Five Frequently Overlooked Points of Construction Contracts
October 18, 2021 —
Craig H. O'Neill - White and Williams LLPThere is no shortage of articles addressing the key points of construction contracts. Just enter that phrase into any internet search engine and you will find plenty. It should go without saying that a construction contract should be in writing, it should clearly identify the scope of work to be performed and the sums to be paid for that work, and it should address the parties’ rights and responsibilities with regard to termination or suspension of the contract, correcting defective work, and handling claims and disputes—just to name a few. Of course, these items should receive their due consideration. Too often, however, other important aspects of the construction contract get shortchanged. This article aims the spotlight on five often overlooked aspects of construction contracts.
Project Schedules
Surprisingly, many construction contracts pay little attention to a central component of any construction project: the project schedule. Many contracts provide the dates of commencement and substantial completion but not much else. With the frequent use of project management techniques such as the Critical Path Method (CPM) and the associated software, it is easier than ever to identify which tasks should be prioritized and identify potential areas of delay. The owner’s contract with the general contractor should clearly define the scheduling methods used and provide measures to keep the parties informed of the progress of the work. By including basic scheduling requirements in the contract documents—such as the submission of “Baseline Project Schedules” (consistent with the contract time provisions), “Schedule Progress Updates” (comparing the progress of the work against the Baseline Project Schedule), and “Schedule Recovery Plans” (when Schedule Project Updates indicate projected delays)—the parties can avoid or reduce disputes over project delays that often lead to litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig H. O'Neill, White and Williams LLPMr. O'Neill may be contacted at
oneillc@whiteandwilliams.com
Traub Lieberman Partner Lisa M. Rolle Obtains Pre-Answer Motion to Dismiss in Favor of Defendant
August 16, 2021 —
Lisa M. Rolle - Traub LiebermanTraub Lieberman Partner Lisa M. Rolle obtained a motion to dismiss in favor of an international hotel chain. In the case brought before the U.S. District Court, Southern District of New York, the Plaintiff sustained a slip and fall injury in a Portuguese hotel (“Hotel”), which was allegedly caused by violations of building codes and New York and Portuguese negligence laws. The Plaintiff notes that the Hotel utilized the branding affiliated with the international hotel chain, and the named corporate entities are subsidiaries of the parent company of the international hotel chain. Further, Plaintiff alleged that the named corporate entities “owned, operated, maintained, and controlled” the Hotel where the accident occurred, as the international hotel had previously acquired the entity which owned the spa branding utilized.
In moving for pre-answer dismissal, Traub Lieberman acknowledged purchase of the managing agent of the Hotel, which became a subsidiary of their operations. However, Traub Lieberman asserted that the international hotel chain had not owned, operated, maintained, or managed the Hotel. Under New York law, parent corporations cannot be held liable for the actions of their subsidiaries, except in cases that support piercing the corporate veil. Traub Lieberman argued that the motion should be granted as a parent company cannot be held liable for acts committed by its subsidiary and further claimed that the parent company has never owned or operated the Hotel.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa M. Rolle, Traub LiebermanMs. Rolle may be contacted at
lrolle@tlsslaw.com
Getting U.S to Zero Carbon Will Take a $2.5 Trillion Investment by 2030
December 29, 2020 —
Will Wade & Eric Roston - BloombergIt’s going to take $2.5 trillion in spending over the next decade to get the U.S. on a path to a carbon-free economy, but the transition will help to pay for itself, Princeton University researchers say.
Achieving net-zero emissions by 2050 -- a central goal of President-elect Joe Biden’s climate plan -- would require expanding renewable-energy systems, building more efficient homes and putting 50 million electric cars on the road, according to a report released Tuesday.
The effort, two years in the making, is the first major assessment since the election detailing how the U.S. can transition to an energy system that satisfies scientific guidance for keeping the climate livable. While the upfront costs are significant, they would be offset by savings associated with switching to cheaper electricity and the creation of as many as 1 million new jobs, according to the researchers, who shared an earlier draft with Biden’s transition team.
Read the court decisionRead the full story...Reprinted courtesy of
Will Wade & Eric Roston, Bloomberg
Massachusetts Federal Court Holds No Coverage for Mold and Water Damage Claim
February 11, 2019 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Clarendon National Ins. Co. v. Philadelphia Indemnity Ins. Co., 2019 WL 134614 (D. Mass. Jan. 8, 2019), the United States District Court for the District of Massachusetts had occasion to consider the application of a prior knowledge provision in the context of a claim for mold and water-related bodily injury and property damage.
