Enforcement Of Contractual Terms (E.G., Flow-Down, Field Verification, Shop Drawing Approval, And No-Damage-For-Delay Provisions)
May 04, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhat you contractually agree to matters, particularly when you are deemed a sophisticated entity. This means you can figuratively live or die by the terms and conditions agreed to. Don’t take it from me, but it take it from the Fourth Circuit’s decision in U.S. f/u/b/o Modern Mosaic, Ltd. v. Turner Construction Co., 2019 WL 7174550 (4th Cir. 2019), where the Court started off by stressing, “One of our country’s bedrock principles is the freedom of individuals and entities to enter into contracts and rely that their terms will be enforced.” Id. at *1.
This case involved a dispute between a prime contractor and its precast concrete subcontractor on a federal project. The subcontractor filed a Miller Act payment bond lawsuit. The trial court ruled against the subcontractor based on…the subcontract’s terms! So, yes, what you contractually agree to matters.
Example #1 – The subcontractor fabricated and installed precast concrete panels per engineering drawings. However, the parking garage was not built per dimensions meaning the panels it fabricated would not fit. The subcontractor had to perform remedial work on the panels to get them to fit. The subcontractor pursued the prime contractor for these costs arguing the prime contractor should have field verified the dimensions. The problem for the subcontractor, however, was that the subcontract required the subcontractor, not the prime contractor, to field verify the dimensions. Based on this language that required the subcontractor to field verify existing conditions and take field measurements, the subcontractor was not entitled to its remedial costs (and they were close to $1 Million). Furthermore, and of importance, the Court noted that the subcontract contained a flow down provision requiring the subcontractor to be bound by all of the terms and conditions of the prime contract and assume those duties and obligations that the prime contractor was to assume towards the owner. While this flow-down provision may often be overlooked, here it was not, as it meant the subcontractor was assuming the field verification duties that the prime contractor was responsible to perform for the owner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
William Doerler Recognized by JD Supra 2022 Readers’ Choice Awards
March 14, 2022 —
William Doerler - White and Williams LLPCongratulations to Bill Doerler, Counsel of the Subrogation Group who has been recognized as a
top author in Product Liability in the 2022 JD Supra Readers' Choice Awards. Bill was ranked number 9 out of a pool of approximately 800 authors writing about product liability matters on JD Supra in 2021.
The Readers’ Choice Awards recognize top authors and firms for their thought leadership in key topics read by C-suite executives, in-house counsel, media and other professionals across the JD Supra platform during 2021. These annual awards (now in their seventh year) recognize JD Supra contributors for the visibility and engagement their thought leadership earned among readers in select subjects during the previous 12 months.
Read the court decisionRead the full story...Reprinted courtesy of
William Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Fifth Circuit Reverses Summary Judgment Award to Insurer on Hurricane Damage Claim
December 18, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit reversed the district court's grant of summary judgment to the insurer on a property damage claim arising from Hurricane Harvey. Advanced Indicator and Manufacturing, Inc. v. Acadia Ins. Co., 50 F.4th 469 (2022).
After Hurricane Harvey struck southern Texas in 2017, Advanced submitted a claim to Acadia for damage to its building that it claimed was caused by the hurricane's winds. Acadia sent an adjuster, Nick Warren, as well as an engineer, Jason Watson. Watson determined that pre-existing conditions - including ongoing leaks from deterioration and poor workmanship - caused the damage, rather than winds from Hurricane Harvey. Warren adopted these conclusions in his recommendations to Acadia. Acadia denied Advanced's claim based on these reports.
