Insurer Able to Refuse Coverage for Failed Retaining Wall
October 28, 2011 —
CDJ STAFFThe Eleventh District of the US Court of Appeals has ruled in the case of Nix v. State Farm Fire & Casualty Company. In this case, the Nixes filed a claim after a portion of the retaining wall in their home collapsed and their basement flooded. State Farm denied the claim “on the ground that the policy excluded coverage for collapses caused by defects in construction and for damage caused by groundwater.”
The court reviewed the Nixes’ policy and found that State Farm’s statement did specifically exclude both of these items. In reviewing the lower court’s ruling, the appeals court noted that State Farm’s expert witness, Mark Voll, determined that the retaining wall “lacked reinforcing steel, as required by a local building code, and could not withstand the pressure created by groundwater that had accumulated during a heavy rainfall.” Additionally, a french drain had been covered with clay soil and so had failed to disperse the groundwater.
The Nixes argued that the flooding was due to a main line water pipe, but their opinions were those of Terry Nix and the contractor who made temporary repairs to the wall. “Those opinions were not admissible as lay testimony. Neither Nix nor the contractor witnessed the wall collapse or had personal knowledge about the construction of the Nixes’ home.”
The lower court granted a summary judgment to State Farm which has been upheld by the appeals court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects and Commercial General Liability in Illinois
October 25, 2013 —
CDJ STAFFNathan B. Hinch writes on his blog about construction defect law in Illinois. Mr. Hinch notes that he has been providing continuing legal education presentations about commercial general liability insurance and coverage of defective construction. In Illinois, for coverage to exist, “there must be ‘an occurrence’ that results in ‘property damage.’”
The Illinois courts have determined that “defective work is not an ‘accident,’ reasoning that the contractor intended to do the work, whether it turned out to be defective or not,” however the court “found that there was an ‘accident’ and therefore an ‘occurrence’ in a case where a contractor allegedly caused property damage by negligently backfilling around a residential basement.” And ‘property damage’ must be “damage to property other than the work.”
Read the court decisionRead the full story...Reprinted courtesy of
Golf Resorts Offering Yoga, Hovercraft Rides to the Green
June 18, 2014 —
Nadja Brandt – BloombergFlorida’s Woodmont Country Club, which once boasted 1,200 members, has been hit hard in the past decade as hurricanes and then the recession kept golfers away. Now the club’s owner is adding conference space, stores, restaurants, a spa and a hotel as part of a planned revival.
About $100 million will be spent on the revamp of the property in Tamarac, about 14 miles (23 kilometers) northwest of Fort Lauderdale, owner Mark Schmidt said. After years of negotiations with local authorities, he expects to receive approval this month for the planned Woodmont improvements.
While tennis courts and swimming pools have long had a place at golf clubs, a growing number of course owners are embracing mixed-use real estate, a concept more often used in urban developments to hedge risk and diversify returns. Property investors are adding everything from medical facilities to amphitheaters and hovercraft operations to increase revenue.
Read the court decisionRead the full story...Reprinted courtesy of
Nadja Brandt, BloombergMs. Brandt may be contacted at
nbrandt@bloomberg.net
COVID-19 Information and Resources
May 04, 2020 —
Richard H. Glucksman, Esq. & Brian D. Kahn, Esq. – Chapman Glucksman Dean & Roeb BulletinINTRODUCTION
The current COVID-19 health crisis has greatly impacted nearly every aspect of our business and personal lives. The constant flow of rapidly evolving, and often contradictory information creates its own challenges for those who are responsible for ensuring compliance with relevant regulations and best practices while still moving forward with their business and family activities.
This bulletin differs from most Chapman, Glucksman, Dean & Roeb bulletins in that it does not highlight a recent case, statute or a single development, but rather acts as a resource and “links” to provide you with needed information and to simplify your search for critical information during this unusual and challenging time.
CIVIL LITIGATION: CLOSURES AND RESTRICTIONS
The State and Federal Court systems in California have drastically reduced their operations. The Governor issued Executive Order N-38-20, this suspends certain limitations on the Chief Justice’s authority, making it possible for orders to be issued adapting the Court’s operations to address the COVID-19 health crisis. As of this time, the most recent statewide order from the Chief Justice is the March 30, 2020 Order which allows Courts to utilize remote technology when possible. The March 30, 2020 Order also clarifies a prior Order suspending all trials for 60 days. As many of you are aware, civil trials in California must commence within five years of the initiation of the action, this is commonly referred to as the “five year rule”. While the five year time period was initially extended by the Chief Justice for 60 days, the Judicial Council subsequently adopted a series of Emergency Rules, including one which extends this to six months for all civil actions filed on or before April 6, 2020. The Judicial Council also adopted rules tolling the statutes of limitation for civil causes of action are tolled from April 6, 2020 to 90 days after the state of emergency has ended.
In addition to the statewide orders and rules, counties have enacted their own rules. Los Angeles Superior Court, for instance, has closed some locations while others remain open on a limited basis. On March 17, 2020 an Order was issued limiting the Court to “essential functions” through April 16, 2020. However, on April 15, 2020, a further Order extended the closure through May 12, 2020. While truly urgent Ex Partes may go forward, all regularly set hearings will be continued until after June 22, 2020. Trials will begin after June 22, 2020 with non-priority trials anticipated to start in later August or September. Notably, any deadlines imposed by current trial or hearing dates still stand until the specific dates are continued.
As with other aspects of the COVID-19 health crisis, the impact upon Civil Litigation continues to evolve, for the most up to date information we include the following links to the California Courts. The first page includes links to all the State and County Orders, the second page is for the Judicial Council Rules.
Links:
https://newsroom.courts.ca.gov/news/court-emergency-orders-6794321
https://newsroom.courts.ca.gov/news/judicial-branch-emergency-actions-criminal-civil-and-juvenile-justice
STATE AND LOCAL STAY AT HOME ORDERS
The State of California declared a state of emergency on March 4, 2020. On March 13, 2020 the President declared a national state of emergency. On March 19, 2020 Governor Newsom issued Executive Order N-33-20, also known as the “Stay at Home” order. This orders all Californian’s to stay at home, unless they are part of an essential businesses are exempt which generally includes construction and insurance. Generally, Californians are allowed to run essential errands, but they are not to congregate with those outside of their household.
In addition to the State, many cities and counties have enacted additional orders regarding whether certain types of businesses can remain open, use of parks, trails and other public amenities as well as what type of protective measures must be adhered to such as covering your face in public. As with Civil Litigation, the State and Local Government regulations continue to evolve. A link to the State’s COVID-19 page is below and we also encourage you to check your local City and County sites for additional information.
https://covid19.ca.gov/
BUSINESS AND FINANCIAL GUIDELINES
The impact of COVID-19 is unprecedented. While “essential businesses” may remain open for customers, steps must be taken to protect the health of both employees and customers. There are both State and, in many instances, Local Government regulations addressing these precautions. In addition to taking safety measures to protect the health of all involved, there are a multitude of financial concerns to be addressed. While most people have already heard about the moratorium on residential and commercial evictions, this does little to address how property owners will receive funds to pay their financial obligations, how tenants can pay their other obligations, how either can make payroll and most importantly, how employees who can no longer work due to their “non-essential” business being closed can put food on their tables.
The Coronavirus Aid, Relief, and Economic Security Act (the “CARES” act) may provide financial relief for many business by means of loans, some of which may be forgivable, and tax credits. The CARES act also modifies the Family Medical Leave Act (“FMLA”) to provide paid leave for those who cannot work due to COVID-19 as well as other benefits. The IRS has extended the deadline to file and pay taxes to July 15, 2020. Additionally, there are other Federal and State benefits which may be available for those whose jobs are impacted.
The financial impacts of COVID-19 are far reaching and continue to evolve. The Department of Insurance ordered insurance companies to return premiums for at least the months of March and April. This applies to certain lines of insurance where the risk of loss has fallen substantially. However, business interruption, environmental and pollution claims have increased exponentially. While most such policies require some physical damage in order to trigger an occurrence, there has been some discussion of legislation deeming the COVID-19 pandemic to fulfill the physical damage requirement.
If your business has been closed or impacted by COVID-19 we encourage you to review your insurance policies and key contracts to ascertain what your rights and obligations are as well as whether you may have any coverage for your losses. Just as importantly, speak with your business partners including vendors, customers and employees to ascertain their capabilities and willingness to work through this crisis.
US Department of Labor OSHA Guidelines:
https://www.osha.gov/SLTC/covid-19/
California Labor & Workforce Development Agency Resource Page:
https://www.labor.ca.gov/coronavirus2019/
California Employment Development Department:
https://www.edd.ca.gov/about_edd/coronavirus-2019.htm
CONSTRUCTION GUIDELINES
Many of our clients are involved in the construction industry. Construction has been deemed an essential activity and is exempt from many of the “stay at home” orders but certain protections and regulations still apply. In addition to the general workplace guidelines discussed above certain jurisdictions are providing guidance as to how to provide a safe construction site workplace. We have included a link the Los Angeles Department Building and Safety guidelines below.
However, in some instances work on a project may be delayed or may not be able to progress due to the project owner stopping work or the inability of subcontractors or suppliers to continue as originally intended. In this case one should review their contracts to see what justifies delay and inability to perform by either party and the impact thereof. Contracts should also be evaluated to ascertain whether the costs associated with compliance with the new COVID-19 regulations are a recoverable cost under the contract. As with the general business discussion above, contractors should review all available insurance, including builder’s risk to ascertain the existence of possible coverage.
LA DBS guidelines:
https://ladbs.org/docs/default-source/publications/misc-publications/construction-site-guidance.pdf
SUMMARY
The COVID-19 health crisis has had and, for the foreseeable future, will have a broad and severe impact on our society. The variety of evolving regulations on the Federal, State and Local Government levels make it challenging to comply, especially for businesses in operation. There are also a variety of resources available to help ensure compliance with these regulations as well as the financial and physical viability of our communities’ companies and employees. Please do not hesitate to contact us if you need any assistance in navigating these rules and resources.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean & Roeb and
Brian D. Kahn, Chapman Glucksman Dean & Roeb
Mr. Glucksman may be contacted at rglucksman@cgdrlaw.com
Mr. Kahn may be contacted at bkahn@cgdrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Enforceability of “Pay-If-Paid” Provisions Affirmed in New Jersey
January 04, 2023 —
Levi W. Barrett, Michael S. Zicherman & Brian Glicos - Peckar & Abramson, P.C.On December 7, 2022, the Appellate Division affirmed the New Jersey Superior Court decision in Jersey Precast v. Tricon Enterprises, Inc. et al., finding that the “pay-if-paid” clause in a material supplier’s purchase order with a general contractor was binding and enforceable. While clauses conditioning a general contractor’s obligation to pay its subcontractors on the general contractor’s receipt of payment from the project owner are not unique – this is the first time that a court in New Jersey has affirmed this practice in a published opinion. [1]
Background
The general contractor, Tricon, sent Jersey Precast its standard form purchase order for the supply of prestressed box beams to fulfill a public improvement contract with Union County. The reverse side of the form purchase order contained standard terms and conditions, and included a pay-if-paid clause drafted by Michael Zicherman, a partner of Peckar & Abramson, P.C. While Jersey Precast provided some draft revisions to the terms and conditions, Tricon never signed the purchase order and the proposed revisions were never accepted. Significantly, Jersey Precast did not attempt to modify the pay-if-paid provision. It later developed that the construction of the project became impossible, and the beams fabricated by Jersey Precast were not used. Tricon invoiced Union County for the cost of the beams, but the County failed to make payment and refused to accept delivery of the beams.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Michael S. Zicherman, Peckar & Abramson, P.C. and
Brian Glicos, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Zicherman may be contacted at mzicherman@pecklaw.com
Mr. Glicos may be contacted at bglicos@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects as Occurrences, Better Decided in Law than in Courts
December 09, 2011 —
CDJ STAFFConstruction defect claims are now occurrences for insurance purposes in four states, Arkansas, Colorado, Hawaii, and South Carolina, yet there are still frustrations for commercial general liability policyholders. Business Insurance describes court decisions on whether construction defect claims are covered as “incongruous,” and this drives up coverage and litigation costs. Construction firms often find they are defending themselves on two fronts, both the construction defect claim and also whether their insurance covers it.
Frank Armstrong, the Senior Vice President and National Director of Construction Claims for Willis North America says that the problem starts with the word “occurrence,” as various state courts have different interpretations of the word. “Certain pieces of it don’t fit well, at lest according to some courts in the country, with coverage for construction defect risks.”
Another insurance executive, Julian Ehlich, the Senior Vice President of Claims for Aon Risk Solutions’ construction services group notes that “jurisdictions differ, so policyholders don’t know what they’re going to get.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Steel Component Plant Linked to West Virginia Governor Signs $1M Pollution Pact
January 04, 2023 —
Mary B. Powers - Engineering News-RecordBluestone Coke, a 100-year old Birmingham. Ala. factory that produces a key component in steelmaking and is partially owned by West Virginia Gov. Jim Justice, must pay nearly $1 million under a Dec. 9 state consent decree for violating federal clean air rules by releasing toxic emissions from coke ovens.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
2019 California Construction Law Update
January 15, 2019 —
Garret Murai - California Construction Law BlogThe California State Legislature introduced 2,637 bills during the second year fo the 2017-2018 Legislative Session. Of these, 1,016 were signed into law.
It was last official bill signing for Governor Jerry Brown who ends not only his second term as Governor but a colorful political career spanning nearly 50 years during which he has dated pop stars, practiced Zen meditation, kicked it with radical ex-nuns and an Apollo astronaut and, at 80, has sparred regularly with President Trump on issues ranging from climate change to immigration to net neutrality.
For those in the construction industry it wasn’t quite as exciting, unless of course you count SCR 120, which officially makes April “California Safe Digging Month.” Hooray!
Each of the bills discussed below took effect on January 1, 2018, except as otherwise stated.
Building Codes
SB 721 – Requires the inspection of exterior elevated elements, including balconies, decks, porches, stairways, walkways, and elevated entry structures, of multifamily buildings with three or more dwelling units by an architect, engineer or contractor with a Class A, B or C-5 license by January 1, 2025 and by January 1st every six years thereafter. Elements posing an immediate threat to the safety of occupants, or which prevent occupant access or emergency repairs, are required to be repaired immediately. Elements not posing an immediate threat to the safety of occupants, or which do not prevent occupant access or emergency repairs, are required to be repaired within 180 days.
Read the court decisionRead the full story...Reprinted courtesy of