Want to Stay Up on Your Mechanic’s Lien Deadlines? Write a Letter or Two
March 22, 2017 —
Christopher G. Hill – Construction Law Musings90 days. 150 days. 6 months. 30 days. Do these numbers sound familiar? If you read Construction Law Musings regularly, they should be. These are various deadlines relating to the recording and enforcement of mechanic’s liens in Virginia.
90 days from your last work performed (or from the last date of the last month of work in the correct circumstances) sets the outside limit on when a construction company can record a lien on a construction project. 150 days is the “look back” period for what work’s value can be included in that lien. 6 months is the statute of limitations for the filing of an enforcement suit. Finally, 30 days amount of time after your start of work within which you, as a construction professional, must notify a mechanic’s lien agent of your presence on a residential project. Of course, there are always nuances to these rules that need to be taken into account, preferably with the help of your friendly neighborhood construction attorney, before deciding how to proceed in this very picky and “form over function” area of construction law.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Wendel Rosen’s Construction Practice Group Welcomes Quinlan Tom
January 06, 2016 —
Garret Murai – California Construction Law BlogThere’s been more cheer than usual at Wendel Rosen’s Construction Practice Group this holiday season.
Earlier this month, Quinlan Tom, a construction and business attorney, joined us from McInerney & Dillon, a venerable and well-respected construction boutique firm (we know a lot of folks there) with local roots like us in Oakland, California. We’ve all known Quinlan for a while, so when he decided to join our band of merry legal practitioners, we were quite thrilled.
Being lawyers though, and better at asking than answering questions, we decided to pose a few questions to Quinlan:
Q. So, you’ve just been sworn to tell the truth, the whole truth, and nothing but the truth, under penalty of perjury. So, tell us about your practice.
A. Let me just start with it’s quite an honor to appear in your blog; I’ve been a reader for a while (in secret of course before I got to Wendel Rosen). I’m also excited to join you and the other members of Wendel Rosen’s Construction Practice Group; as you mention, I’ve known each of you professionally for quite some time and respect each of you tremendously.
I started as a construction litigator right out of law school. I completed three years of mechanical engineering at UC Davis and put that on my resume when I was looking for a job after law school. (In addition, my dad retired after 40 years in the trenches as a union electrician). McInerney & Dillon (“M&D”) and a couple of other firms found that interesting and I ended up starting with M&D. I did find that my engineering studies helped with my acclimation to construction disputes. While I never pretend to be an engineer, it has provided me with a foundation of how the construction process works and how the projects are designed. 26 years later, I continue to enjoy counseling my clients in their construction disputes/issues and still find each construction project I am involved with fascinating.
I have tried, arbitrated and litigated cases for 26 years, from the United States District Court to the California Superior Court and the California Office of Administrative Hearings. I have argued cases before the Ninth Circuit Court of Appeals and the California Court of Appeal. I counsel my clients into hopefully making the best business decisions available melding the knowledge I have gleaned from my litigation experience with their financial and personal goals.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Are Contracting Parties Treated the Same When it Comes to Notice Obligations?
June 25, 2019 —
G. Scott Walters - Smith CurrieOverview
Experienced project delivery team members know too well the importance of timely and proper notice during a construction project. Ideally, contractual notice provisions, and any penalties for non-compliance, should apply equally to all of the contracting parties. For example, failure to comply with a notice provision concerning contract changes could bar a party from pursuing claims. And, untimely or improper notice can, likewise, prevent certain defenses to claims.
Nowhere is notice more scrutinized than in the federal government contracting arena. Recently, the United States Court of Federal Claims issued two separate decisions involving the same construction project and the same parties and dealing with two specific aspects of notice in the federal government contracting process. The court’s decisions on the notice issues may, at first, appear to contradict each other or to favor one party over the other. A closer look at these two decisions reveals that notice requirements, in the context of federal government construction contracts, can come in multiple forms and notice is not a “one size fits all” proposition.
Read the court decisionRead the full story...Reprinted courtesy of
G. Scott Walters, Smith CurrieMr. Walters may be contacted at
gswalters@smithcurrie.com
Timely and Properly Assert Affirmative Defenses and Understand Statutory Conditions Precedent
August 05, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case serves as a reminder to TIMELY and PROPERLY assert affirmative defenses and to understand statutory conditions precedent to construction lien claims. Failing to do one or the other could be severely detrimental to the position you want to take in a dispute, whether it is a lien foreclosure dispute, or any other dispute.
In Scherf v. Tom Krips Construction, Inc., 2024 WL 3297592 (Fla. 4th DCA 2024), the president of a construction company and his wife were building a residence. They orally accepted the proposal from the concrete shell contractor and asked for invoices to be submitted to the president’s construction company. No written contract was memorialized. The president and his wife did not pay the concrete shell contractor and the contractor recorded a lien and sued to foreclose on the lien. Years later (the case had been stayed because the president and his wife filed for bankruptcy and the shell contractor had to get leave of the automatic bankruptcy stay to pursue the lien foreclosure), the shell contractor moved for summary judgment. The president and his wife moved for leave to file an amended answer and affirmative defenses. They claimed the oral contract was with the construction company and the shell contractor was required to serve a Notice to Owner under
Florida Statute s. 713.06. Alternatively, they argued that if the oral contract was with the president and his wife, the shell contractor was required to serve a Final Contractor’s Payment Affidavit at least 5 days before filing its lien foreclosure claim, and did not, as required by s. 713.06.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Restrictions On Out-Of-State Real Estate Brokers Being Challenged In Nevada
April 10, 2019 —
Aaron D. Lovaas - Newmeyer & Dillion LLPFor years, the Nevada Real Estate Division (“NRED”) and its sub-entity, the Nevada Real Estate Commission (“NREC”), have been tasked with administering the licensing procedures applicable to real estate professionals in Nevada, as well as enforcement of the regulations governing business practices, advertising, commissions, license maintenance, and a host of other dayto-day parameters within which the profession operates. Within the past five years, however, the NREC has tasked itself with the publicly stated goal of “protecting” Nevada real estate licensees and the commissions they earn from out-of-state real estate professionals seeking to do business in the Silver State. While efforts to preserve local real estate opportunities for local brokers might seem sound, an international brokerage firm is challenging the foundation of that structure. If they win, the outcome could have huge implications on the real estate industry in Nevada. Businesses, here’s a breakdown of the existing structure and what the challenge is all about.
The Existing Regulatory Structure
Through amending their own regulations, the NRED and NREC have created a regulatory structure that:
- Prohibits any non-Nevada licensed real estate broker from representing any seller (Nevada based or non-Nevada based) of any Nevada real estate;
- Prohibits any non-Nevada licensed real estate broker from representing any Nevada resident in the purchase of Nevada real estate; and
- Allows non-Nevada licensed real estate brokers to represent non-Nevada purchasers of Nevada real estate only if the out-of-state broker formally affiliates (and therefore shares commissions with) a resident Nevada-licensed broker.
Read the court decisionRead the full story...Reprinted courtesy of
Aaron D. Lovaas, Newmeyer & Dillion LLPMr. Lovaas may be contacted at
aaron.lovaas@ndlf.com
Pennsylvania’s Supreme Court Limits The Scope Of A Builder’s Implied Warranty Of Habitability
September 10, 2014 —
Edward A. Jaeger, Jr. and William L. Doerler – White and Williams LLPIn Conway v. Cutler Group, Inc., -- A.3d --, 2014 WL 4064261 (Pa.), the Supreme Court of Pennsylvania addressed the question of whether a subsequent home buyer can recover from a home builder pursuant to the builder’s implied warranty of habitability, a warranty that protects those who purchase a newly constructed home from latent defects. Concluding that a builder’s warranty of habitability is grounded in contract, the Court held that a subsequent purchaser of a previously inhabited home cannot recover damages from a builder-vendor based on the builder-vendor’s breach of the implied warranty of habitability. The Court’s decision leaves unanswered the question of whether a purchaser who is also the first user-purchaser of a new home can pursue a breach of warranty action against a builder with whom the purchaser is not in privity of contract.
