Underpowered AC Not a Construction Defect
November 07, 2012 —
CDJ STAFFAfter buying a home in Louisiana, Mike Gines determined that the home’s air conditioning unit was insufficient to maintain an appropriate temperature. He contacted the home builder, D.R. Horton, Inc., which worked with the air conditioning installer, Reliant Heating & Air Conditioning, in order to repair the system. When the problems persisted, Gines filed a class action petition against Horton and Reliant in state court. Horton and Reliant moved the case to the federal courts, whereupon Gines asserted the defendants were in violation of the Louisiana New Home Warranty Act (NHWA). Horton stated that the claim under the NHWA was invalid, because Gines had not alleged actual physical damage to his home.
The district court granted Horton’s motion to dismiss. Gines sought a reversal from the Fifth Circuit Court of Appeals and sought to have two questions of state law addressed by the Louisiana Supreme Court.
The district court ruled that the NHWA was the “sole remedy under Louisiana law for a purchaser of a new home with construction defects. Gines argued that court erred in this, but also conceded that this was the conclusion of the Louisiana Supreme Court.
Further, Gines argued that a provision in the NHWA that allows the inclusion of construction defects that do not cause damage was satisfied by paragraph 6 of the contract. The court noted that Gines did not attach a copy of the contract to either the original or amended complaint, and so the court does not need to address these claims. However, the court cautioned that if a copy had been included, they still would have rejected the claim, as “the cited language does not indicate a waiver of the physical damage requirement.” They also note that “paragraph 13 of the contract shows that Gines was aware to the absence of any such waiver in the contract.”
The court concludes that “the moral of this story is that in order to avoid the harsh result that has obtained here, the buyer of a newly constructed home in Louisiana should seek to obtain in the contract of sale an express waiver of the actual damage requirement of the NHWA.” The appeals court affirmed the decision of the circuit court and denied the application to certify questions to the Louisiana Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Citigroup Pays Record $697 Million for Hong Kong Office Tower
June 18, 2014 —
Michelle Yun – BloombergCitigroup Inc. (C) paid a record HK$5.4 billion ($697 million) to a unit of Wheelock & Co. for a Hong Kong office tower that will bring most of its 5,000 employees under one roof.
The price for the 512,000 square-foot property in Kowloon is the largest ever office transaction in Hong Kong, the New York-based bank said in a statement yesterday. The tower, scheduled for completion by the end of 2015, will be used to house staff currently spread out across offices in the city, said Weber Lo, the bank’s chief executive officer for Hong Kong and Macau.
Citigroup joins banks and insurers in buying buildings in the city as falling vacancies pose a challenge for companies looking for large office spaces, realtor CBRE Group Inc., which advised the deal, said in a first-quarter review report.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Yun, BloombergMs. Yun may be contacted at
myun11@bloomberg.net
Dealing with Abandoned Property After Foreclosure
April 10, 2019 —
Bremer Whyte Brown & O'Meara LLPCalifornia landlords must follow very specific steps before disposing of property that is clearly abandoned, left on real estate which has been the subject of court proceedings such as eviction or foreclosure, or otherwise left behind. Following the statutory procedures relating to abandoned property protects landlords from potential liability for an improper “conversion.”
Former tenants/owners and others “reasonably believed” to be owners of the apparently abandoned personal property must be given proper written notice of the right to reclaim the abandoned property. The tenant is presumed to be the owner of any “records” remaining on the property. The California Code of Civil Procedure provides a template for such notice. The notice to be provided to former tenants/owners must be in “substantially” the same form provided in the California Code of Civil Procedure and must contain the following information:
- A description of the abandoned property in a manner reasonably adequate to permit the owner of the property to identify it;
- The location where the tenant can claim the property;
- The time frame that the tenant has to claim the property. The date specified in the notice shall be a date not less than fifteen (15) days after the notice is personally delivered or, if mailed, not less than eighteen (18) days after the notice is deposited in the mail;
- A statement that reasonable storage costs will be charged to the tenant/owner and the tenant/owner must pay those costs before claiming the property; and
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
The General Assembly Adds Some Clarity to Contracts and Unlicensed Contractors
March 28, 2018 —
Christopher G. Hill – Construction Law MusingsFor years, the statute regarding performing construction without a valid license (
Va. Code 54.1-1115) was a bit murky. While that statute listed several prohibited acts, among them contracting without the proper class of license or use of the license of another, the consequences of such activity, in particular the effect that such action would have on the enforcement of a construction contract (Section C of the statute), were less than clear.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
More Money Down Adds to U.S. First-Time Buyer Blues: Economy
August 20, 2014 —
Michelle Jamrisko and Alexis Leondis – BloombergThe challenges facing prospective buyers of the least expensive homes in the U.S. are getting harder to overcome.
