When Subcontractors Sue Only the Surety on Payment Bond and Tips for General Contractors
August 13, 2019 —
Ira M. Schulman & Emily D. Anderson - ConsensusDocsPayment bonds have been a staple of public construction projects since 1874, when the U.S. Congress first passed the Heard Act, which required that contractors obtain payment bonds for public projects to ensure that subcontractors and material suppliers have a way to recover their damages if an upstream contractor fails to pay for work performed and materials furnished on the project. The 1874 Heard Act has since been replaced by the 1935 Miller Act, and the concept has been expanded to construction projects funded by the states through state statutes known as “Little Miller Acts.” But the structure remains the same: On most public projects where the project’s cost exceeds $100,000, the prime contractor (the bond principal) is required to obtain a payment bond from a surety equal to the contract price to guarantee to subcontractors and material suppliers (the bond obligees) that the surety will pay for labor and materials under certain statutory or contractual conditions should the contractor fail to make payment.
A surety is jointly and severally liable with the contractor to the subcontractor, which means that the subcontractor may seek recovery against either the contractor or the surety or both, and the contractor and surety will be liable for the damages together. Put another way, in most states and in federal court, an unpaid subcontractor has the right to sue only the surety on the payment bond without joining the contractor because a contract of suretyship is a direct liability of the surety to the subcontractor.1 When the contractor fails to perform, the surety becomes directly responsible at once — it is unnecessary for the subcontractor to establish that the contractor failed to carry out its contract before the obligation of the surety becomes absolute.
Reprinted courtesy of
Ira M. Schulman, Pepper Hamilton LLP and
Emily D. Anderson, Pepper Hamilton LLP
Mr. Schulman may be contacted at schulmani@pepperlaw.com
Ms. Anderson may be contacted at andersone@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Court Clarifies Construction Coverage
June 28, 2013 —
CDJ STAFFThe Connecticut Supreme Court has recently ruled on a case in which breach of contract and bad-faith claims were made against an insurer in an construction defect case. Joseph K. Scully of Day Pitney LLP discussed the case in a piece on Mondaq.
Mr. Scully noted that the background of the case was that Capstone Building was the general contractor and project developer of a student housing complex for the University of Connecticut. Unfortunately, the building had a variety of problems, some of which were violations of the building code. Mr. Scully noted that the building had “elevated carbon monoxide levels resulting from inadequate venting, improperly sized flues.” Capstone entered into mediation with the University of Connecticut. Capstone’s insurer, the American Motorists Insurance Company (AMICO), declined involvement in the participation. Afterward, Capstone sued AMICO. The issues the court covered involved the insurance on this project.
The court addressed three questions. The first was “whether damage to a construction project caused by construction defects and faulty workmanship may constitute ‘property damage’ resulting from an ‘occurrence.’” The court concluded that it could “only if it involved physical injury or loss of use of ‘nondefective property.’”
The second question dealt with whether insurers were obligated to investigate insurance claims. The court, “agreeing with the majority of jurisdictions,” did not find “a cause of action based solely on an insurer’s failure to investigate a claim.” Under the terms of the contract, it was up to AMICO to decide if it was going to investigate the claim.
Thirdly, the court examined whether “an insured is entitled to recover the full amount of a pre-suit settlement involving both covered and noncovered claims after an insurer wrongfully disclaims coverage.” The court concluded that the limits are that the settlement be reasonable, the policy limit, and the covered claims.
Mr. Scully concludes that the decision will limit “the scope of coverage for construction defect claims” and “also imposes reasonable requirements on an insured to allocate a settlement between covered and noncovered claims.
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Court of Appeals Upholds Denial of Coverage Because Insurance Broker Lacked Agency to Accept Premium Payment
December 07, 2020 —
Lawrence J. Bracken II, Michael S. Levine & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn American Reliable Insurance Company v. Lancaster, the Georgia Court of Appeals reversed the denial of a property insurer’s summary judgment motion concerning the insurer’s denial of a fire loss claim. The basis of the denial was that the policyholders had failed to pay the policy premium. The policyholders, Charlie and Wanda Lancaster, claimed that they had paid their policy premiums for several years to their insurance agent, Macie Yawn. In October 2014, American Reliable mailed a renewal notice to the Lancasters notifying them that premium payments had to be made directly to the insurer. After it did not receive payment from the Lancasters, American Reliable sent them a cancellation notice in December 2014, again notifying them that payments be made directly to the insurer. The Lancasters denied having received either notice from American Reliable, but the record included a receipt for certificate of mailing.
After the Lancaster’s home burned down in 2015, American Reliable denied coverage on the grounds that the policy had been cancelled for nonpayment of premium. In the subsequent coverage action, the trial court denied American Reliable’s motion for summary judgment, ruling that a factual issue existed as to the actual and apparent agency of the insurance agent, Yawn. On appeal, the Court of Appeals found that the trial court erred in deciding that there was a factual issue concerning Yawn’s agency. Specifically, the Court of Appeals ruled that the record showed American Reliable had terminated Yawn’s agency to accept policy premiums, and that the Lancaster’s received notice of that termination in the renewal and cancellation notices. In addition to determining that Yawn was not an actual agent, the Court held that Yawn did not have apparent agency, because the notices sent to the Lancasters stated that the premium payment was to be paid to American Reliable, not to the agent.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
More on the VCPA and Construction
February 01, 2023 —
Christopher G. Hill - Construction Law MusingsI have posted before regarding the intersection between the Virginia Consumer Protection Act (VCPA) and construction contracting in regard to residential construction projects. A case out of the Eastern District of Virginia District Court further discusses this intersection as it relates to design contracts that also include the procurement and installation of certain design elements post-design. The basic facts of Marcus v Dennis are as follows:
In October of 2018, Defendant Marlene Dennis, the owner of Marlene Dennis Design, LLC (“MDD”), operating out of Virginia, entered into a contract to provide design services and the procurement and installation of certain design elements for the Plaintiffs, Gregory and Jamie Marcus, at their Maryland home. The Marcuses agreed to $175 per hour to Dennis with a cap of a total of $100,000.00 for design consultation and furniture selection and procurement. The Marcuses also agreed that they would pay no more than $250,000.00 for furnishings, rugs, artwork, decorative lighting, and accessories. In November 2020, Dennis sent an invoice for $68,000.00 and informed the Plaintiffs that the total contract fees would be more than the $100,000.00 cap. After paying $124,722.41 in design fees, the Plaintiffs received an invoice for $255,5560.72 in January of 2021. Despite the cap of $250,000.00, the Plaintiffs wired $255,000.00 to Dennis while requesting the backup invoices for the material charges. After much effort and a threat of litigation, the Plaintiffs received documents from Dennis showing that Dennis inflated the costs of the materials prior to passing the costs along to the Marcuses. The Plaintiffs’ home was unfurnished and empty as of April 10, 2021, and the Marcuses had to hire and pay another design team over $85,000.00 to finish Dennis’ work. Needless to say, the Marcuses sued both Dennis and her firm for breach of contract, breach of fiduciary duty, and for violation of the VCPA. Dennis moved to dismiss the Complaint.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
US Homes Face Costly Retrofits for Induction Stoves, EV Chargers
May 20, 2024 —
Kendra Pierre-Louis - BloombergBuyers of new homes in the US may find themselves saddled with electrical systems better suited to the 20th century than the 21st.
The International Code Council, which sets model construction standards for new homes, was expected to include building electrification measures in its 2024 energy code on March 20. But following appeals lodged by industry groups, the ICC board moved the measures to the code’s appendices, effectively making them optional, as first reported by the Huffington Post.
If new homes aren’t wired for increasing power needs from electric appliances and car chargers, it will bump the effort and cost of making such upgrades onto homeowners — a deterrent to going electric. Energy efficiency advocates say this could slow the pace of the energy transition, costing both jobs and the planet.
Read the court decisionRead the full story...Reprinted courtesy of
Kendra Pierre-Louis, Bloomberg
Fifth Circuit -- Damage to Property Beyond Insured’s Product/Work Not Precluded By ‘Your Product/Your Work Exclusion’
January 24, 2022 —
Anthony L. Miscioscia & Marianne Bradley - White and Williams LLPOn January 11, 2022, the United States Court of Appeals for the Fifth Circuit issued its decision in Siplast, Incorporated v. Employers Mutual Casualty Company, 2022 U.S. App. LEXIS 795 (5th Cir. Jan. 11, 2022), finding that an insurer had a duty to defend its insured in a construction defect case where the underlying complaint alleged damage to property beyond the product and work of the insured.
Siplast, Inc. (Siplast) had contracted with the Archdiocese of New York (the Archdiocese) to install a roof membrane system at a high school in the Bronx, New York. Id. at *1. As part of the contract, Siplast guaranteed that the roof membrane system would remain in a watertight condition for at least twenty years. Id. at *2. If it did not, Siplast would repair the roof membrane system at its own expense. Id.
Several years after the installation, the Archdiocese observed water damage in the ceiling tiles at the high school. Id. The Archdiocese contacted Siplast, who attempted to repair the damage and prevent further leaks; however, leaks and resultant damage continued to occur. Id. Siplast subsequently refused to make any more improvements to the roof. Id.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Marianne Bradley, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Bradley may be contacted at bradleym@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes, Being too Cute with Pleading Allegations is Unnecessary
June 06, 2018 —
David Adelstein - Florida Construction Legal UpdatesThere are times where being too darn cute with your pleading allegations is unnecessary and does not work. But, the point is really that the cuteness is unnecessary.
In a Miller Act payment bond dispute in Boneso Brothers Construction, Inc. v. Sauer, Inc., 2018 WL 2387833 (N.D.Cal. 2018), a claimant asserted claims against a Miller Act payment bond surety for breach of the payment bond, breach of a subcontract, open account, and account stated. The question is why would the claimant sue the payment bond surety for breach of subcontract (when the subcontract was not with the surety), and open account and account stated. I have no clue, other than such claims appeared quite unnecessary when the claimant asserted an action on the Miller Act payment bond (which is what the surety is liable under — actions under the statutory payment bond). Such claims were dismissed. And, they should have been.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case
August 04, 2011 —
CDJ STAFFOn July 28, the Washington Court of Appeals ruled in Clasen Fruit & Cold Storage v. Frederick & Michael Construction Co., Inc. that more than six years had passed since a contractor had concluded work and so granted a summary dismissal of the suit.
Frederick & Michael Construction Co., Inc. (F&M) was contracted to construct several buildings for Clasen Fruit and Cold Storage. These were completed in March, 1999. The buildings suffered wind damage to the roofs in 2001, 2003, 2005, and 2006. In the first two incidents, F&M repaired the roofs with Clasen paying for repairs.
In 2005, Clasen hired Continuous Gutter to make repairs. The final incident was the collapse of the roof of one building. This was attributed to “excessive moisture in the roof’s vapor barriers.” At this point, Clasen demanded that F&M pay for repair and replacement costs. In 2008, Clasen sued F&M for damages for breach of contract and negligent design and construction of the roof.
The decision then covered the meanings, in Washington law, of “termination of services” and “substantial completion.” The panel concluded that construction was “substantially completed in 1997” and “relevant services” by 2001. “But Clasen did not sue until 2008, some seven years after termination of any roof related services.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of