New Jersey Supreme Court Holding Impacts Allocation of Damages in Cases Involving Successive Tortfeasors
March 28, 2022 —
Thomas Regan & Karley Kamaris - Lewis BrisboisNewark, N.J. (March 21, 2022) - Late in 2021, the Supreme Court of New Jersey addressed the issue of allocating damages in personal injury cases in which the plaintiff asserts claims against successive tortfeasors, such as medical malpractice in the treatment of a slip and fall injury caused by negligence. The decision in Glassman v. Friedel, 249 N.J. 199 (2021) overruled and replaced the long-held principles established in Ciluffo v. Middlesex General Hospital, 146 N.J. Super. 478 (App. Div. 1977) regarding successive liability. Ciluffo held that, when an initial tortfeasor settles before trial, the non-settling defendants in a successive tort were entitled to a pro tanto credit for the settlement amount against any damages assessed against them. The Superior Court of New Jersey Appellate Division in 2020, and the Supreme Court of New Jersey last year, abandoned that framework for one more consistent with statutory contribution law in the Garden State.
In Glassman v. Friedel, 465 N.J. Super. 436 (App. Div. 2020), the Appellate Division held that the application of the principles in Ciluffo in a negligence case has no support in modern jurisprudence, thus limiting its application. It rejected the holding in Ciluffo in light of the state legislature’s enactment of the Comparative Negligence Act, which requires juries to apportion damages between successive events and apportion fault among the parties responsible for each event. The appellate division went on to hold that a non-settling, successive tortfeasor may present proofs at trial as to the negligence of the settling tortfeasor, and that the burden of proof as to the initial tortfeasor’s negligence being the proximate cause of the second causative event indeed lies on the non-settling defendant. In sum, the appellate division in Glassman established steps the jury can use to determine successive tortfeasor liability, but largely treated it as one, attenuated incident.
Reprinted courtesy of
Thomas Regan, Lewis Brisbois and
Karley Kamaris, Lewis Brisbois
Mr. Regan may be contacted at Thomas.Regan@lewisbrisbois.com
Ms. Kamaris may be contacted at Karley.Kamaris@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Courthouse Reporter Series: The Travails of Statutory Construction...Defining “Labor” under the Miller Act
August 01, 2023 —
Brendan J. Witry - The Dispute ResolverIn a recent case—United States ex rel. Dickson v. Fidelity & Deposit Co. of Maryland (“Dickson”)—the U.S. Court of Appeals for the Fourth Circuit recently re-examined and defined what work qualifies as “labor” under the Miller Act.
United States ex rel. Dickson v. Fidelity & Deposit Co. of Maryland, No. 21-160, 67 F.4th 182 (4th Cir. April 26, 2023) (slip op.).
Unlike private projects, unpaid subcontractors cannot encumber the federal government’s property with mechanics liens. Instead, the Miller Act provides a remedy for subcontractors in the form of a payment bond on all federal public works contracts exceeding $100,000. 40 U.S.C. § 3131(b).
In the Dickson case, Claimant Elliot Dickson served as a subcontractor to Forney Enterprises (“Forney”), with whom the Department of Defense (the “DOD”) contracted to renovate several staircases and the fire suppression systems at the Pentagon.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Conway & Mrowiec Attorneys LLLPMr. Witry may be contacted at
bjw@cmcontractors.com
The Devil is in the Details: The Texas Construction Trust Fund Pitfalls Residential Remodelers (and General Contractors) Should Avoid
December 26, 2022 —
Rochelle Cabe & Roni Most - Kahana FeldA tale of Texas Construction Trust Account woe. You’re a contractor running a business doing interior remodels for clients in a major metropolitan Texas area. You sign up clients with a contract developed by our friends at LegalZoom and get your team to work. Three months into your remodeling project with Mr. and Mrs. “you thought they were happy” Clients, you get this letter:
“Consistent with the requirements of §162.006 and §162.007 of the Texas Property Code, Mr. and Mrs. “you thought they were happy” Clients demand a full and complete accounting of all funds you have received from any source relating to this project.”
