Preventing Acts of God: Construction Accidents Caused by Outside Factors
September 20, 2017 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Seth Smiley. Seth, a native of Baton Rouge, is the owner of Smiley Law Firm. He is admitted to practice in all state and federal courts in Louisiana and California. Seth Smiley is the son of a general contractor, and acquired valuable work experience in the construction industry prior to entering law school. He earned his J.D. from Loyola, New Orleans in 2009. In his practice, Seth handles all aspects of construction cases, from initial contracting all the way to final payment once work is complete. Other areas of focus include commercial lease disputes, personal injury, business formation, and insurance property damage claims. Seth loves to fight insurance companies. Seth is currently the primary author of the Smiley Law Blog. The blogs primary focus is to provide value for current and prospective clients regarding trending legal issues in which the attorneys at Smiley Law Firm cover.
There are several factors a construction team can control on a job site. The foreman can ensure scaffolding is secure and that all employees are properly trained, and all workers can take steps to ensure a reasonably safe work site. Accidents can and will happen despite the best efforts of those involved.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
General Liability Alert: A Mixed Cause of Action with Protected and Non-Protected Activity Not Subject to Anti-SLAPP Motion
February 18, 2015 —
Valerie A. Moore, Lawrence S. Zucker II and Blythe Golay – Haight Brown & Bonesteel LLPIn Baral v. Schnitt (filed 2/5/2015, No. B253620), the California Court of Appeal, Second Appellate District, held that California’s anti-SLAPP statute does not authorize the striking of allegations of protected activity in a cause of action that also contains meritorious allegations of non-protected activity not within the purview of the statute. In so holding, the court attempted to resolve, or at least add its voice to, the growing conflict among appellate districts on the issue.
A SLAPP lawsuit (Strategic Lawsuit Against Public Participation) seeks to chill or punish the exercise of constitutional rights to free speech and to petition the government for redress of grievances. California’s Legislature enacted the anti-SLAPP statute to permit a defendant to file a special motion to strike as to any cause of action that arises out of an act in furtherance of such rights. In Baral, the plaintiff alleged that his business partner had violated fiduciary duties in usurping the plaintiff’s ownership and management interests in their jointly owned company, so that the defendant could benefit from a secret sale of the company. The complaint alleged that the defendant hired a public accounting firm and prevented the plaintiff from participating in its investigation in order to force the plaintiff's cooperation of the sale of the company. The defendant filed an anti-SLAPP motion, seeking to strike all references to the accounting firm's audit. The trial court denied the motion, on the ground that the anti-SLAPP statute applies to causes of action, not allegations.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Valerie A. Moore,
Lawrence S. Zucker II and
Blythe Golay
Ms. Moore may be contacted at vmoore@hbblaw.com.
Mr. Zucker may be contacted at lzucker@hbblaw.com.
Ms. Golay may be contacted at bgolay@hbblaw.com.
Read the court decisionRead the full story...Reprinted courtesy of
Court Dismisses Cross Claims Against Utility Based on Construction Anti-Indemnity Statute
August 14, 2018 —
David R. Cook - Autry, Hall & Cook, LLPWhen a plane crashed and several passengers and crew died or were injured, their representatives sued several defendants, including a nearby plant owner, Milliken & Company (“Plant Owner”), based on claims that transmission lines on Plant Owner’s property were too close to the runways, were too high, and encroached on the airport easements. Plant Owner cross claimed against utility owner, Georgia Power Company (“Utility”). Plant Owner’s claim was based on an easement it granted to Utility, which required Utility to indemnify it for any claims arising out of Utility’s construction or maintenance of the transmission lines.
In defense, Utility argued that the easement’s indemnity provision violated Georgia’s construction anti-indemnity statute.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Law Firm Settles Two Construction Defect Suits for a Combined $4.7 Million
October 25, 2013 —
CDJ STAFFConstruction Lawyers, LLP has announced that it has settled two Florida construction defect suits, both of which were filed by condominium associations. The first of these involved the Estates at Park Central Condominium Association, a 244-unit condominium complex in Orlando Florida. The condominium association alleged leaks into balconies and garages, and deficiencies in stucco application. After nearly three years since the filing of the lawsuit, and only weeks before the trial was to begin, the case was settled for $2 million.
