Dispute Review Boards for Real-Time Dispute Avoidance and Resolution
August 20, 2019 —
Neal J. Sweeney, Esq. - ConsensusDocsThe use of dispute tribunals generally referred to as Dispute Review Boards or DRBs on major projects has matured. Use of a DRB cannot guarantee elimination of post-project litigation, but when used properly, a DRB can be an enormously effective tool to avoid and resolve disputes rapidly and during construction.
The modest out-of-pocket costs of a DRB can pay big dividends. DRBs offer the opportunity to shorten the life cycle of a dispute by requiring the principals to confront and address the merits of their dispute, rather than simply hunkering down and focusing on posturing and preparing for arbitration or litigation. Even when a DRB cannot immediately resolve a dispute, the process can still facilitate subsequent settlement and cost-effectively prepare both parties for formal adjudication. DRBs can also enhance communications and help the parties avoid and resolve problems before they spiral into disputes.
DRBs were first and are most widely used on big civil and infrastructure projects, but the benefits of a DRB extend equally to major building projects, particularly hospitals, and industrial projects and should be used in those sectors.
Read the court decisionRead the full story...Reprinted courtesy of
Neal J. Sweeney, Esq., Jones Walker LLPMr. Sweeney may be contacted at
nsweeney@joneswalker.com
Contractor’s Charge Of Improvements To Real Property Not Required For Laborers To Have Lien Rights
June 13, 2018 —
Matt T. Paxton - Ahlers Cressman & Sleight PLLC BlogIn Washington, persons furnishing labor, professional services, material, or equipment for improvements of real property are generally entitled to a lien on that property, but only if their labor is furnished at the direction of the owner or the owner’s “construction agent.”[1] Whether a lien attaches, therefore, can turn on whether the person directing work is the owner’s construction agent. Washington’s mechanic’s lien statute defines “construction agent” as “any registered or licensed contractor, registered or licensed subcontractor, architect, engineer, or other person having charge of any improvement to real property, who shall be deemed the agent of the owner for the limited purpose of establishing the lien created by this chapter.”[2]
Read the court decisionRead the full story...Reprinted courtesy of
Matt T. Paxton, Ahlers Cressman & Sleight PLLCMr. Paxton may be contacted at
matt.paxton@acslawyers.com
Be Careful with Continuous Breach and Statute of Limitations
January 21, 2019 —
Christopher G. Hill - Construction Law MusingsIf you are a construction attorney like me (or anyone that takes cases to court), you deal with statutes of limitation on a daily basis. These statutes seem pretty simple. A party has “X” amount of time in which to file its lawsuit after accural of the cause of action. In a breach of contract suit, the accrual is the date of breach. Easy, right? Wrong, at least in some circumstances.
Take for example, the case of Fluor Fed. Sols., LLC v. PAE Applied Techs., LLC out of the 4th Circuit Court of Appeals. In this unpublished opinion the Court looked at “continuous breach” versus “series of separate breaches.” The basic facts are that in 2000 Flour entered into a contract with PAE whereby PAE requested and claims to have received consent from Flour to a 2.3% administrative cost cap on Flour’s work on an Air Force contract. Flour claimed that it did not agree to this cap. In 2002, Flour begain billing PAE for its costs plus the 2.3% administrative markup and billed in this fashion for the first full year. However, in subsequent years and for the next 11 years, Flour billed PAE at a higher markup rate than the 2.3%. PAE disputed the increased markup and paid Flour at the 2.3% rate. Flour periodically protested but made no move to court until it filed suit in March of 2016. After a bench trial, the district court found that Flour had agreed to the cap and found for PAE.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Florida Supreme Court Decision Limits Special Damages Presented to Juries
July 18, 2022 —
John A. Rine & Shannon Murphy - Lewis BrisboisTampa, Fla. (June 16, 2022) - Verdicts in personal injury cases are greatly impacted by the amount of medical expenses a plaintiff can present to juries. In Florida, collateral sources of compensation, such as insurance payments, are generally not disclosed to juries. However, caselaw also typically does not allow plaintiffs to recover the gross amount of medical bills, but instead the amount after insurance adjustments. For decades, Florida courts have considered whether the bills are reduced by the adjustments before or after verdict. The recent Florida Supreme Court decision in Dial v. Calusa Palms Master Association, Inc., No. SC21-43 (Fla. Apr. 28, 2022), has standardized the way past medical expenses are presented to juries where the plaintiff was treated under Medicare.
As is commonly understood, the original amount billed by medical providers is far different than the amount actually paid. Most treatment is subject to some private or government insurance and those insurers typically have negotiated rates for treatment. Thus, the bills are reduced subject to insurance contractual adjustments and the resulting net bills are far lower. For decades, defense attorneys have argued that juries should hear only the lower net amount.
Read the court decisionRead the full story...Reprinted courtesy of
John Rine, Lewis BrisboisMr. Rine may be contacted at
John.Rine@lewisbrisbois.com
The Secret to an OSHA Inspection
December 02, 2015 —
Craig Martin – Construction Contractor AdvisorWouldn’t it be nice to know ahead of time what an OSHA inspector will be looking for when he comes to your work site? Well, I know the secret. And, it’s not really a secret. Just look at OSHA’s top ten citation standards and it becomes quite clear.
In 2015, OSHA’s top ten most frequently cited violations are:
1. Fall protection (C)
2. Hazard communication
3. Scaffolding (C)
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Construction Lien Needs to Be Recorded Within 90 Days from Lienor’s Final Furnishing
March 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA lienor needs to record its construction lien within 90 days of its final furnishing date. This final furnishing date excludes punchlist, warranty, or the lienor’s own corrective work. A lien recorded outside of the 90-day window will be deemed invalid.
The opinion in In re: Jennerwein, 309 B.R. 385 (M.D. Fla. 2004) provides a good discussion of this 90-day window. This matter dealt with a debtor / owner’s bankruptcy where the owner was contesting the validity of a construction lien by its pool contractor. The owner contended that the lienor’s lien was recorded outside of this 90-day window thus rendering the lien invalid. The bankruptcy court was determining the validity of the lien.
In this matter, the owner hired a swimming pool contractor to construct a pool. On October 25, 2002, the pool contractor installed pavers around the pool. After this was performed, the pool contractor realized the owner was unable to obtain the financing to pay for the pool. As a result, the pool contractor ceased doing any more improvements. But, neither the pool contractor nor the owner terminated the contract. Then, on November 27, 2002, the pool contractor sent a supervisor to the property to inspect the pool (work-in-place), the pool equipment, the installed pavers, made a list of the unfinished work, and remove any debris. On January 27, 2003, the pool contractor recorded its lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
AGC’s 2024 Construction Outlook. Infrastructure is Bright but Office-Geddon is Not
February 12, 2024 —
Garret Murai - California Construction Law BlogThe Associated General Contractors of America has issued its
2024 Construction Outlook. According to its survey of construction contractors throughout the United States, contractors have a mixed outlook for 2024 with firms predicting transitions in the demand for projects, the types of challenges they will face and technologies they plan on embracing. According to the survey, contractors continue to cope with significant labor shortages, the impact of higher interest rates and input costs and a supply chain which, while better than in past few years, is still far from normal.
Of the 17 categories of construction types included in the survey, respondents expected a net positive growth in 14 of those categories, with infrastructure projects leading the net positive readings following the passage of the
Infrastructure Bill in 2021, and commercial retail and office leading the net negative readings as a result of the continuing
office-geddon:
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
When is Mediation Appropriate for Your Construction Case?
May 07, 2015 —
Christopher G. Hill – Construction Law MusingsHere at Construction Law Musings, I have often discussed mediation as a good alternative to the expense and headaches of litigation. What I have discussed less often are the circumstances in which it is most appropriate to consider or even push for mediation.
The obvious and clearest time that mediation must be used is where the contract requires it. Many construction contracts, including those from the AIA (when the parties check the appropriate box) require mediation as a prerequisite to arbitration or litigation. As is almost always the case in Virginia, this clause will be enforced. In short, if your construction contract has such a clause, and despite my reservations about “mandatory mediation,” you need to at least go through the process before moving forward with your construction claim.
The more interesting case is where no such clause exists and the parties reach an impasse, sometimes prior to litigation and often after the filing of a construction complaint or demand for arbitration. What questions should you as a construction attorney be asking both to and about your construction clients before attempting mediation?
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com