Boilerplate Contract Language on Permits could cause Problems for Contractors
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor discusses the potential problems for a contractor that a “boilerplate contract” could cause: “A recent case revealed the problems a contractor had with permits when the contractor’s estimate contemplated an easy permitting process and compliance, but in actuality it was much, much more difficult.”
Martin cites the case Bell/Heery v. United States, where a contractor discovered that the permit process would be much more time-consuming and expensive than originally planned. When Bell/Heery asked for additional funds to cover the additional costs, the “contracting officer rejected the request, finding that Bell/Heery had assumed the risk of the permitting process and it was liable for any costs associated with the permitting process and construction methods required by the permitting process.”
“Bell/Heery appealed to the Court of Claims,” but lost the battle. The contractor had to absorb $7 million in costs to comply with the required permits.
Read the court decisionRead the full story...Reprinted courtesy of
“Wait! Do You Have All Your Ducks in a Row?” Filing of a Certificate of Merit in Conjunction With a Complaint
January 13, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Barrett v. Berry Contr. L.P., No. 13-18-00498-CV, 2019 Tex. LEXIS 8811, the Thirteenth District Court of Appeals of Texas considered, among other things, the procedural timing requirements of filing a certificate of merit in conjunction with a complaint. The court concluded that the proper reading of the statute requires a plaintiff to file a certificate of merit with the first complaint naming the defendant as a party.
In Barrett, after sustaining injuries while working at a refinery, David Barrett (Barrett) filed suit against Berry Contracting, LP and Elite Piping & Civil, Ltd. on July 6, 2016. In Barrett’s first amended complaint, which he filed on August 23, 2016, Barrett added Govind Development, LLC (Govind) as another defendant. Barrett subsequently filed a second amended complaint (omitting Govind) and, on December 27, 2017, shortly before the statute of limitations ran, a third amended complaint (reasserting claims against Govind). On January 28, 2018, after the statute of limitations period ran, Barrett filed a certificate of merit. Govind filed a motion to dismiss the claim, asserting that Barrett violated the statute that required a certificate of merit to be filed with the complaint, Tex. Civ. Prac & Rem. Code §150.002.
Tex. Civ. Prac. & Rem. Code §150.002(a) states,
In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, a claimant shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect or registered professional land surveyor…
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
White House’s New Draft Guidance Limiting NEPA Review of Greenhouse Gas Impacts Is Not So New or Limiting
September 09, 2019 —
Norman F. Carlin & Eric Moorman - Gravel2Gavel Construction & Real Estate Law BlogOn June 21, 2019, the White House Council on Environmental Quality (CEQ) issued draft guidance clarifying the treatment of greenhouse gas (GHG) emissions in environmental impact reviews of federal projects under the National Environmental Policy Act (NEPA). Those wishing to comment on the draft must submit comments within 30 days after it is published in the Federal Register.
The draft guidance is part of the Trump Administration’s continuing efforts to streamline the permitting and environmental review process for infrastructure and energy projects. It replaces NEPA guidance on climate impacts issued in 2016 by the Obama administration, which was rescinded by President Trump’s Executive Order 13783 early in 2017. Although some initial reports suggest that the new draft guidance significantly pulls back from the Obama administration’s approach, on closer comparison it does not depart that much from the major recommendations of the rescinded guidance.
In general, NEPA requires federal agencies proposing to undertake, approve or fund a major federal action to evaluate its environmental impacts, including both direct and reasonably foreseeable indirect effects; to consider alternatives and mitigation; and to discuss cumulative impacts resulting from the incremental effects of the project when added to those of other past, present, and reasonably foreseeable future projects. The new draft and the rescinded 2016 guidance contain similar recommendations regarding an agency’s obligations to consider indirect and cumulative GHG impacts, as well as on the use of cost-benefit analysis and the contentious Social Cost of Carbon (SCC) metric.
Reprinted courtesy of
Norman F. Carlin, Pillsbury and
Eric Moorman, Pillsbury
Mr. Carlin may be contacted at norman.carlin@pillsburylaw.com
Mr. Moorman may be contacted at eric.moorman@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to all of our 2023 Attorneys Named as Super Lawyers and Rising Stars
June 12, 2023 —
White and Williams LLPFifteen White and Williams lawyers have been named by Super Lawyers as a Delaware, Maryland, Massachusetts, New Jersey, New York or Pennsylvania "Super Lawyer," while twelve received "Rising Star" designations. Lawyers are selected through a process that takes into consideration peer recognition and professional achievement. The lawyers named to this year’s list represent a multitude of practices throughout the firm.
