Eight Ways to Protect a Construction Company Before a Claim Is Filed
November 04, 2019 —
Mary Bacon - Construction ExecutiveClaims are inevitable in the construction industry. They can take on a life of their own and come with the burden of legal fees, wasted executive time and a possible judgment. Too often the only winners are the lawyers.
TIPS FOR PROTECTING MANAGEMENT AND THE BUSINESS BEFORE A CLAIM IS FILED
- Respect the business entity’s corporate structure. First and most importantly, respect the business entity’s corporate form. Legal entities have certain formalities like filing an annual list of officers, maintaining separate bank accounts, conducting certain meetings and following bylaws, etc. Respect these formalities. Failure to follow them exposes the owner to personal liability for company debts. And while a business claim has the potential to wipe out a business, owners should not risk having their personal assets on the line as well.
- Get a good contract. In most instances, a contract governs what happens and who is responsible for payment associated when a certain issue or dispute arises. A clear, well-written contract can often avoid a dispute or liability for a dispute. Actively participate in the contract negotiation and drafting process to make sure each party’s role and responsibilities are clearly accounted for.
- Make friends with clients. While it is true that “business is business,” people are often fairer and more willing to work towards a solution for people they are friends with. In most cases, friends will help friends in ways that people would not help mere business associates. When encountering a problem on a job, a friend may be willing to help achieve a more favorable outcome.
Reprinted courtesy of
Mary Bacon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Bacon may be contacted at
mbacon@spencerfane.com
What to Expect From the New Self-Retracting Devices Standard
November 29, 2021 —
Andre Pelland - Construction ExecutiveOne of the latest and most anticipated changes to occur this year relevant to fall protection is the publishing of the ANSI/ASSP Z359.14 2021 revision. Although the effective date isn’t until August 2022, this change is prompting the need for end user to prepare for using and understanding the new terminology performance requirements that will ultimately alter equipment selection criteria.
The reason for its relevance is mostly due to its industry dependence and the increasing popularity of these types of devices. This voluntary consensus standard accounts for a vast portion of the fall protection market equipment and has been adopted as the industry standard, even though it is not the legal requirement. To assure a smooth transition, the immediate priority should be to understand the changes and what it means from a usability standpoint. A clear understanding of what changes devices need to comply will allow users to proceed with a comprehensive transition plan.
What Are the Most Relevant Changes for the User?
Classes
The most significant changes are for Class A and B devices used to designate arrest distances and forces and the introduction of the Class 1 and 2 devices. These classes were known as designators for arresting falls at 24 inches and under with higher forces (Class A), and 54 inches and under with lower forces (Class B). Class 1 devices allow anchoring on overhead anchorages only and limitg freefall to no more than two feet.
Reprinted courtesy of
Andre Pelland, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Pelland may be contacted at
andre.pelland@puresafetygroup.com
Carrier Has Duty to Defend Claim for Active Malfunction of Product
October 19, 2020 —
Tred R. Eyerly - Insurance Law HawaiiRejecting that the underlying claim was based solely on faulty workmanship, the Third Circuit held the insurer had a duty to defend allegations of a malfunctioning product. Nautilus Ins. Co. v. 200 Christina Street Partners LLC, 2020 U.S. App. LEXIS 22118 (3d Cir. July 16, 2020).
The insureds were sued by homeowners in two separate suits alleging defects in the construction of their homes. Nautilus defended under a reservation of rights. Nautilus filed suit in District Court and moved for judgment on the pleadings. The District Court denied the motion, finding Nautilus had a duty to defend because the underlying claims sufficiently alleged product--related tort clams that could fall within the scope of coverage under the relevant policies.
The Third Circuit affirmed. There was a distinction between a claim of faulty workmanship, for which the insurer did not have a duty to defend, and a claim of "active malfunction" of a product, for which an insurer did have such a duty. An active malfunction was sufficiently fortuitous as to constitute an "occurrence."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
That Boilerplate Language May Just Land You in Hot Water
December 17, 2015 —
Kevin Brodehl – California Construction Law BlogThe following post originally appeared in my partner
Kevin Brodehl‘s informative blog,
Money and Dirt. If you’re involved in real estate investment, development and/or secured lending in California, it’s a must read. While Kevin’s post below discusses a case involving a real estate purchase agreement, it applies equally to construction contracts, perhaps even more so, since I can’t think of any other type of contract in which indemnity and integration clauses are as common, or as integral.
Almost all real estate purchase and sale agreements contain provisions relating to integration and indemnity.
In the “boilerplate” worldview, these provisions are standard, generic, and basically all the same — integration clauses prohibit extrinsic evidence that would contradict the terms of the agreement, and indemnity clauses force the seller to protect the buyer from third party claims arising after closing.