In Conway, the Cutler Group, Inc. (Cutler) sold a new home to Davey and Holly Fields. The Fields subsequently sold the home to Michael and Deborah Conway. After the Conways discovered water infiltration problems in their home, they filed a one-count complaint against Cutler, alleging that Cutler breached its implied warranty of habitability. In response to the Conways’ complaint, Cutler filed preliminary objections, arguing that the warranty of habitability extends from the builder only to the first purchaser of a newly constructed home. The trial court sustained Cutler’s preliminary objections based on the lack of contractual privity between the parties and the Conways appealed the trial court’s decision. On appeal, the Superior Court reversed, stating that the implied warranty of habitability is based on public policy considerations and exists independently of any representations by the builder, and even in the absence of an express contract between the builder and the purchaser. Cutler appealed the Superior Court’s decision to the Supreme Court.
To address the question of whether the implied warranty of habitability extends to a subsequent purchaser of a used residence, the Court discussed the history of the implied warranty of habitability in Pennsylvania. As stated by the Court, the Court adopted the implied warranty of habitability in the context of new home sales to reject the traditional doctrine of caveat emptor (buyer beware) because the purchaser of a new home justifiably relies on the skill of the developer. Thus, as between the builder-vendor and the buyer, the builder should bear the risk that the home he builds is habitable and functional. In adopting the doctrine, the Court noted that the doctrine is rooted in the existence of a contract – an agreement of sale – between the builder-vendor and the buyer.
Reprinted courtesy of
Edward A. Jaeger, Jr., White and Williams LLP and
William L. Doerler, White and Williams LLP
Mr. Jaeger may be contacted at jaegere@whiteandwilliams.com; Mr. Doerler may be contacted at doerlerw@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Get Away with Default (but don’t count on it)
July 27, 2020 —
Christopher G. Hill - Construction Law MusingsAs an almost universal rule here in Virginia, failing to show up for court or respond to a lawsuit is a bad idea. Consequences include default judgment against you without the right to defend or make your case. Courts simply enter judgment and the consequences of that judgment will follow.
However, and as is often the case around here, there are small exceptions where the courts of Virginia allow the defaulting party off the hook. Sullivan Mechanical Contractors, Inc. v. KBE Building Corporation is just such a case. In Sullivan Mechanical, the Federal District Court for the Western District of Virginia was faced with a Motion to Vacate Default Judgment from KBE. The facts are laid out in the opinion, but basically come down to the usual subcontractor not paid by the general contractor and general contractor has reasons for non-payment. Subcontractor, Sullivan Mechanical, sued KBE and KBE failed to respond in a timely manner. One day after the deadline for response had passed, Sullivan moved for entry of default and the clerk entered the default that same day. KBE moved to vacate the default a mere 6 days after entry of default.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Standard For Evaluating Delay – Directly from An Armed Services Board Of Contract Appeal’s Opinion
October 04, 2021 —
David Adelstein - Florida Construction Legal UpdatesSometimes, it is much better to hear it from the horse’s mouth. That is the case here. The Armed Services Board of Contract Appeal’s (ASBCA) opinion in Appeals of -GSC Construction, Inc., ASBCA No. 59402, 2020 WL 8148687 (ASBCA November 4, 2020) includes an informative discussion of a contractor’s burden when it encounters excusable delay and, of importance, the standard for evaluating delay. It’s a long discussion but one that parties in construction need to know, appreciate, and understand. EVERY WORD IN THIS DISCUSSION MATTERS.
Construction projects get delayed and with a delay comes money because time is money. Many claims are predicated on delay. These can be an owner assessing liquidated damages due to a delayed job or a contractor seeking its costs for delay. Either way, the standard for evaluating delay and the burdens imposed on a party cannot be understated and, certainly, cannot be overlooked. For this reason, here is the discussion on evaluating delay directly from the horse’s mouth in the Appeal of-GSC Construction, Inc.:
The critical path is the longest path in the schedule on which any delay or disruption would cause a day-for-day delay to the project itself; those activities must be performed as they are scheduled and timely in order for the project to finish on time. Wilner v. United States, 23 Cl. Ct. 241, 245 (1991). In Yates-Desbuild Joint Venture, CBCA No. 3350 et al., 17-1 BCA ¶ 36,870, our sister board compiled an excellent and very helpful synopsis of the standards for evaluating delay claims, which I adopt nearly verbatim among the discussion that follows.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com