Georgia Court of Appeals Holds That Insurer Must Defend Oil Company Against Entire Lawsuit
October 07, 2019 —
Lawrence J. Bracken II, Michael S. Levine & Alexander D. Russo - Hunton Andrews KurthThe Georgia Court of Appeals recently affirmed a grant of summary judgment in favor of Mountain Express Oil Company on its breach of contract claim against liability insurer, Southern Trust Insurance Company. Empire Petroleum brought claims against Mountain Express for breach of contract, injunctive relief, and libel or slander, among others. Mountain Express sought a defense to that lawsuit under its insurance policy with Southern Trust. Southern Trust contended that the insurance policy did not cover Empire’s non-libel/slander claims, and therefore reimbursed Mountain Express for only a portion of its attorneys’ fees. After the Empire lawsuit settled, Mountain Express sued Southern Trust for breach of contract and bad faith for failing to pay the remaining defense costs, contending that Southern Trust had a duty to defend the entire lawsuit.
The Georgia Court of Appeals affirmed the trial court’s grant of summary judgment to Mountain Express on its breach of contract claim. Citing policy language stating that “[the insurer] will have the right and duty to defend the insured against any ‘suit’ seeking those damages,” the court held that Southern Trust was obligated to defend the entire lawsuit. Specifically, in reaching that conclusion, the court noted that by agreeing to defend any “suit,” not any “claim,” Southern Trust obligated itself to defend the entire lawsuit if any claim could be covered under the policy. Accordingly, Southern Trust breached the policy when it only agreed to defend some of the claims against its insured.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Coverage Under Builder's Risk Policy Properly Excluded for Damage to Existing Structure Only
April 05, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Tenth Circuit affirmed the District Court's determination that there was no coverage under the builder's risk policy. Gerald H. Phipps, Inc. v. Travelers Prop. Cas. Co. of Am., 2016 U.S. App. LEXIS 2764 (10th Cir. Feb. 16, 2017).
GH Phipps Construction Company (GHP) was hired to renovate and expand the University of Denver's library. GHP was completing installation of a new roof on the library when water from melting snow leaked into the building. The water damaged existing drywall and insulation in the stairwells and elevator shafts that GHP planned to preserve and update. Before the snow melt mishap, GHP had completed some preliminary work in the damaged areas to designate locations for future installation of mechanical, plumbing and electrical systems. But GHP had not yet installed any new materials, updated any lighting fixtures, or patched and painted any existing drywall in the damaged areas.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Failing to Adopt a Comprehensive Cyber Plan Can Lead to Disaster
January 13, 2020 —
Richard Volack - Construction ExecutiveDespite being aware of cyber risk, and even frightened by it, a shocking number of companies in the construction industry have neither a cyber insurance policy nor a basic cyber security plan to deal with a hack or breach into their computer systems. Once breached, companies with no plan in place become, essentially, a rudderless ship subject to the whims of criminal tides.
A proper cyber plan lays out at least the following:
- the criteria for when a plan would be triggered (i.e., in the event of a breach or a hack);
- which persons inside the company (in-house counsel, IT personnel, executive, project managers) and which persons outside the company (attorney with knowledge of cyber issues and ideally construction law as well; forensic computer experts, crisis management experts; and an insurance broker familiar with cyber policies) should be involved;
- the chain of command and communication in this type of situation and the distinct roles each of the above players will fulfill (Note: this is not the same as the normal corporate chain of command); and
- the various available options to address the breach situation, which will all depend upon the facts at issue—such as the type and extent of the breach and how much of what particular kind of information was lost, stolen or exfiltrated.
Reprinted courtesy of
Richard Volack, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Volack may be contacted at rvolack@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage For Construction Defect Under Illinois Law
January 28, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court followed precedent in Illinois and upheld the insurer's denial of coverage for construction defects that did not damage other property. Design Concrete Founds., Inc. v. Erie Ins. Prop. & Cas. Co., 2014 Ill. App. Unpub. LEXIS 2684 (Ill Ct. App. Nov. 26, 2014).
In 2005, the homeowners contracted with the general contractor to build a home. The general contractor hired Design to do the foundation work. Design performed its work in August 2005. After the work was completed, cracks formed in the foundation, allowing water to enter the basement and an inward shifting of the foundation.
