Court Clarifies Sequence in California’s SB800
December 20, 2012 —
CDJ STAFFAs California’s Right-To-Repair law, SB800, nears its ninth birthday, it has remained “largely untested in the legal system” as noted by Megan MacNee of Wood, Smith, Henning & Berman LLP on the site RealEstateRama. She writes that some homeowners have requested documents prior to filing a claim, which she describes as an attempt to “game the system,” and “analogous to requiring a party to litigation to comply with discovery before a complaint is filed.”
The court determined that homeowners may not request documents from the builder until they have actually filed a claim. The court noted that SB800 lacks any clear indication that homeowners may request documents before filing a claim (and also does not indicate that a builder would have to provide documents in these circumstances). The court concluded that the section that sets up the prelitigation procedures occurs before they section on documents discovery. “Because the document request is part of the prelitigation procedure, and the prelitigation procedure does not begin until the homeowner has served notice of a claim, it follows that there can be no prelitigation obligation to produce documents under section 912, subdivision (a) unless the homeowner has commenced the prelitigation procedure by serving notice of a claim.”
Read the court decisionRead the full story...Reprinted courtesy of
Lack of Workers Holding Back Building
May 10, 2013 —
CDJ STAFFBuilders are hiring again, or at least they’re trying to. According to an article in the Los Angeles Times, many of the workers who were laid off during the construction bust have gone on to work in other areas. John Nunan of Unger Construction told the Times that “we’re starting to see spot shortages of labor.”
One problem is that despite the boom, wages haven’t risen. Rising costs for materials and land have put an additional squeeze on builders. One building supervisor noted that during the boom, he was making $26 an hour and entry level workers $17. Now he earns $16 an hour.
From bust to recovery was about five years, and its labor pool could not just wait those years. Industry representatives told the Times that it has created a perception that construction is not a stable form of employment. Brian Turmail of the Associated General Contractors of America cited “pretty consistent news coverage about the fact that there are no jobs in construction.”
Read the court decisionRead the full story...Reprinted courtesy of
Wes Payne Receives Defense Attorney of the Year Award
September 30, 2019 —
Wesley Payne, IV - White and Williams LLPWes Payne was recognized by the Pennsylvania Defense Institute (PDI) as the Defense Attorney of the Year. The award was given at PDI’s Annual Conference held in Bedford Springs, PA on July 11th.
The annual award honors an attorney that “best exemplifies the qualities of professionalism, dedication to the practice of law, promotion of the highest ideals of justice in the community, and has a demonstrated commitment to PDI and its members.”
Wes has over 30 years of experience representing insurance carriers and insureds in first and third-party litigation matters. He is Chair of the firm's Diversity Committee, Co-Chair of the Pro Bono Committee and Chair of the firm's Homeless Advocacy Group. He also serves on several pro bono and civil boards and is active in several legal organizations, holding leadership positions with many of them.
Read the court decisionRead the full story...Reprinted courtesy of
Wesley Payne, IV, White and Williams LLPMr. Payne may be contacted at
paynew@whiteandwilliams.com
Homebuilding Down in North Dakota
October 30, 2013 —
CDJ STAFFOnly eleven new homes have been started this year in the Pierre area in North Dakota. Last year saw 35 homes built in the same area. Brad Lawrence, the Fort Pierre Director of Public Works, blamed last year’s Hurricane Sandy in New Jersey, stating that “superstorm Sandy has just devoured a tremendous amount of building projects.”
Area builders did say that some building materials went up in price after the storm, describing it as an “availability scare,” but some prices went down during the summer of 2013. Susan Ogan, of Neil Ogan Construction said that “our biggest thing is that people cannot find a lot they can afford and still say within their budget for the overall project.”
Although single-family homes aren’t being built, apartments are. “We’ve got a 24-unit apartment going in as we speak,” said Mr. Lawrence. That, some feel, may be responsible for the lack of demand for single-family homes.
Read the court decisionRead the full story...Reprinted courtesy of
Evaluating Smart Home Technology: It’s About More Than the Bottom Line
May 03, 2021 —
James W. McPhillips & Rachel Newell - Gravel2Gavel Construction & Real Estate Law BlogOutfitting a commercial real estate space with smart technology can be a significant cost. While the long-term benefits and strategic improvements we’ve discussed previously can make that investment worthwhile, the evaluation period is critical to ensure an impactful ROI. Property developers, owners, and managers should undertake a rigorous evaluation process to ensure the technology procurement aligns with the project’s overall financial plan. And this is not just about getting the cost right. If the technology does not meet the needs of the space, then all the smart technology in the world will not prevent the project from being a sunk cost.
Do the Research so You Know …
The Technology. While the RFP is a key step of the procurement process, a more informal research phase should be undertaken first. Smart technology is a rapidly evolving field, and before reaching out to vendors, the business should ensure that it understands what is available—both in terms of the kinds of technology that can be implemented, and the various companies that offer solutions. Gathering this information early will yield results that align more closely with a particular building’s needs.
Reprinted courtesy of
James W. McPhillips, Pillsbury and
Rachel Newell, Pillsbury
Mr. McPhillips may be contacted at james.mcphillips@pillsburylaw.com
Ms. Newell may be contacted at rachel.newell@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The International Codes Development Process is Changing to Continue Building Code Modernization
March 06, 2023 —
The International Code CouncilWashington D.C., March 02, 2023 (GLOBE NEWSWIRE) -- The International Code Council is revising its rigorous code development process. The changes will take effect in 2024-2026 for the development of the 2027 International Codes (I-Codes) and will move the development process to an integrated and continuous three-year cycle.
In the new timeline, year one will include two Committee Action Hearings for Group A Codes; year two will include two Committee Action Hearings for Group B Codes; and year three will be the joint Public Comment Hearings and Online Governmental Consensus Vote for both Group A and B Codes.
The addition of the second Committee Actions Hearings in year one and two will foster a more in-depth vetting of code change proposals, allowing an opportunity for the committee members to review and evaluate the original proposals and consider the submitted responses. This also provides more opportunity for proponents to build consensus for their code change proposal and ensure the best version of their intended improvement to the existing codes.
Additionally, with combined Public Comment Hearings in the third year, voting members are able to vote on all suggested changes to the next edition of the I-Codes at one time. The updated process also provides more opportunity for proposed new referenced standards to be developed and finalized on a consistent timeline regardless of the group (Group A or B) with which they are associated.
About the International Code Council
The International Code Council is the leading global source of model codes and standards and building safety solutions. Code Council codes, standards and solutions are used to ensure safe, affordable and sustainable communities and buildings worldwide.
Read the court decisionRead the full story...Reprinted courtesy of
Home Sales Going to Investors in Daytona Beach Area
December 11, 2013 —
CDJ STAFFHouses are selling quickly in the Daytona Beach, Florida area, but many of the buyers are investors who are buying up homes in hopes of selling them several years later. Maryke Guild, a real estate agent said that “in three, four years’ time, when the market has been resaturated, those guys are going to sell at a profit, there’s no doubt.” But while the housing market is good news for investors, it’s actually bad news for homebuilders.
“Flips are not what’s going to sustain the market,” said John Adams the general manager of the Adams, Cameron & Co., a Daytona-area real estate firm. Contractors are building new homes in the Daytona area, but the number of homes built in Volusia County in 2013 is a little more than a fifth of what was built in 2005. In adjacent Flagler County, homebuilding is at less than a tenth of what it was in 2004.
Read the court decisionRead the full story...Reprinted courtesy of
Arizona Supreme Court Holds a Credit Bid at a Trustee’s Sale Should Not be Credited to a Title Insurer Under a Standard Lender’s Title Policy To the Extent the Bid Exceeds the Collateral’s Fair Market Value
March 01, 2017 —
Richard H. Herold - Snell & Wilmer Real Estate Litigation BlogThe Arizona Supreme Court recently addressed what impact, if any, a lender’s credit bid at an Arizona trustee’s sale has on an insurer’s liability under Sections 2, 7 and 9 of the standard’s lender’s title policy (“Policy”), holding in Equity Income Partners, LP v. Chicago Title Insurance Company, 241 Ariz. 334, 387 P.3d 1263 (February 7, 2017) as follows:
1. Section 2 of the Policy, entitled “Continuation of Insurance,” not Section 9, entitled “Reduction of Insurance; Reduction or Termination of Liability,” applies when a lender acquires property at a trustee sale by “either a full- or partial-credit bid” since Section 2 directly addresses the existence and amount of coverage in such circumstances. Id. at 1267.
Read the court decisionRead the full story...Reprinted courtesy of
Richard H. Herold, Snell & WilmerMr. Herold may be contacted at
rherold@swlaw.com