Be Careful with Continuous Breach and Statute of Limitations
January 21, 2019 —
Christopher G. Hill - Construction Law MusingsIf you are a construction attorney like me (or anyone that takes cases to court), you deal with statutes of limitation on a daily basis. These statutes seem pretty simple. A party has “X” amount of time in which to file its lawsuit after accural of the cause of action. In a breach of contract suit, the accrual is the date of breach. Easy, right? Wrong, at least in some circumstances.
Take for example, the case of Fluor Fed. Sols., LLC v. PAE Applied Techs., LLC out of the 4th Circuit Court of Appeals. In this unpublished opinion the Court looked at “continuous breach” versus “series of separate breaches.” The basic facts are that in 2000 Flour entered into a contract with PAE whereby PAE requested and claims to have received consent from Flour to a 2.3% administrative cost cap on Flour’s work on an Air Force contract. Flour claimed that it did not agree to this cap. In 2002, Flour begain billing PAE for its costs plus the 2.3% administrative markup and billed in this fashion for the first full year. However, in subsequent years and for the next 11 years, Flour billed PAE at a higher markup rate than the 2.3%. PAE disputed the increased markup and paid Flour at the 2.3% rate. Flour periodically protested but made no move to court until it filed suit in March of 2016. After a bench trial, the district court found that Flour had agreed to the cap and found for PAE.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
New Jersey Supreme Court Holding Impacts Allocation of Damages in Cases Involving Successive Tortfeasors
March 28, 2022 —
Thomas Regan & Karley Kamaris - Lewis BrisboisNewark, N.J. (March 21, 2022) - Late in 2021, the Supreme Court of New Jersey addressed the issue of allocating damages in personal injury cases in which the plaintiff asserts claims against successive tortfeasors, such as medical malpractice in the treatment of a slip and fall injury caused by negligence. The decision in Glassman v. Friedel, 249 N.J. 199 (2021) overruled and replaced the long-held principles established in Ciluffo v. Middlesex General Hospital, 146 N.J. Super. 478 (App. Div. 1977) regarding successive liability. Ciluffo held that, when an initial tortfeasor settles before trial, the non-settling defendants in a successive tort were entitled to a pro tanto credit for the settlement amount against any damages assessed against them. The Superior Court of New Jersey Appellate Division in 2020, and the Supreme Court of New Jersey last year, abandoned that framework for one more consistent with statutory contribution law in the Garden State.
In Glassman v. Friedel, 465 N.J. Super. 436 (App. Div. 2020), the Appellate Division held that the application of the principles in Ciluffo in a negligence case has no support in modern jurisprudence, thus limiting its application. It rejected the holding in Ciluffo in light of the state legislature’s enactment of the Comparative Negligence Act, which requires juries to apportion damages between successive events and apportion fault among the parties responsible for each event. The appellate division went on to hold that a non-settling, successive tortfeasor may present proofs at trial as to the negligence of the settling tortfeasor, and that the burden of proof as to the initial tortfeasor’s negligence being the proximate cause of the second causative event indeed lies on the non-settling defendant. In sum, the appellate division in Glassman established steps the jury can use to determine successive tortfeasor liability, but largely treated it as one, attenuated incident.
Reprinted courtesy of
Thomas Regan, Lewis Brisbois and
Karley Kamaris, Lewis Brisbois
Mr. Regan may be contacted at Thomas.Regan@lewisbrisbois.com
Ms. Kamaris may be contacted at Karley.Kamaris@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Dispute Waged Over Design of San Francisco Subway Job
July 30, 2019 —
Erica Berardi - Engineering News-RecordContractor Tutor Perini Corp. is clashing with the San Francisco Municipal Transportation Agency over what the firm says are alleged design flaws that may push past December the completion of the already-delayed $1.6-billion Central Subway Project.
Read the court decisionRead the full story...Reprinted courtesy of
Erica Berardi, ENRMs. Berardi may be contacted at
BerardiE@enr.com
Real Estate & Construction News Round-Up (01/25/23) – Artificial Intelligence, Proptech Innovation, and Drone Adoption
February 14, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores new artificial intelligence tools and their projected impact on real estate agents, key trends driving proptech innovation, barriers to adopting drones in the construction industry, and more.
- Artificial intelligence (AI) has the potential to become an invaluable tool to streamline the selling journey of a property, empower buyers to make informed decisions, and enhance the work of real estate agents. (Alexandra Cain, The Urban Developer)
- Miami real estate agents experiment with the new artificial intelligence tool, ChatGPT, which can generate text based on simple prompts, to write house listings, communicate with developers, and produce content. (Martin Vassolo, Axios)
- Asset owners in Asia and Europe turn to artificial intelligence to collect ESG information across public and private markets, including from residential buildings in Japan. (Hugo Cox, Asian Investor)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Ethical Limits on Preparing a Witness for Deposition or Trial
October 28, 2024 —
Stu Richeson - The Dispute ResolverIn this week’s blog post, we are going to take a brief look at ethical issues associated with preparing a witness for a deposition or to testify at trial. Most attorneys would agree that it is permissible to meet with a witness before the witness’s deposition to discuss what to expect. On the other hand, there is no question that advising a witness to provide false testimony would be improper. But what about the area in between those two extremes? For instance, can an attorney suggest to a witness how to phrase answers to anticipated questions that, while true, might not be the way the witness would have answered the question absent the attorney’s coaching?
A little over a year ago, the American Bar Association Standing Committee on Ethics and Professional Responsibility issued ABA Formal Opinion 508: The Ethics of Witness Preparation. The opinion provides certain examples of things that are and are not permissible in preparing a witness for a deposition or trial.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
PPP Loan Extension Ending Aug. 8
August 03, 2020 —
Construction ExecutiveThere is just over one week left to apply for the extended period of the Paycheck Protection Program, which will accept new applications through Aug. 8. Congress extended the legislation by unanimous consent on June 30 and President Trump signed the bill into law on July 4, 2020, allowing approximately $131.9 billion in funding to remain accessible to small businesses affected by the COVID-19 pandemic.
Associated Builders and Contractors has expressed support for several changes to the PPP, but submitted comments on July 27, 2020, to the U.S. Department of the Treasury and U.S. Small Business Administration regarding changes to an interim final rule altering loan forgiveness and loan review procedures. ABC urges the government agencies to:
- Provide further guidance on when businesses should apply for loan forgiveness and when they are notified of their forgiveness status.
- Issue further guidance on the PPP audit process.
- Increase flexibility for employee retention requirements and loan forgiveness.
- Provide further clarification of non-payroll costs.
- Refocus efforts to deliver PPP funds to underserved communities and minority businesses.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Gibbs Giden is Pleased to Announce Four New Partners and Two New Associates
January 08, 2024 —
Gibbs Giden Locher Turner Senet & Wittbrodt, LLPWe take great pleasure in announcing that
Richard Marks and
Kyle Marks have joined the firm. They bring a combined 60 years of real property law experience to Gibbs Giden. Well known Title Insurance and seasoned real estate attorneys they have both served as chair of the Title Insurance Subsection of the Los Angeles County Bar Association and are adjunct professors at Southwestern University School of Law. We are excited to welcome these two exceptional partners and their commitment to representing clients with honesty, integrity, and excellence. You can find them in our firm’s Westlake office.
Talented attorneys
Samantha Riggen and
Christopher Trembley have been named partners. Samantha represents clients in all areas of business and commercial matters with an emphasis on construction litigation on both public and private projects. Christopher’s practice also focuses on construction litigation on behalf of a wide spectrum of industry-stakeholder clients, including suppliers, contractors, and owners. Both work in our firm’s Westlake Village office.
We are also pleased to announce we’ve hired two new associates.
Sarah La Mendola and
Madison Wedderspoon. Sarah has developed an expertise in a wide range of real estate, business, and corporate matters. She received her JD from the University of Pavia, one of the top universities in Italy, in 2012 and her LLM from UCLA in 2015. You can find Sarah in our Westlake Village office. Madison recently graduated from the Boyd School of Law cum laude, is based in our Las Vegas office and works in the areas of business law, contracts, healthcare law, construction, real estate, and common interest community transactional and litigation work.
Read the court decisionRead the full story...Reprinted courtesy of
Gibbs Giden
Rhode Island Affirms The Principle That Sureties Must be Provided Notice of Default Before They Can be Held Liable for Principal’s Default
August 21, 2023 —
Dennis Cavanaugh & Tasnuva Islam - Construction Law ZoneMost bond forms in use today, including the standard form AIA A312-2010, contain express condition precedents that trigger a surety’s obligations under the bond. Under a performance bond, the bond obligee is required to provide formal notice to the surety that the principal has materially defaulted and that the surety must begin to perform under the terms of the bond. This principle is grounded in the idea that the surety should have an opportunity to address the default and investigate the claim so as to mitigate its own liability. Failure to provide sufficient notice will discharge the surety of its obligations under the bond.
Reprinted courtesy of
Dennis Cavanaugh, Robinson & Cole LLP and
Tasnuva Islam, Robinson & Cole LLP
Mr. Cavanaugh may be contacted at dcavanaugh@rc.com
Ms. Islam may be contacted at tislam@rc.com
Read the court decisionRead the full story...Reprinted courtesy of