What should you do? Should you ignore it? Should you respond? Fear sets in, you call your crew, and you stop the work. Mr. and Mrs. “you thought they were happy” Clients become Mr. and Mrs. “irate and angry” Clients and they sue you alleging breach of fiduciary duty, breach of contract, and perhaps fraud.
Reprinted courtesy of
Rochelle Cabe, Kahana Feld and
Roni Most, Kahana Feld
Ms. Cabe may be contacted at rcabe@kahanafeld.com
Mr. Most may be contacted at rmost@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Brown Paint Doesn’t Cover Up Construction Defects
April 25, 2012 —
CDJ STAFFIn a decision that describes the case as illustrating “the perils that real estate brokers and their agents assume when acting as a dual listing agent to both the buyers and sellers of the same house,” the California Court of Appeals has issued a decision in William L. Lyon & Associates v. The Superior Court of Placer County. Lyon & Associates sought summary judgment to dismiss the claims of the Henleys who bought a home in a transaction where a Lyon agent represented both sides.
The prior owners of the home, the Costas, had used a Lyon agent in purchasing their home. When they later sought to sell it, that agent “became aware of some of the house’s defects and problems.” In response, the Costas sought the help of another agent, Connie Gidal, also of Lyons & Associates. Photos taken in the presence of Ms. Gidal show defects of the paint and stucco. The Costas also took the step of painting the house dark brown. During the sale process, “rain caused many of the painted-over defects to reappear.” The Costas “purchased more dark brown paint and covered up the newly visible damage prior to inspection by the Henleys.”
With the damage concealed, the Henleys bought the home in May 2006. The agreement with Lyons & Associates noted that “a dual agent is obligated to disclose known facts materially affecting the value or desirability of the property to both parties.” Escrow closed on May 9, 2006. The contract with the broker included a two-year limit on the time to bring legal action.
The Henleys moved in during June 2006, and “began to discover construction defects that had been concealed by the Costas.” In addition to the painted-over stucco problems, the Henleys found that the Costas had “installed quartzite stone overlays on the backyard steps in a manner that caused water intrusion on the house’s stucco walls.”
In May 2009, the Henleys sued the Costas, Ron McKim Construction, Lyons & Associates, and Ms. Gidal. Their complaint alleged that Lyons & Associates had committed breach of contact, negligence, fraud, breach of fiduciary duty, and negligent nondisclosure in connection with the construction defects. The Costas named Lyons in a cross complaint. Lyons moved for summary judgments on the grounds that the two-year statute of limitations had expired before the complaint and cross-complaint were filed. Both the Henleys and the Costas opposed this claim. The court denied the motion and Lyons appealed.
The appeals court upheld the denial, noting that the both California Supreme Court decision and later action by the legislature compels real estate brokers and salespersons “to conduct a reasonably competent and diligent visual inspection of the property offered for sale.” The court noted that under California law, brokers have responsibilities to both sellers and buyers. The section of law cited by Lyons applies to seller’s agents. The court rejected the contention by Lyons that they were “cooperating brokers.” The Henleys were “not constrained by the two-year statute of limitations.”
Lyons contended that even if California’s statute did not apply, there was a contractual limit of two years. The court also rejected this, agreeing with the Henleys that “the two-year limitation period must be extended by the discovery rule.”
The court noted that “Lyon & Associates may not reap the benefit of a shortened contractual limitation period when its own alleged malfeasance contributed to the delay in the discovery of the buyer’s injury.” The court found that the Henleys could proceed with their breach of contract claim, because, “when a breach of contract is committed in secret, such as the intentional nondisclosure of a real estate broker regarding a previously visible construction defect, the contractual limitations period is properly held subject to the discovery rule.” The court felt that the interpretation favored by the California Association of Realtors would “halve the applicable statute of limitations period.”
In addition to rejecting Lyon request for summary judgment on the claims made by the Henleys, the court also rejected the request of summary judgment on the claims made by the Costas, concluding that neither claim is time-barred. Costs were awarded to both the Henleys and Costas.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
General Contractors Have Expansive Common Law and Statutory Duties To Provide a Safe Workplace
February 18, 2020 —
Paul R. Cressman Jr. - Ahlers Cressman & Sleight PLLCOn November 21, 2019, the Washington Supreme Court handed down its decision in Vargas v. Inland Washington, LLC.[1]
At the time of the incident in May 2013, Mr. Vargas, the plaintiff, was helping pour the concrete walls for what would become a parking garage for an apartment building. He was employed by Hilltop Concrete Construction. Inland Washington was the general contractor, and subcontracted with Hilltop to pour concrete. Hilltop, in turn, entered into agreements with Ralph’s Concrete Pumping and Miles Sand & Gravel to provide a pump truck, certified pump operator, and supply concrete.
