement in August in which it, along with other defendants including the state of Hawaii, Maui County and landowners, would pay $4 billion to resolve hundreds of lawsuits stemming from last year’s wildfire, according to a filing Tuesday.
The settlements don’t resolve claims with insurers that are part of separate lawsuits.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Chediak, Bloomberg
Finding Insurer's Declaratory Relief Action Raises Unsettled Questions of State Law, Case is Dismissed
November 05, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the District of Hawaii dismissed the insurer's action for declaratory relief because it raised issues that were unsettled by Hawaii courts. Association of Apartment Owners of Lahaina Residential Condominium, et al., No. 1-24-cv-00075-JAO-BMK, Order Granting AOAO's Motion to Dismiss (D. Haw. Aug. 29, 2024).
The case addressed whether a property damage exclusion barred coverage over an owner's claim that a condominium association and its property manager failed to obtain adequate insurance before the condominium's property was damaged by the Maui wildfire in August 2023. Great American filed suit seeking a declaration that it had no duty to defend or indemnify the Association and the property manage, Quam Properties Hawaiiana, Inc., in connection with a demand for mediation submitted to the Association and Quam on behalf of one of the owners.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Risk of A Fixed Price Contract Is The Market
August 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen performing work on a fixed price or unit, there is risk that is being assumed on your end. One risk is the market. You are ultimately banking on the fact that the market is not going to make your fixed prices unprofitable. That’s not an unforeseeable occurrence because the market shifts and that shift can have a negative ripple effect.
In a recent case out of the Federal Circuit, U.S. Aeroteam, Inc. v. U.S., 2022 WL 243176 (Fed.Cir. 2022), this market risk played a role in a fixed price contract. Here, a contractor was hired by the federal government to produce ground support trailers. A key component of these trailers was a running gear. The contractor relied on a vendor for these running gears. Due to financial difficulties, the vendor had to raise its unit price for the running gears. Based on the increased price, the contractor elected to manufacture the running gears itself. The contractor asked the government if this was ok and the government approved the request. Once the contractor started manufacturing these running gears, it had an “awe” moment – the manufacturing costs were higher than anticipated. The contractor submitted a request for equitable adjustment which the government denied. The Contractor than sued the government raising three arguments to support its entitlement to additional costs: (1) constructive change; (2) cardinal change; and (3) commercial impracticability. The contractor lost on all arguments. It probably should have lost on all arguments.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Florida’s Construction Defect Statute of Repose
August 24, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Butler Weihmuller of Katz Craig LLP discussed Florida’s 10-year statute of repose law: “Under § 95.11(3)(c), the action must commence within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.”
However, Weihmuller explains that parties may disagree on the specific date For instance, in Busch v. Lennar Homes, LLC, Florida’s 5th DCA recently “reversed a trial court’s dismissal of a homeowner’s construction defect claim that was filed just beyond 10 years after the closing date on the property.” The previous decision had been based on the notion that the contract had been completed upon the date of closing. The 5th DCA declared that “a contract is not completed until both sides of a contract have been performed” and “pointed to the ‘inspection and punch-list clause’ of the contract.” The clause indicated that “[a]ny remaining items that Seller has agreed to correct will be corrected by Seller at Seller’s sole cost and expense prior to closing or at Seller’s option within a reasonable time after closing.” Since not all punch-list items had been completed prior to closing, the 5th DCA held that the contract had not been completed at closing, and therefore the statute of repose did not begin until the punch-items had been accomplished.
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Citizen Suits, “Facility” Management and Some Nuance for Your Hazard Ranking
September 28, 2020 —
Anthony B. Cavender - Gravel2GavelSome very interesting and fairly complex environmental law rulings have been released in the past few days.
U.S. Supreme Court—Trump, et al. v. Sierra Club, et al.
On July 31, 2020, in a 5-to-4 decision, the Supreme Court denied a motion to lift the stay entered by the Court a few days earlier. The earlier action stayed a preliminary injunction issued by the U.S. District Court for the Northern District of California, which had enjoined the construction of a wall along the Southern Border of the United States which was to be constructed with redirected Department of Defense funds. The merits will be addressed by the lower court and perhaps the U.S. Court of Appeals for the Ninth Circuit.
U.S. Court of Appeals for the District of Columbia Circuit—Meritor, Inc. v. EPA
In a case involving EPA’s administration of the Superfund National Priority List (NPL) of priority Superfund sites requiring expedited cleanup, the court held that EPA had acted in accordance with the law and its implementing rules, and denied relief. Meritor was spun off from Rockwell Corporation, and is responsible for Rockwell’s environmental liabilities, including sites Meritor never operated. In 2016, EPA added the Rockwell International Wheel & Trim facility in Grenada, Miss., to the NPL list. Meritor alleged that this listing was arbitrary and capricious, pointing to EPA’s failure to adequately consider the impact of a mitigation measure added to the facility to address vapor intrusion, a factor EPA must consider in its application of the agency’s hazard ranking system. However, the court was not impressed by these arguments, and denied relief. The court’s discussion of the nuances of the hazard ranking system is very instructive
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Fracking Fears Grow as Oklahoma Hit by More Earthquakes Than California
July 09, 2014 —
Zain Shauk – BloombergSquinting into a laptop perched on the back of his pickup, Austin Holland searches for a signal from a coffee-can-sized sensor buried under the grassy prairie.
Holland, Oklahoma’s seismology chief, is determined to find the cause of an unprecedented earthquake epidemic in the state. And he suspects pumping wastewater from oil and gas drilling back into the Earth has a lot to do with it.
“If my research takes me to the point where we determine the safest thing to do is to shut down injection -- and consequently production -- in large portions of the state, then that’s what we have to do,” Holland said. “That’s for the politicians and the regulators to work out.”
So far this year, Oklahoma has had more than twice the number of earthquakes as California, making it the most seismically active state in the continental U.S. As recently as 2003, Oklahoma was ranked 17th for earthquakes. That shift has given rise to concern among communities and environmentalists that injecting vast amounts of wastewater back into the ground is contributing to the rise in Oklahoma’s quakes. The state pumps about 350,000 barrels of oil a day, making it the fifth largest producer in the U.S.
Read the court decisionRead the full story...Reprinted courtesy of
Zain Shauk, BloombergMr. Shauk may be contacted at
zshauk@bloomberg.net
Know What You’ve Built: An Interview with Timo Makkonen of Congrid
September 09, 2019 —
Aarni Heiskanen - AEC BusinessConstruction contains thousands of big and small tasks. How can a client and contractor know if they have all been completed as intended? Congrid offers an answer to that question.
Congrid is a Finnish construction software developer. The company provides software for punch lists, quality and safety audits, and design document distribution. It operates in Finland, Sweden, and the U.K.
The company’s founding team members, collectively, offer a combination of expertise in construction management, software development, and marketing and sales. “I come from the electronics industry. I came into this business through my old schoolmates,” says Timo Makkonen, Congrid’s CEO. “My specialty is business development and leadership.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi