Construction Defect Leads to Death, Jury Awards $39 Million
November 27, 2013 —
CDJ STAFFA failure in the installation of a 13-ton concrete panel in Milwaukee County lead to the death of a 15-year-old boy in 201; two others were also injured. A lawsuit over this has concluded with the contractor, Advance Cast Stone, found culpable due to their concealing that the panel was not installed as prescribed. The incident happened at a parking garage operated by the county.
Advanced Cast Stone made the claim that the method they used to secure the panel had been approved by other in the project. The jury awarded $6.3 million to the estate of Jared Kellner, $1.5 million each to the young man who was injured, Eric Wosniki, and his parents. The county was also awarded $6 million for lost revenue in the parking garage and for repairs.
Read the court decisionRead the full story...Reprinted courtesy of
In Pennsylvania, Contractors Can Be Liable to Third Parties for Obvious Defects in Completed Work
July 10, 2023 —
Michael L. DeBona - The Subrogation StrategistIn Brown v. City of Oil City, No. 6 WAP 2022, 2023 Pa. LEXIS 681 (2023), the Supreme Court of Pennsylvania (Supreme Court) recently held that a contractor can be liable for dangerous conditions it creates even if the hazard is obvious or known by the property owner. In City of Oil City, the City of Oil City (Oil City) contracted with Harold Best and Struxures, LLC and Fred Burns, Inc. (collectively Contractors) to reconstruct the concrete stairs to the city library. Contractors completed their work at the end of 2011. In early 2012, Oil City received reports of issues with the stairs. Oil City notified Contractors that it considered the stairs dangerous and that Contractors’ defective workmanship created the condition. Neither Oil City or Contractors took any action to fix the stairs or warn of the danger and the stairs’ condition worsened with time.
On November 23, 2015, David and Kathryn Brown exited the library. Kathryn Brown tripped on one of the deteriorated steps, falling and striking her head. Kathryn suffered a traumatic head injury and passed away six days later. The Estate of Kathryn Brown and David Brown, individually (collectively, the Browns), sued Oil City as the owner of the library and Contractors. With respect to Contractors, the Browns asserted that Contractors’ work on the stairs created a dangerous condition that presented an unreasonable risk of harm to those using the steps.
Read the court decisionRead the full story...Reprinted courtesy of
Michael L. DeBona, White and WilliamsMr. DeBona may be contacted at
debonam@whiteandwilliams.com
¡AI Caramba!
January 07, 2025 —
Daniel Lund III - LexologyYou can’t make this up.
That’s what a federal judge in Texas told an attorney whom it was sanctioning for impermissible reliance on artificial intelligence in preparing a brief to the court.
“Pending before the court is the question of whether Plaintiff's counsel… should be sanctioned for submitting a response brief to the court that includes case cites generated by artificial intelligence that refer to nonexistent cases as well as to nonexistent quotations.”
Counsel for the defendant in the case – pursuing summary judgment for a tire manufacturer in a wrongful termination lawsuit – pointed up in a reply brief that the opposition brief of the plaintiff cited two purported – and as it turned out, nonexistent – unpublished decisions: Roca v. King's Creek Plantation, LLC, 500 F. App'x 273, 276 (5th Cir. 2012) and Beets v. Texas Instruments, Inc., No. 94-10034, 1994 WL 714026, at *3 (5th Cir. Dec. 16, 1994), and quotations from as many as six other apparently-existing cases but which were unable to be found within the reported decisions.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Recycling Our Cities, One Building at a Time
December 13, 2022 —
Aaron Clark & Erica Yokoyama - BloombergTakumi Osawa kneels on the narrow balcony of a wooden house outside Tokyo and describes how, 140 years ago, workers would have hoisted baskets of mulberry leaves to the second floor to feed silkworms. When they ate, it sounded like rain.
Known in Japan as minka, these locally crafted structures with characteristic pitched roofs were built for hundreds of years to accommodate farmers, artisans and merchants. This one was originally constructed in 1879 and housed a family on the first floor who tended silkworms on the second and third. Minka are typically designed like an interlocking puzzle, without nails or screws, which allowed Osawa and a team of craftsmen to take the building apart, move it about 90 kilometers (56 miles) east and reassemble it closer to Tokyo, where a couple now live in it.
The number of empty homes in Japan is rising as the population shrinks and younger generations gravitate toward the city. Government data suggests as many as 8 million houses, many built during a post-World War II construction boom that lasted into the 1980s, now lie unoccupied.
Reprinted courtesy of
Aaron Clark, Bloomberg and
Erica Yokoyama, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Clarifies When the Statute of Repose is Triggered For a Multi-Phase or Multi-Building Project
December 07, 2020 —
Jeffrey J. Vita & Anna M. Perry - Saxe Doernberger & Vita, P.C.Lennar Hingham Holdings, LLC (“Lennar”) built a twenty-eight-building, 150-unit condominium project containing twenty-four discrete phases over a seven-year span. The condominium association subsequently brought an action against Lennar and others alleging design and construction defects to four main components of the common elements: “decks and columns,” “roofing/flashing,” “exterior walls/flashing/building envelope,” and “irrigation system.” In response, the defendants argued that the plaintiff’s claims with respect to six of the twenty- eight buildings were barred by Massachusetts’s six-year statute of repose, G. L. c. 206 § 2B.
The United States District Court for the District of Massachusetts previously held that all twenty-eight of the condominium’s buildings should be treated as a single improvement for purposes of application of the statute of repose. Subsequently, the court certified the following question to the Massachusetts Supreme Judicial Court: Where the factual record supports the conclusion that a builder or developer was engaged in the continuous construction of a single condominium development comprising multiple buildings or phases, when does the six-year period for an action of tort relating to the construction of the condominium’s common or limited common elements start running?
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Anna M. Perry, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at JVita@sdvlaw.com
Ms. Perry may be contacted at APerry@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: An End-of-Year Environmental Update
January 09, 2023 —
Anthony B. Cavender - Gravel2GavelAs 2022 draws to a close, here is a brief description of recent environmental and regulatory law rulings, as well as new federal rulemaking proceedings.
United States Tax Court
Green Valley Investors, LLC et al, v. Commissioner of Internal Revenue
On November 9, 2022, the Tax Court agreed with the taxpayers that the IRS’s use of administrative Notice 2017-10 to impose substantial tax liabilities violated the Administrative Procedure Act (APA). The notice was the agency’s response to a provision in the American Jobs Creation Act of 2004 which increased the penalties for engaging in a reportable transaction understatement. Here, at issue was the value of charitable deductions generated by the creation of environmental easements made in connection with land transactions. These claimed deductions amounted to more than $60 million. The petitioners argued that IRS Notice 2017-10, which authorized such large penalties, was in fact a “legislative rule” whose promulgation should have complied with the notice and comment requirements of the APA. The agency contended that the Congress, by implication, absolved the IRS from the notice and comment requirements. The court agreed with the petitioners and set aside Notice 2017-10 and the imposition of penalties under Section 6662A of the Jobs Creation Act. On December 8, 2022, the IRS published a notice of proposed rulemaking that would correct the APA deficiencies noted by the courts. (See 87 FR 75185.)
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
A Classic Blunder: Practical Advice for Avoiding Two-Front Wars
August 23, 2021 —
William Underwood - ConsensusDocs“Ha ha! You fool! You fell victim to one of the classic blunders – the most famous of which is ‘never get involved in a land war in Asia’ – but only slightly less well-known is this: ‘Never go in against a Sicilian when death is on the line.’”[1]
Vizzini forgot to include “never fight a two-front war with your owner and a subcontractor” on his list of classic blunders, but it certainly belongs there. This article examines practical tips and tricks for general contractors to avoid the classic blunder of a two-front war, including recommended contract provisions and sound project documentation practices.
Admittedly, general contractors face a wide array of obligations on a project. And perhaps one of the most delicate balancing acts is managing relationships with the owner and your subcontractors. But far too often general contractors find themselves in the difficult position of fighting a two-front war against one (or more) of their subcontractors and the project owner.
But this does not always have to be the case—there are ways for general contractors to reduce the risk of finding themselves in a two-front war. And every project does not have to devolve in a circular firing squad with you in the middle. That said, this article comes with the caveat that a general contractor cannot avoid a two-front war in every instance, nor does this article examine every imaginable way to reduce the risk of a two-front war (see e.g. https://www.consensusdocs.org/pass-through-subcontractor-claims-liquidating-agreements-and-avoiding-a-two-front-war/). But this article will provide an overview of several key tools that can be used to minimize the risk of falling into a classic blunder.
Read the court decisionRead the full story...Reprinted courtesy of
William Underwood, Jones Walker LLPMr. Underwood may be contacted at
wunderwood@joneswalker.com
Appeals Court Explains Punitive Damages Awards For Extreme Reprehensibility Or Unusually Small, Hard-To-Detect Or Hard-To-Measure Compensatory Damages
November 10, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Nickerson v. Stonebridge Life Ins. Co. (No. B234271A, filed 11/3/16), (“Nickerson II”) a California appeals court outlined the requirements for complying with the single-digit multiplier annunciated as a Constitutional limitation on punitive damages by the United States Supreme Court in State Farm Mut. Automobile Ins. Co. v. Campbell (2003) 538 U.S. 408, for awards of punitive damages against insurers in cases of extreme reprehensibility or unusually small, hard-to-detect or hard-to-measure compensatory damages.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of