Already beset by stagnant wages, growing student debt and competition from investors who are snapping up listings, those looking to purchase moderately priced houses must also provide more cash up front. The median down payment for the cheapest 25 percent of properties sold in 2013 was $9,480 compared with $6,037 in 2007, the last year of the previous economic expansion, according to data from 25 of the largest metro areas compiled by brokerage firm Redfin Corp.
The higher bar is a symptom of still-tight credit that is crowding out first-time buyers even as interest rates remain near historical lows. Younger adults, who would normally be making initial forays into real estate, are among those most affected, weakening the foundations of the housing market and limiting its contribution to economic growth.
Ms. Jamrisko may be contacted at mjamrisko@bloomberg.net; Ms. Leondis may be contacted at aleondis@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko and Alexis Leondis, Bloomberg
Meet BWB&O’s 2025 Best Lawyers in America!
September 09, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce Partners
Nicole Whyte,
Keith Bremer,
Vik Nagpal,
John O’Meara,
Sheila Stiles,
Patrick Au, and
Nicole Schmidt have been selected by their peers for inclusion in the 31st edition of The Best Lawyers in America, and Partner
Devin Gifford, and Associates
Melissa Youngpeter,
Ryan Flanagan, and
Alexandria Zeis are included in the fifth edition of Best Lawyers: Ones to Watch in America. Each person is being recognized for their diligent work in the areas of Family Law, Construction, Commercial, Personal Injury, and Real Estate Litigation.
Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fraud, the VCPA and Construction Contracts
November 26, 2014 —
Christopher G. Hill – Construction Law MusingsI’ve discussed the economic loss rule here at Musings on several occasions. The economic loss rule basically states that where one party assumes a duty based in contract or agreement, the Virginia courts will not allow a claim for breach of that duty to go forward as anything but a contract claim. This doctrine makes fraud claims nearly, though not absolutely, impossible to maintain in a construction context. In a majority of instances, fraud and construction contracts are very much like oil and water, leaving parties to fight it out over the terms of a particular contract despite actions by one party or the other that non-lawyers would clearly see as fraud.
However, a recent case decided by the Virginia Supreme Court gives at least some hope to those who are seemingly fooled into entering a contract that they would not other wise have entered into. In Philip Abi-Najm, et. al, v Concord Condominium, LLC, several condominium purchasers sued Concord under for breach of contract, breach of the Virginia Consumer Protection Act (VCPA) and for fraud in the inducement based upon flooring that Concord installed that was far from the quality stated in the purchase contract. Based upon these facts, the Court looked at two questions: 1. Did a statement in the contract between Concord and the condo buyers create a situation in which the merger doctrine barred the breach of contract claim, and 2. Did the economic loss rule bar the VCPA and fraud claims?
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Utah’s Highest Court Holds That Plaintiffs Must Properly Commence an Action to Rely on the Relation-Back Doctrine to Overcome the Statute of Repose
August 20, 2018 —
Shannon M. Warren - The Subrogation StrategistEarlier this summer, in Gables & Villas at River Oaks Homeowners Ass’n v. Castlewood Builders LLC, 2018 UT 28, the Supreme Court of Utah addressed the question of whether the plaintiff’s construction defects claims against the general contractor for a construction project were timely-filed, or barred by the statute of repose. In Utah, the statute of repose requires that an action be “commenced within six years of the date of completion.” The plaintiff alleged that its 2014 amended complaint naming the general contractor as a defendant was timely-commenced because, before the date on which Utah’s statute of repose ran, a defendant filed a motion to amend its third-party complaint to name the general contractor as a defendant, and the defendant subsequently assigned its claims to the plaintiff. The plaintiff argued that the filing of its 2014 amended complaint related back[1] to the date of its original complaint. The Supreme Court disagreed, holding that an action is “commenced” by filing a complaint and that a motion for leave to amend does not count as “commencing” an action.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com