The homeowners sued the general contractor and Design. The complaint alleged that Design failed to build the foundation in a workmanlike manner, resulting in the development of cracks in the foundation.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
AAA Revises its Construction Industry Arbitration Rules and Mediation Procedures
April 02, 2024 —
Garret Murai - California Construction Law BlogThis one is for the lawyers. Or for those of you who are claims-minded . . .
Effective March 1, 2024, the American Arbitration Association (“AAA”) revised its Construction Industry Arbitration Rules and Mediation Procedures. For those involved in construction, this is important since the AAA Rules are the default arbitration rules contained in AIA form contracts and are often the arbitration rules referenced in other construction contracts as well.
So, what are the changes?
- General: Fax numbers have gone the way of the Dodo bird and replaced by email addresses for all parties. Also, while already done in practice, preliminary hearings may now be held via videoconference in addition to telephone and in-person (Rule R-23).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
New Jersey/New York “Occurrence”
July 30, 2014 —
Scott Patterson – CD CoverageIn National Union Fire Insurance Co. of Pittsburgh, PA v. Turner Construction Co., 986 N.Y.S.2d 74 (N.Y. App. Div. 2014), Turner was the general contractor for a high rise office building constructed in New Jersey for owner GSJC. Turner subcontracted with Permasteelisa for the building’s exterior curtain wall which consisted of granite and glass with an attached network of decorative pipe rails. A segment of the pipe rails fell from the building onto the street. GSJC determined that a significant percentage of the pipe rail connections to the curtain wall did not conform to specifications or were defective. GSJC sued Turner and Permasteelisa in New Jersey state court for breach of contract, breach of warranty, and negligence, seeking damages for the damage to the curtain wall and the danger of additional pipe rail falling in the future. National Union, which had issued an OCIP policy for the project, defended Turner and Permasteelisa under a reservation of rights and then filed a declaratory judgment action in New York state court. The New York trial court entered judgment for National Union. On appeal, the intermediate court of appeals affirmed. As to choice of law, the court stated that “it is undisputed that the law of New Jersey governs this action, which turns on insurance policy interpretation, and that New Jersey and New York law are consistent as to the issues in dispute here.”
Read the court decisionRead the full story...Reprinted courtesy of
Scott Patterson, CD Coverage
NYC Condo Skyscraper's Builder Wins a Round -- With a Catch
November 15, 2017 —
Oshrat Carmiel - BloombergThe battle over whether an 800-foot condo tower planned for Manhattan’s East Side can be built to its full height took a step forward Wednesday -- with city officials saying both yes, and no.
A years-long neighborhood lobbying effort to cap the height of new towers near the East 50s riverfront won an endorsement Wednesday from the planning commission, which agreed to rezone the area in a way that would make skyscraping condo towers impossible to build. But commissioners also voted to allow Sutton 58, the under-construction project that inspired the rezoning push, to be grandfathered in under the new law, and proceed as is.
Read the court decisionRead the full story...Reprinted courtesy of
Oshrat Carmiel, Bloomberg
Construction Law Advisory: Mechanical Contractor Scores Victory in Prevailing Wage Dispute
September 03, 2014 —
Steven M. Cvitanovic & Jessica M. Lassere Ryland - Haight Brown & Bonesteel LLPOn August 27, 2014, the First District Court of Appeal weighed in on whether prevailing wages are required for public contracts in situations where work is performed in furtherance of the project but at a permanent offsite manufacturing facility that is not exclusively dedicated to the project. In Sheet Metal Workers' International Association, Local 401 v. John C. Duncan and Russ Will Mechanical, the project at issue was for a community college district where Russ Will was the HVAC subcontractor. The contract documents required contractors to pay prevailing wages but they did not limit where or how Russ Will would fabricate sheet metal required for the job. Russ Will used its existing fabrication facility to form the sheet metal.
An employee of Russ Will filed a complaint with the DIR alleging he should have been paid prevailing wages for work related to the project. The worker fabricated sheet metal for the project but at Russ Will’s Hayward facility, not at the site. The DIR issued a coverage determination in which it concluded that Russ Will was required to pay prevailing wages for the offsite fabrication work associated with the project. The DIR's determination turned on whether Russ Will was exempt from the prevailing wage law as a material supplier. To qualify for the material supplier exemption, the employer must sell supplies to the general public and its fabrication or manufacturing facility must not be established for the particular public works contract or be located at the site of the public work.
Following the DIR determination, Rush Will filed an administrative appeal. The department reversed its initial coverage determination, concluding that the offsite fabrication performed by Russ Will was not subject to the prevailing wage law.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of