A rubber hose carrying concrete whipped Mr. Vargas in the head. It knocked him unconscious and caused a traumatic brain injury.
Vargas, through his guardian ad litem, along with his wife and children, sued Inland Washington, Ralph’s, and Miles.
The trial court initially dismissed on summary judgment Vargas’ claims that Inland Washington was vicariously liable for the acts of Hilltop, Ralph’s, and Miles. Later, the trial court also granted Inland Washington’s motion for summary judgment that it was not directly liable as a matter of law.
Read the court decisionRead the full story...Reprinted courtesy of
Paul R. Cressman Jr., Ahlers Cressman & Sleight PLLCMr. Cressman may be contacted at
paul.cressman@acslawyers.com
First Trump Agenda Nuggets Hit Construction
January 26, 2017 —
Pam Radtke Russell, Mary B. Powers & Debra K. Rubin - Engineering News-RecordPresident Donald J. Trump began making good on campaign promises to put Americans back to work and reduce the size of government, as he signed orders and memoranda setting in motion approval of the Obama administration-halted Keystone XL and Dakota Access pipelines and streamlining of infrastructure and manufacturing permitting processes. But firms and watchdog groups are concerned how an announced freezing of government hiring and contracting will play out, as well as the future of environmental protection.
Reprinted courtesy of Engineering News-Record staff
Pam Radtke Russell,
Mary B. Powers and
Debra K. Rubin Read the court decisionRead the full story...Reprinted courtesy of
Ms. Rubin may be contacted at
rubind@enr.com
Foreclosure Deficiency: Construction Loan vs. Home Improvement Loan
November 12, 2019 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogIn a recent Arizona Court of Appeals case, Helvetica Servicing, Inc., v. Pasquan, 2019 WL 3820015, (8/15/19), the Court of Appeals addressed the distinction between (1) a construction loan (or refinance of same) and (2) a home improvement loan (or refinance of same), as it relates to Arizona’s anti-deficiency statute, A.R.S. §33-729(A).
In general, an anti-deficiency statute provides that although a purchase-money lender or a construction lender can – in appropriate circumstances – foreclose on their loan and cause a sale of the property to pay the loan, the lender cannot (if the statutory criteria are met) force the homeowner/borrower to pay the remaining balance still owed on the loan following the foreclosure (known as the deficiency). In other words, if the anti-deficiency rule applies, the lender’s sole remedy to collect on the loan is a foreclosure sale of the property; and the homeowner/borrower’s downside risk is loss of the property in foreclosure; the homeowner/borrower does not have any personal liability to pay the remaining unpaid balance of the loan post-foreclosure. In effect, the homeowner/borrower can simply walk away and not have to repay the loan.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
Lewis Brisbois Promotes 35 to Partnership
March 15, 2021 —
Lewis BrisboisLewis Brisbois is proud to announce the promotion of 35 of its associates to partner. With these promotions, Lewis Brisbois’ total partnership comes to 933 across its 53 offices. The diverse class of newly promoted attorneys includes 15 women, which brings the total percentage of female partners at Lewis Brisbois to 33%.
Los Angeles Managing Partner Jana I. Lubert expressed her excitement about the recent promotions, stating, “On behalf of the Management Committee, I congratulate these outstanding attorneys on their achievement. They have demonstrated an exceptional level of dedication to Lewis Brisbois and to our clients, especially during this difficult past year. I am particularly proud of the diversity that exists across this group.”
Similarly, San Bernardino and Chief Diversity Partner Rima M. Badawiya shared her enthusiasm over the diversity of the new partners, explaining, “This group of exceptional attorneys, who have been promoted based upon their extraordinary performance, represents the diversity that exists throughout Lewis Brisbois and our commitment to advancing those who achieve at the highest level.”
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois