Tokyo's Skyline Set to See 45 New Skyscrapers by 2020 Olympics
April 20, 2017 —
Gareth Allan & Katsuyo Kuwako - BloombergTokyo’s skyline is set to welcome 45 new skyscrapers by the time city hosts the Olympics in 2020, as a surge of buildings planned in the early years of Abenomics near completion.
Japan’s capital will see nearly 50 percent more new high-rise space in the next three years than it did in the preceding three, Toyokazu Imazeki, chief analyst at office leasing and consulting firm Sanko Estate Co Ltd., said in an interview. He said the increase was fueled by the fiscal expansion and monetary easing under Abe’s economic program, launched after his election in late 2012.
“This marks the timing for completion of buildings planned from about 2013 when developers were expecting the economy to expand,” said Imazeki. The increase in building was supported not only by Abe’s expansionary policies but also Japan’s ultra-low interest rates, he said.
Reprinted courtesy of
Gareth Allan, Bloomberg and
Katsuyo Kuwako, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 —
Beverley BevenFlorez CDJ STAFFIn the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision… Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Rules Developers can be Required to Include Affordable Housing
June 17, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Los Angeles Times reported that in a unanimous decision, the California Supreme court justices declared that “cities and counties” can “require developers to sell some housing at below-market rates.”
Chief Justice Tani Cantil-Sakauye wrote, “It will come as no surprise to anyone familiar with California’s current housing market that the significant problems arising from a scarcity of affordable housing have not been solved over the past three decades,” as quoted in the Los Angeles Times.
Los Angeles Mayor Eric Garcetti applauded the decision: “This gives Los Angeles and other local governments another possible tool to use as we tackle our affordable housing crisis.”
Read the court decisionRead the full story...Reprinted courtesy of
DC Metro Extension’s Precast Supplier Banned from Federal Contracts
November 16, 2020 —
Jim Parsons - Engineering News-RecordStowe, Pa.-based Universal Concrete Products, which supplied hundreds of defective precast panels for the $2.7 billion Silver Line light rail extension in northern Virginia, has received a three-year ban on participating in federally financed transportation projects. Imposed by the Federal Transit Administration, the ban makes Universal ineligible for contracts, grants, loans or other financial assistance from agency of the federal government until the end of 2023.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Did You Really Accept That Bid? – How Contractors Can Avoid Post-Acceptance Bid Disputes Over Contract Terms
July 28, 2016 —
David A. Harris & Steven M. Cvitanovic – Haight Brown & Bonesteel LLPWhen California general contractors submit bids to an owner, can they force their subcontractors to honor their bids? Can they recover damages if the subcontractor later refuses to do so?
While the general rule in California is that a general contractor who reasonably relies on a subcontractor’s bid may recover damages when the subcontractor reneges, the Court of Appeal for the Second Appellate District recently held that there is a substantial and important exception to the general rule.
In Flintco Pacific, Inc. v. TEC Management Consultants, Inc. (LASC No. YC067984), the Court of Appeal held that where a general contractor requires a subcontractor to enter into a “standard-form subcontract” which materially differs from the subcontractor’s bid, the general contractor has rejected the subcontractor’s bid and has instead issued a counteroffer. The subcontractor is thereafter free to walk, or accept the new terms. If the subcontractor walks, the general contractor may not seek to enforce the terms of the subcontract or seek reliance damages.
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Condos Down in Denver Due to Construction Defect Litigation
November 06, 2013 —
CDJ STAFFA new report suggests that fears of construction defect litigation may be the cause of the slump in condo building in the Denver area. The Denver Business Journal reports that the Denver Regional Council of Governments commissioned the study by Economic & Planning Systems. The conclusion of the report was that the only type of condominium likely to be built is high-cost units with high profit margins. This is not good news for the DRCOG, which is seeking to create more affordable housing.
The report found that builders assess the likeliness of being sued “is nearly 100 percent,” that costs of addressing construction defects are 12% higher than at apartment complexes, and that preparing for litigation adds about $15,000 to the cost of a condo unit.
One possible remedy is to reform Colorado’s construction defect laws. Bob Muphy, the mayor of Lakewook and an advocate of construction defect litigation reform, said that he sees “this as a verification of what I’ve been talking about.”
Read the court decisionRead the full story...Reprinted courtesy of
Sweat the Small Stuff – Don’t Overlook These Three (3) Clauses When Negotiating Your Construction Contract
April 08, 2024 —
Bill Shaughnessy - ConsensusDocsReviewing and understanding the terms of your construction contract before signing on the dotted line (ideally with counsel involved) is an obvious best practice – whether you are owner, general contractor, design-professional or down-tier subcontractor or supplier. Typically, during this review process, parties pay closest attention to terms relating to price, scope, schedule, insurance, indemnification, and damages. And rightfully so, as these are just some of the most fundamental and important clauses of any construction contract.
But during this review and understanding process, parties often overlook and fail to fully review and understand several notably important contract provisions (other than the examples above) which can have just as significant an impact on the project and even unintended consequences once construction starts. This article discusses three (3) of these often-overlooked provisions which should also be carefully reviewed to ensure the project runs smoothly and to avoid unintended consequences or even disputes (and litigation) during construction:
- Incorporation by reference clause;
- Order of precedence or higher standard clause; and
- Choice of law clause.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker LLP (ConsensusDocs)Mr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
When Subcontractors Sue Only the Surety on Payment Bond and Tips for General Contractors
August 13, 2019 —
Ira M. Schulman & Emily D. Anderson - ConsensusDocsPayment bonds have been a staple of public construction projects since 1874, when the U.S. Congress first passed the Heard Act, which required that contractors obtain payment bonds for public projects to ensure that subcontractors and material suppliers have a way to recover their damages if an upstream contractor fails to pay for work performed and materials furnished on the project. The 1874 Heard Act has since been replaced by the 1935 Miller Act, and the concept has been expanded to construction projects funded by the states through state statutes known as “Little Miller Acts.” But the structure remains the same: On most public projects where the project’s cost exceeds $100,000, the prime contractor (the bond principal) is required to obtain a payment bond from a surety equal to the contract price to guarantee to subcontractors and material suppliers (the bond obligees) that the surety will pay for labor and materials under certain statutory or contractual conditions should the contractor fail to make payment.
A surety is jointly and severally liable with the contractor to the subcontractor, which means that the subcontractor may seek recovery against either the contractor or the surety or both, and the contractor and surety will be liable for the damages together. Put another way, in most states and in federal court, an unpaid subcontractor has the right to sue only the surety on the payment bond without joining the contractor because a contract of suretyship is a direct liability of the surety to the subcontractor.1 When the contractor fails to perform, the surety becomes directly responsible at once — it is unnecessary for the subcontractor to establish that the contractor failed to carry out its contract before the obligation of the surety becomes absolute.
Reprinted courtesy of
Ira M. Schulman, Pepper Hamilton LLP and
Emily D. Anderson, Pepper Hamilton LLP
Mr. Schulman may be contacted at schulmani@pepperlaw.com
Ms. Anderson may be contacted at andersone@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of