Alleged Damage to Personal Property Does Not Revive Coverage for Construction Defects
November 23, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Illinois Appellate Court determined the general contractor was not covered for construction defects despite allegations of damage to personal property. Wesfield Ins. Co. v. West Van Buren, LLC, 59 N.E. 2d 877, (Ill. Ct. App. 2016).
The developer constructed a condominium development in Chicago. The installation of the roof was contracted to Total Roofing. Total Roofing agreed to insure and indemnify the developer against liability for Total Roofing's work. Total Roofing obtained a CGL policy with Westfield Insurance Company listing the developer as an additional insured.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Top Developments March 2024
April 22, 2024 —
Complex Insurance Coverage ReporterCLAIMS-MADE COVERAGE
Zurich Am. Ins. Co. v. Syngenta Crop Prot. LLC, 2024 Del. LEXIS 68 (Del. Feb. 26, 2024)
Delaware Supreme Court concludes that a letter from a lawyer informing an insured of possible lawsuits without identifying potential plaintiffs or demanding payment is not a “claim for damages” within the meaning of claims-made CGL and umbrella liability policies. Citing case law from Delaware and other jurisdictions, it reasoned that, in the ordinary sense, a “claim for damages” (which the policies did not define) is “a demand or request for monetary relief by or on behalf of an identifiable claimant.” According to the court, the letter in question did not meet this definition because it did not identify any claimants “except in the vaguest terms” or request monetary relief on any claimant’s behalf, but rather communicated only a threat of future litigation. As a result, the letter was not a claim made before the policy periods at issue.
POLLUTION EXCLUSION
Wesco Ins. Co. v. Brad Ingram Constr., 2024 U.S. App. LEXIS 1488 (9th Cir. Jan. 23, 2024)
A divided Ninth Circuit panel, applying California law, holds that a pollution exclusion* in a CGL policy does not preclude a duty to defend an underlying suit alleging physical injury from exposure to “clouds of toxic dust” deposited in the environment by a wildfire and released during clean up efforts. Citing MacKinnon v. Truck Ins. Exch., 73 P.3d 1205 (Cal. 2003), the majority explained that determining whether a “pollution event” (i.e., “environmental pollution”) resulting in excluded injury has occurred involves consideration of “the character of the injurious substance” and whether the exposure resulted from a “mechanism specified in the policy.” It concluded that a potential for coverage (and, therefore, a defense obligation) existed because, although wildfire debris may be considered a “pollutant” in certain circumstances, the mechanism alleged in the underlying complaint – “expos[ure] . . . to clouds of toxic dust during the loading and unloading of [the underlying plaintiff’s] truck” – did not clearly constitute an “event commonly thought of as pollution.”
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Nader Eghtesad v. State Farm General Insurance Company
September 28, 2020 —
Michael Velladao - Lewis BrisboisIn Eghtesad v. State Farm Gen. Ins. Co., 51 Cal.App.5th 406 (June 29, 2020), the California Court of Appeal reversed the trial court’s entry of judgment in favor of State Farm General Insurance Company (“State Farm”) based on an order sustaining a demurrer without leave to amend regarding a complaint filed by Nader Eghtesad. Mr. Eghtesad, representing himself, filed a form complaint checking a box for breach of contract. The complaint alleged two paragraphs contending that State Farm had acted in bad faith and concealed benefits due under a policy issued to a former tenant who rented space in a building owned by Eghtesad. Eghtesad was an additional insured under the tenant’s policy. In that regard, the building was damaged during the time that the building was rented and Eghtesad tendered a claim under the State Farm policy contending that he was an additional insured pursuant to the terms of the lease with the tenant. According to Eghtesad, State Farm advised him that he could only make a claim for slander against the former tenant and that coverage was not afforded for his property damage claim.
After Eghtesad filed his form complaint, State Farm demurred to the complaint and argued that it did not state facts supporting a cause of action for breach of contract. Ultimately, the trial court agreed with State Farm and entered an order sustaining the demurrer without leave to amend, such that a judgment was entered in State Farm’s favor. Due to health reasons, Eghtesad was never able to file an opposition to the demurrer, despite two extensions of time provided by the trial court intended to allow Eghtesad time to retain counsel and to recover from injuries sustained as a result of an automobile accident.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Scope of Alaska’s Dump Lien Statute Substantially Reduced For Natural Gas Contractors
March 16, 2020 —
Trevor Lane - Ahlers Cressman & Sleight PLLCIn All American Oilfield, LLC v. Cook Inlet Energy, LLC,[1] the Supreme Court of Alaska clarified and substantially reduced a natural gas contractor’s ability to secure a preferred lien for its contribution to a natural gas well.
Alaska’s dump lien statute (AS § 34.35.140) authorizes a laborer to claim a lien for the amount owed for their labor in the production of a “dump or mass” of “extracted, hoisted and raised” matter from a mine. While Alaska’s dump lien statute is one of three Alaskan statutes allowing laborers to attach liens to mines, mining equipment or minerals,[2] the dump lien statute is unique because it is prior and preferred over other liens, increasing the laborer’s chance of being paid in a bankruptcy proceeding.
Attaching a lien to a “dump or mass” of hard-rock minerals piled outside a mine or oil stored in a tank is relatively straightforward. However, natural gas is typically left in its natural reservoir until removed by a pipeline that carries the gas to a location far from the mine. Natural gas is not extracted and stored in a “dump or mass” like other minerals, and until August 2019, controversy existed over how—or if—the dump lien statute could be used by natural gas contractors.