The second case has also spent the last three years in mediation, however its trial date was further away. The Grand Venezia Condominium Owners Association alleged construction defects including leaking roofs and windows, and improperly installed stucco, leading to dry rot and water damage. The condominium community comprises 336 units in Clearwater, Florida and the units were originally built as apartments. Here, the settlement with the contractor was for $2.75 million. A lawsuit against the developer continues.
Read the court decisionRead the full story...Reprinted courtesy of
Builder’s Risk Coverage—Construction Defects
August 20, 2019 —
Brian Hearst - Construction ExecutiveThis is the second of three articles bringing clarity to the complex and challenging course of construction exposures and providing solutions for mitigating risk through builder’s risk insurance coverage. Part I, Builder’s Risk Coverage – Language Matters, addressed a select few critical exposures to projects under the course of construction. Part II addresses how a standard builder’s risk policy may respond to a loss arising from defective construction and alternative insurance market offerings that can help with specific costs associated with construction defect loss.
Coverage for Loss Ensuing from Faulty Workmanship
Part I tackled the standard builder’s risk exclusion that applies to losses arising from faulty materials or workmanship. Traditionally, carriers do not have an appetite for covering a contractor’s failure to perform their work properly. There is one exception, which is coverage is available for ensuing loss – or the resulting damage to other property from faulty workmanship.
If the excluded cause of loss (i.e., faulty workmanship) causes resultant damage, the builder’s risk policy will cover the damages to the extent the peril of fire is covered. The ensuing loss exception limits the faulty work exclusion to costs directly related to repairing or replacing the faulty work.
For example, suppose faulty wiring work leads to a fire which damages part of a structure under construction. The faulty workmanship exclusion would apply to the actual faulty wiring work, but if fire is a covered peril under the policy (this is nearly always the case), the policy would respond to the structure’s fire damage.
Reprinted courtesy of
Brian Hearst, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Hearst may be contacted at
Brian.Hearst@lockton.com
2017 Susan G. Komen Race for the Cure
March 01, 2017 —
Haight Brown & Bonesteel LLPAs a part of our 80 acts of Kindness commitment, Haight has registered a team to walk/run in the Susan G. Komen Race for the Cure Event taking place Saturday, March 11, 2017 at Dodger Stadium from 7:00 a.m. - 11:30 a.m.
We have a great group of partners, associates, and staff joining the Haight team to walk or run in support of the Susan G. Komen Foundation. For over 30 years, the Foundation’s efforts have funded life-saving breast cancer research and provided support to the thousands of women and men battling the disease.
For 80 years, Haight Brown & Bonesteel has been one of California’s leading full service law firms. To commemorate our 80 years in business, we are giving back to the community. Throughout 2017, we will demonstrate our commitment to those in need through 80 different acts of kindness.
Read the court decisionRead the full story...Reprinted courtesy of
Haight Brown & Bonesteel LLP
Contractors Struggle with Cash & Difficult Payment Terms, Could Benefit From Legal Advice, According to New Survey
December 30, 2019 —
Christopher G. Hill - Construction Law MusingsGuest Post Friday is back with a post from my pal Scott Wolfe. Scott is the founder and CEO of Levelset, which is used by thousands of contractors to make payments fast and easy. Scott, previously a construction attorney himself, founded Levelset to even the $1 trillion construction playing field, and is on a mission to make payments less stressful for contractors and suppliers across the globe.
Getting paid in construction is slow, hard, and stressful, according to a survey conducted by Levelset & TSheets by Quickbooks that polled over 500 construction professionals. Half of the contractors surveyed complained that they did not get paid on time, which caused serious cash flow issues that negatively impacted their customer relationships and frequently forced them to dip into personal savings and lines of credit to keep their business afloat.
View the 2019 Construction Payment Report here.
Unfortunately, since the construction industry’s slow payment problems are well-documented, this sad reality isn’t too surprising. The findings, though, do demonstrate a massive cash crunch for the 1.5 million+ contractors in the United States, and underscores the importance of having legal help and counsel from a construction lawyer before, during, and after jobs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com