Reprinted courtesy of
White and Williams LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Update Coverage for Construction Defect Claims in Colorado
February 11, 2013 —
Tred R. Eyerly Whether construction defect claims against an insured contractor or subcontractor are covered is undergoing an intense debate in Colorado that is reminiscent of the current coverage battle in Hawaii.
Although I missed the case until recently, the decision in Colo. Pool Sys. v. Scottsdale Ins Co., 2012 Colo. App. LEXIS 1732 (Colo. Ct. App. Oct. 25, 2012), appears to divert from a prior case from the Colorado Court of Appeals, Gen. Sec. Indem. Co. v. Mountain States Mut. Cas. Co., 205 P.3d 529 (Colo. App. 2009). Gen. Security held that faulty workmanship, standing alone, was not an "accident." Gen. Security was heavily relied upon by the Hawaii Intermediate Court of Appeals when it found construction defects arose from breach of contract and were not covered under a liability policy. See Group Builders v. Admiral Insurance Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010).
In Colo. Pool Sys., Colorado Pool hired subcontractors to construct a poll's concrete shell. After the shell was poured, an inspection noticed that some re-bar was too close to the surface. The owner turned to its general contractor, White Construction Group, and demanded that the pool be removed and replaced. White turned to Colorado Pool, who notified its carrier, Scottsdale.
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Law HawaiiMr. Eyerly can be contacted at
te@hawaiilawyer.com
Home Prices in 20 U.S. Cities Rose at Slower Pace in May
July 30, 2014 —
Victoria Stilwell – BloombergResidential real-estate prices rose in the 12 months ended May at the slowest pace in more than a year as a lull in the U.S. housing market limits appreciation.
The S&P/Case-Shiller index of property values in 20 cities increased 9.3 percent from May 2013, the smallest year-to-year advance since February 2013, after rising 10.8 percent in the year ended in April, the group said today in New York. The median projection of 30 economists surveyed by Bloomberg called for a 9.9 percent year-over-year advance. Compared with the prior month, prices dropped for the first time in two years.
Higher mortgage rates and strict lending requirements are bridling sales, which will probably prompt sellers to lower their expectations of how much they can get for their properties. Continued job growth and greater balance between supply and demand will be needed to bring some potential homebuyers back into the market.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Five Steps Employers Should Take In the Second Year Of the COVID-19 Pandemic
March 29, 2021 —
Laura H. Corvo - White and Williams LLPFor the past year, employers faced unprecedented difficulties as they navigated the twists, turns and ever-present challenges the COVID-19 pandemic dished out. A year later, new challenges face employers. The promise of vaccines, the fear of new variants, and the realization that “normal” will never look quite the same, leave many employers to wonder: “what next?”. As employers prepare to enter the second year of the COVID-19 pandemic, here are five things they should plan to do.
1. Update Workplace Safety Measures
At the onset of the pandemic, employers struggled to understand the safety obligations involved in preventing the spread of COVID in the workplace. As we approach the second year of the pandemic, clearer legal standards and better science exist requiring employers to update the steps they are taking to keep their workplaces safe.
Read the court decisionRead the full story...Reprinted courtesy of
Laura H. Corvo, White and Williams LLPMs. Corvo may be contacted at
corvol@whiteandwilliams.com
Bright-Line Changes: Prompt Payment Act Trends
September 16, 2024 —
Stephanie L. Cooksey - Peckar & Abramson, P.C.Untimely payment by the owner for contract work and additional work on construction projects can place an unfair financial burden on contractors and subcontractors. Most states have attempted to eliminate or mitigate this inequity in construction contracting through Prompt Payment Acts that govern payment deadlines and provide remedies for untimely payment. This article addresses the legislative trends aimed at minimizing the risk of non-payment, overdue payment, and withholding retainage in favor of downstream parties to a construction contract.
Fortifying Contractor Protections with “Bright-Line” Language
Over the last decade, states have been tightening prompt payment laws by replacing broad, general statutory language with bright-line rules. What is a bright-line rule? A specific or definite figure, a quantifiable marker—i.e., something owners, contractors, subcontractors, and suppliers should be aware of. Practically speaking, the more bright-line a prompt payment statute is, the greater the likelihood it will affect a construction project in your state.
A standard form construction contract, if not reviewed carefully, can create conflicts or confusion if it gives a party more leeway on payment deadlines than the applicable Prompt Payment Act. For example, consider an owner-issued Construction Change Directive (“CCD”) that requires a contractor to commence additional work immediately while a formal change order is negotiated. Consequently, a CCD can push financial burdens downstream, whether inadvertently or not, and may conflict with statutory payment deadlines. Nevertheless, an owner can be justified in its utilization of a CCD to maintain the project schedule. How should the parties competing interests be resolved?
Read the court decisionRead the full story...Reprinted courtesy of
Peckar & Abramson, P.C.