Read the court decisionRead the full story...Reprinted courtesy of
Trevor Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
trevor.lane@acslawyers.com
Construction Delays: Which Method Should Be Used to Calculate Delay?
July 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf you need to prove and allocate construction project delays, you should engage a scheduling consultant qualified with CPM (critical path method) analysis. You should also engage counsel to assist in preserving your rights, as well as presenting and maximing your arguments for delay.
There are numerous methodologies used to quantify and allocate delay. You want to discuss the most effective analysis for your case and facts including whether you want/should use a forward-looking prospective analysis or a backward-looking retrospective analysis that factors in as-built data. In doing so, you want to make sure you understand the pros and cons of each methodology including the bases to attack the methodology that will be subject to cross-examination. The five primary CPM methodologies are as follows:
- As-Planned Versus As-Built. This methodology compares the as-planned baseline schedule to an as-built schedule reflecting progress to assign delay. An as-built schedule that reflects progress includes actual start dates, finish dates, and durations. The actual dates and durations are compared with the as-planned dates and durations on the baseline schedule to determine delay. Under this methodology, the delay impact is determined retrospectively.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Legal Landscape
June 17, 2024 —
David McMillin - Construction ExecutiveThe construction industry continues to change as new technologies reshape jobsites and new generations of leaders rethink the way companies should operate. But one piece of the puzzle remains very much the same: Everyone needs a good lawyer.
According to the most recent edition of the Arcadis Construction Disputes Report, the average value of a dispute in the industry has soared to $42.8 million—a 42% year-over-year increase between 2021 and 2022. And based on how busy the attorneys at
Construction Executive’s 2024 Top 50 Construction Law Firmshave been this year, there is no sign of legal issues becoming less important to builders and contractors.
Every construction leader wants to spend more time and energy doing what they do best—building projects safely, efficiently and profitably—and less time thinking about the things that might land them in court. How can you best avoid big disputes bound for mediation, arbitration or litigation? What emerging rules and regulations should be on your radar as you develop strategies for success?
While legal issues will never disappear, listening to what some of the best construction lawyers in the country—all members of 2024 Top 50 Construction Law Firms—are thinking about offers a helpful perspective on future-proofing your business against risk, liability and worse.
Reprinted courtesy of
David McMillin, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Get Away with Unwritten Contracts. . .
January 20, 2020 —
Christopher G. Hill - Construction Law MusingsI have spoken often regarding the need for a well written construction contract that sets out the “terms of engagement” for your construction project. A written construction contract sets expectations and allows the parties to the contract to determine the “law” of their project. An unwritten “gentleman’s agreement” can lead to confusion, faulty memories, and more money paid to construction counsel than you would like as we lawyers play around in the grey areas.
One other area where the written versus unwritten distinction makes a difference is in the calculation of the statute of limitations. In Virginia, a 5 year statute of limitations applies to written contracts while a 3 year statute of limitations applies to unwritten contracts. This distinction came into stark relief in the case of M&C Hauling & Constr. Inc. v. Wilbur Hale in the Fairfax, Virginia Circuit Court. In M&C Hauling, M&C provided hauling services to the defendant through a subcontract with Hauling Unlimited in 2014, the last of which was in July. M&C provided over 2000 hours of hauling and provided time tickets (that were passed to Mr. Hale on Hauling Unlimited letterhead and signed by Mr. Hale or his agent) and an invoice stating the price term of $75.00 per hour. No separate written contract between M&C and Hauling Unlimited or Mr. Hale existed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Re-Thinking the One-Sided Contract: Considerations for a More Balanced Approach to Contracting
November 21, 2022 —
William Underwood - ConsensusDocsConstruction projects can be inherently risky – often there are multiple parties (owners, architects, engineers, contractors, subcontractors, consultants, vendors, government officials, sureties, insurers, and many others), unforeseen site conditions, tangled supply chains, acts of God, inadequate funding, site safety matters, and a whole host of other issues that can make even a relatively straight-forward job complex. Parties necessarily want to minimize their individual risk to the greatest extent possible on construction projects. And to do so, they may seek to push as much risk as possible onto the other side through one-sided terms in their construction contract.
But is an entirely one-sided contract the best way to mitigate risk? In many instances, the answer is no. Every contract is different – and many considerations should be taken into account when drafting and negotiating contracts – but entirely one-sided can often have unintended consequences and create risks that otherwise might not exist in a contract that allocates and balances risk more equally across the parties.
This article reviews several considerations (although it is not an exhaustive list) for avoiding one-sided contracts, including some of the benefits created through the use of equitable contract clauses. And for context, some examples of one-sided contract clauses include no relief for other contractor/owner-caused delays; no relief for force majeure events; no relief for unforeseen site conditions; and broad form indemnification clauses (i.e. one party assumes the obligation to pay for another party’s liability even if the other party is solely at fault). Again, this is a non-exhaustive list, and many other standard contract provisions can be altered to become one-sided. But the general premise of a “one-sided contract clause” is that it shifts all risk, obligation, and liability to one party. And this article examines why that might not be the best idea.
Read the court decisionRead the full story...Reprinted courtesy of
William Underwood, Jones Walker LLPMr. Underwood may be contacted at