Construction Defects in Roof May Close School
October 21, 2013 —
CDJ STAFFA school in Wales may have to close due to roof leaks. The school was opened six years ago, but since then the leaks at Ysgol Ffynnonbedr are “leading to the deterioration of the structure and fabric of the school.” The Lampeter city council have budgeted £35,000 (about $56,000) for repairs to the roof.
The leaks have already rendered some of the electrical systems and teaching areas unusable. The city council had been in discussion with the builders, Cowlin Construction, when that firm was bought by Balfour Beatty. Balfour Beatty did not comment to the Cambrian Times about resolving the construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Legislature Enables Pre-Judgment Interest in Personal Injury Cases
February 01, 2021 —
Justin Zimmerman - Lewis BrisboisOn January 13, 2021, the Illinois General Assembly passed HB 3360, which will enable pre-judgment interest of 9% in personal injury cases. The legislation was sponsored by Madison County, Illinois-area representative Jay Hoffman (D-Belleville) and Illinois state senator Dan Harmon (D-Oak Park).
Under current Illinois law, plaintiffs are not entitled to pre-judgment interest in personal injury cases because the nature and extent of a plaintiff’s damages cannot be calculated in advance and liability is uncertain (compared, for example, to a breach of contract claim).
If signed by the governor, personal injury actions in Illinois will be subject to 9% per annum pre-judgment interest accruing “on the date the defendant has notice of the injury from the incident itself or a written notice." Notably, the bill will also impact pending litigation as interest begins to accrue on the effective date of the legislation for cases already filed.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Zimmerman, Lewis BrisboisMr. Zimmerman may be contacted at
Justin.Zimmerman@lewisbrisbois.com
Revisiting Statutory Offers to Compromise
August 28, 2023 —
Kathryne Baldwin - Wilke FleuryThe fourth appellate district published an opinion earlier this year in Smalley v. Subaru of America, Inc. (2022) 87 Cal.App.5th 450 that serves as an excellent refresher on requirements of the “998 Offer,” or a statutory offer to compromise pursuant to Code of Civil Procedure (“CCP”) §998.
In Smalley, set in the context of a Lemon Law action, Defendant Subaru made a 998 Offer for $35,001.00, together with attorneys’ fees and costs totaling either $10,000.00 or costs and reasonably incurred attorneys’ fees, in an amount to be determined by the Court. (Smalley, supra, 87 Cal.App.5th at 454.) Plaintiff objected that the offer was not reasonable and the case proceeded to trial. At trial, a jury found in favor of Plaintiff and awarded him a total judgment award of $27,555.74 – far short of the $35,001.00 offer. The trial court found Plaintiff had failed to beat the 998 at trial and that Subaru’s earlier 998 offer was reasonable. Plaintiff appealed the post-judgment order awarding Plaintiff pre-offer costs and Defendant post-offer costs on the grounds that the 998 was not reasonable in that it did not specify whether Plaintiff would be deemed the prevailing party for purposes of a motion for attorneys’ fees. The fourth district affirmed the trial court’s order and engaged in a helpful review of 998 requirements.
Read the court decisionRead the full story...Reprinted courtesy of
Kathryne Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com
Gehry-Designed Project Seen Bringing NYC Vibe to L.A.
April 28, 2014 —
Nadja Brandt and John Gittelsohn – BloombergBillionaire Stephen Ross’s Related Cos. new project in the sleepy end of downtown Los Angeles is designed to invigorate Grand Avenue the way its Time Warner Center helped energize New York’s Columbus Circle.
“The notion of bringing together this diverse mix of uses, and allowing for a lot of public spaces and public events, has proven to be very powerful in the right locations and with the right planning.” said William Witte, president of Related’s California division.
The New York-based firm formed a joint venture with Los Angeles-based SBE Entertainment Group LLC to restart plans for a $650 million-to-$700 million complex with entertainment, shopping, apartments, condominiums and a luxury hotel, Witte said. After going back and forth with local officials for most of the past year, Related won approval in January for the Frank Gehry-designed project from Los Angeles County supervisors.
Ms. Brandt may be contacted at nbrandt@bloomberg.net; Mr. Gittelsohn may be contacted at johngitt@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Nadja Brandt and John Gittelsohn, Bloomberg
What Do I Do With This Stuff? Dealing With Abandoned Property After Foreclosure
October 20, 2016 —
Lyndsey Torp – Snell & Wilmer Real Estate Litigation BlogYou’ve successfully foreclosed on a commercial building in California, and, thankfully, the borrower moved out after foreclosure or after a period of tenancy. But the borrower left behind all sorts of property – furniture, filing cabinets, records, and other assorted property. While you may be tempted to just toss it all in the dumpster, doing so may subject you to liability. There are several statutes that you should consider when determining how to handle the abandoned property.
Statutory Options for a Landlord
A landlord-tenant relationship may arise following foreclosure if, for example, the owner of the property accepts rent from the former owner. If the tenant subsequently turns over possession of the commercial property but leaves personal property at the premises,[1] California Civil Code provides a landlord with statutory options to deal with “lost” (Cal. Civ. Code § 2080) or “abandoned” property (Cal. Civ. Code §1993).
Read the court decisionRead the full story...Reprinted courtesy of
Lyndsey Torp, Snell & WilmerMs. Torp may be contacted at
ltorp@swlaw.com
William Doerler Recognized by JD Supra 2022 Readers’ Choice Awards
March 14, 2022 —
William Doerler - White and Williams LLPCongratulations to Bill Doerler, Counsel of the Subrogation Group who has been recognized as a
top author in Product Liability in the 2022 JD Supra Readers' Choice Awards. Bill was ranked number 9 out of a pool of approximately 800 authors writing about product liability matters on JD Supra in 2021.
The Readers’ Choice Awards recognize top authors and firms for their thought leadership in key topics read by C-suite executives, in-house counsel, media and other professionals across the JD Supra platform during 2021. These annual awards (now in their seventh year) recognize JD Supra contributors for the visibility and engagement their thought leadership earned among readers in select subjects during the previous 12 months.
Read the court decisionRead the full story...Reprinted courtesy of
William Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com