Advanced sued Acadia, alleging breach of contract and bad faith. Advanced filed a motion to remand to state court which was denied. Acadia moved for summary judgment arguing that it did not breach the policy and that Advanced could not segregate any damages caused by hurricane from pre-existing damage. The district court granted Acadia's motion, finding that Acadia's denial of Advanced's claim was based on "extensive consideration of the evidence." Further, Advanced failed to carry its burden of showing that covered and non-covered damages could be segregated as required by Texas's concurrent causation doctrine. Finally, the bad faith claim was dismissed because there was no breach of contract.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
#6 CDJ Topic: Construction Defect Legislative Developments
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFRichard H. Glucksman,
Jon A. Turigliatto, and
David A. Napper of
Chapman Glucksman Dean Roeb & Barger discussed Right to Repair developments occurring in Nevada, Arizona, Florida, and Colorado in their article, “Right to Repair Reform: Revisions and Proposals to State’s ‘Right to Repair Statutes.”
Read the full story...
Texas also had changes that affected construction defect claims, as covered by
David H. Fisk of
Coleman & Logan PC: “Before filing a lawsuit or initiating an arbitration proceeding pertaining to a construction defect, a condominium association in Texas with eight or more units must now comply with the newly added Section 82.119 to Chapter 82 of the Texas Property Code. This is in addition to compliance with the Texas Residential Construction Liability Act (RCLA) and any preconditions included in the condominium association’s declarations.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Nomos LLP Partner Garret Murai Recognized by Super Lawyers
July 08, 2024 —
Garret Murai - California Construction Law BlogNomos LLP Partner Garret Murai has been recognized as a 2024 Northern California Super Lawyers honoree in the area of Construction Litigation. This is the eleventh consecutive year that he has been recognized by Super Lawyers.
Super Lawyers, an annual listing of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and personal achievement, is limited to no more than five percent (5%) of lawyers in a state who are selected through a multiphase process that includes a statewide survey of lawyers, independent research evaluation and peer reviews by practice area.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Toward Increased Citizen Engagement in Urban Planning
November 14, 2018 —
Aarni Heiskanen - AEC BusinessDigitalization creates new opportunities for citizen engagement in urban planning. I gave a short presentation on the topic at the Digitalization in Urban Planning event in Helsinki.
The event was organized by CHAOS Architects, a tech company. Its AI cloud platform allows citizens to share ideas about their city and co-create it with their community. The platform contains engagement-driven applications and third-party APIs that process business intelligence for better interaction and decision-making.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Building Materials Price Increase Clause for Contractors and Subcontractors – Three Options
June 21, 2021 —
William L. Porter - Porter Law GroupWith the arrival of inflation come concerns regarding increases in the price of building materials within the construction industry. Contractors, subcontractors and others who contract to perform construction work can suffer significant losses when the prices they must pay for materials rises significantly between the time they sign the contract and actually purchase the materials. The general rule is that, unless there exists a contract clause allowing contractors or subcontractors to pass significant price increases for materials on to others, contractors and subcontractors are stuck with the price stated in the contract or subcontract. When prices rise, the contractor or subcontractor eats the difference. Rising prices can thus turn a profitable project into a catastrophic failure. How are contractors and subcontractors to protect themselves?
Once a contract is executed, there is usually little that can be done to change the document to address rising prices. Effort must therefore turn to future protection. The best technique for dealing with increasing future prices for building materials is by adding a price escalation clause to contracts and subcontracts. While this will not help for past contracts or subcontracts, it can certainly offer significant protection going forward.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Colorado Homes Approved Despite being Too Close Together
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFABC 7 reported that more than a dozen homes in Adams County, Colorado were inspected and approved by Building and Safety despite being built too close together. The problem was discovered by an inspector who cited a new home for being “4 inches too close to adjoining property.” Jim Williamette, the Adams County Chief Building Official told ABC 7, “It’s a fire issue for the separation of buildings.”
The county may have solved the issue, according to ABC 7. Williamette stated that the properties “will be modified with fire-resistant windows” and combined with the “already-installed fire-resistant siding, the windows will satisfy the international building code.” Currently, the parties are in verbal agreement, and a “signed design proposal” is expected no later than January 21st.
Read the court decisionRead the full story...Reprinted courtesy of