But a recently published opinion by the California Court of Appeal (Fourth District, Division Three in Santa Ana) — Hot Rods, LLC v. Northrop Grunman Systems Corp. — clarifies that integration and indemnity clauses can have vastly different effects depending on how they are drafted.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin Brodehl, California Construction Law BlogMr. Brodehl may be contacted at
kbrodehl@wendel.com
Combating Climate Change by Reducing Embodied Energy in the Built Environment
December 02, 2019 —
Brent Trenga - Construction ExecutiveThe building and construction industry is a significant consumer of non-renewable energy resources and is contributing to changing the earth’s environment in damaging and irreversible ways. These impacts are being felt in climate-related shifts that include increases in the earth’s average temperature and rising sea levels.
A new report by NASA and the National Oceanic and Atmospheric Administration shows that 2018 was the fourth-hottest year since 1880, the earliest year for which reliable global temperature data is available. The three hottest years on record were 2015, 2016 and 2017.
Additionally, the rise in sea levels is causing “nuisance floods” to become more common. From the 1950s to the early 2000s, the days of flooding in the 27 most vulnerable cities across the United States grew from two per year to nearly 12.
These and other environmental impacts underscore the urgency of battling climate change and how critical it is for all industries—including construction—to stem the tide on this issue.
Reducing embodied energy in the built environment is one way the building and construction sector can do its part to address one of the major challenges of this century.
Reprinted courtesy of
Brent Trenga, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Trenga may be contacted at
brent.trenga@kingspan.com
Court Finds that Subcontractor Lacks Standing to Appeal Summary Judgment Order Simply Because Subcontractor “Might” Lose at Trial Due to Order
May 03, 2021 —
Garret Murai - California Construction Law BlogCases sometimes take unanticipated twists and turns. Atlas Construction Supply, Inc. v. Swinerton Builders, Case No. D076426 (January 26,2021), involving a tragic construction accident, a motion for summary judgment, a motion for good faith settlement, and a stipulated dismissal, is one of those cases.
The Accident
Swinerton Builders was the general contractor on a residential construction project in San Diego, California. Swinerton contracted with J.R. Construction, Inc. to perform concrete work and with Brewer Crane & Rigging, Inc. to perform crane work on the project. J.R. Construction in turn rented a concrete column formwork approximately 10 feet tall and weighing 300 to 400 pounds from Atlas Construction Supply, Inc.
One day on the construction project, Marcus Develasco, Sr. and another co-worker, employees of J.R. Construction, climbed to the top of the formwork to adjust its size. The formwork, which had been positioned on the site by Brewer, was upright but unsupported by braces. When the co-worker stepped off the formwork, Develasco’s weight caused the unsecured formwork to topple over, killing Develasco in the process.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Can a Non-Union Company Be Compelled to Arbitrate?
August 02, 2017 —
Wally Zimolong - Supplemental ConditionsSome of the most viewed topics on this blog are those concerning double breasted company. That is a two separate firms, commonly owned, one that is a signatory to a union and the other that is merit shop.
An issue frequently encountered with double breasted construction companies is an union arbitrator’s jurisdiction over the non-signatory firm. The issue usually goes something like this. A signatory employer’s collective bargaining agreement contains language prohibiting double breasting (which could be invalid). The collective bargaining agreement also contains an arbitration provision requiring all disputes concerning a breach of the agreement (a grievance) be decided by an arbitrator in private arbitration. The union files a demand for arbitration claiming that the union signatory has breached the collective bargaining agreement’s anti-dual shop provision. The union names the non-union firm as a party to the arbitration based on its status as an alleged “single employer.”
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Replacement of Gym Floor Due to Sloppy Paint Job is Not Resulting Loss
January 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion for summary judgment finding damage to the gym floor due to a poor paint job was not a resulting loss. Bob Robinson Commercial Flooring, Inc. v. RLI Ins,. Co., 2023 U.S. Dist. LEXIS 196105 (D. Ark. Nov. 1, 2023).
Bob Robinson Commercial Flooring (BRCF) submitted a bid to the general contractor, Nabholz Construction Corporation, to install a vinyl athletic floor and striping at a middle school. The job also included the painting of a "Wildcat" logo the main gym floor. Therefore, BRCF's job was to install floors with proper painting and striping. Robert Liles and Robert Lines Parking Lot Services was the subcontractor hired to do the painting and striping. BRCF did not supervise or inspect Liles' work while it was ongoing.
Nabholz informed BRCF that there were problems with the floor painting, including crooked lines, incorrect markings, misplacement of the three point lines for the basketball surface, drips, smudges, etc. The gym floor was eventually rejected due to the nature of the vinyl flooring, once primer and paint were applied, the paint could not be removed and repainted. BRCF had to hire a new subcontractor to remove the flooring, install new flooring and then paint new lines. The cost for removal and replacement was $134,188.95.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com