Philadelphia insured a condominium property management company under a general liability insurance policy for the period September 1, 2007 through September 1, 2008. In 2009, the insured was sued by a unit owner alleging bodily injury and property damage resulting from toxic mold conditions resulting from leaks that had been identified in her unit as early as 2004. Notably, the complaint alleged that mold was identified in 2006 and that repair efforts were undertaken, but that these efforts all proved unsuccessful. Plaintiff alleged that she was forced to vacate her apartment in 2008 as a result of the conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub LiebermanMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Application of Frye Test to Determine Admissibility of Expert
April 03, 2019 —
David Adelstein - Florida Construction Legal UpdatesFlorida went back to the Frye test/standard, instead of the Daubert test utilized in federal court, to determine the admissibility of expert testimony. The Frye test is more favorable to plaintiffs because it applies when an expert renders an opinion based on new or novel scientific principles. See D.R. Horton, Inc. v. Heron’s Landing Condominium Ass’n of Jacksonville, Inc., 44 Fla.L.Weekly D109b (Fla. 1st DCA 2018) (“The supreme court has described the Frye test as one in which the results of mechanical or scientific testing are not admissible unless the testing has developed or improved to the point where the experts in the field widely share the view that the results are scientifically reliable as accurate. Stated differently, under Frye, the proponent of the evidence has the burden of establishing by a preponderance of the evidence with the general acceptance of the underlying scientific principles and methodology. However, as stated, the Frye standard only applies when an expert attempts to render an opinion that is based upon new or novel scientific principles.”).
In D.R. Horton, Inc., a condominium association sued the developer and general contractor (same entity) for construction defects that included claims in negligence, violation of building code, and breach of statutory warranties. The developer/general contractor moved in limine / to strike the association’s experts under, at the time, a Daubert analysis, but which became a Frye analysis during the pendency of the appeal. The expert opined as to construction defects and damage and the appropriate repairs – really, no different than any construction defect dispute, from what it appeared. The trial court denied the motion and during trial the experts testified and a sizable damages judgment was entered against the developer/contractor prompting the appeal. One issue on appeal was the admissibility of the expert’s opinion. The appellate court noted that a Frye analysis is not necessary because the experts used a scientifically reliable and peer-reviewed methodology.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
When Can a General Contractor’s Knowledge be Imputed to a Developer?
August 06, 2014 —
Zach McLeroy – Colorado Construction LitigationThe Colorado Court of Appeals recently handed down an opinion clarifying when the knowledge of a general contractor can be imputed to a developer. In the case of Jehly v. Brown, 327 P.3d (Colo. App. 2013), the Court of Appeals held that a developer cannot be held liable for fraudulent concealment when the developer has no actual knowledge of the fact or facts allegedly being concealed even if the general contractor had knowledge.
In this case, Brown, the developer, owned real property in Teller County and hired a general contractor to build a single-family house. Sometime before or during the construction, the general contractor became aware that part of the home site was located in a designated floodplain. Although the general contractor was aware that part of the home site was located in a floodplain, he continued to build the home without informing Brown of the floodplain designation.
Once the home was complete, Brown sold the property to the Jehlys. Brown completed a Seller’s Property Disclosure Form regarding the condition of the house and property, but failed to identify that the home site was located in a governmentally designated floodplain.
Read the court decisionRead the full story...Reprinted courtesy of
Zack McLeroy, Higgins, Hopkins, McLain & Roswell, LLCMr. McLeroy may be contacted at
McLeroy@hhmrlaw.com
U.S. Home Sellers Return for Spring as Buyers Get Relief
February 10, 2014 —
Prashant Gopal – BloombergSuzanne Baker and her siblings bought a foreclosed home in Atlanta two years ago, added a fourth bathroom, then waited for values to rebound before considering a sale. Now, she says, they’re ready to cash in.
The family last month listed the four-bedroom house in the affluent Buckhead neighborhood for $710,000. It was purchased as an investment for about $375,000 in late 2011, before bulk buyers snapped up many of the area’s distressed homes, helping to drive up prices in Atlanta by more than 25 percent.
“The market is back up,” Baker said. “We think we can make a good amount of profit so we’re going to try.”
For two years, a shortage of sellers like the Bakers has propped up prices across the U.S. as shoppers jostled for a dwindling supply of houses. Now, as the market’s busiest season approaches, escalating values are spurring more listings as homeowners regain equity lost in the worst crash since the 1930s. While new-home construction at a third of its 2006 peak will keep inventory tight, the supply increase is poised to damp price gains while higher mortgage rates cut into demand.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Buy Clean California Act Takes Effect on July 1, 2022
July 25, 2022 —
Garret Murai - California Construction Law BlogThe Buy Clean California Act (BCCA) – Public Contract Code section 3500 et seq. – requires state agencies to consider the carbon content of the following products when awarding contracts:
- Structural steel;
- Concrete reinforcing steel;
- Flat glass; and
- Mineral wool board insulation.
It is anticipated that additional products may be added through future legislation.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com