Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
What are Section 8(f) Agreements?
July 02, 2018 —
Wally Zimolong – Supplemental Conditions Like many areas of federal labor law, there are different rules for construction industry employers. One major difference is in how employers become unionized. Typically, under Section 9(a) of the National Labor Relations Act, a union becomes a collective bargaining agent of employees only after a majority of employees show support for union representation. In other words, the employees chose whether to be represented by a particular union. However, under Section 8(f) of the NLRA, construction industry employers can choose to become union without any showing of majority support by employees. In fact, construction industry employers don’t need to have any employees at all to sign a “8(f) agreement.” Thus, these agreements have become known as pre-hire agreements.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Approaches to Managing Job Site Inventory
January 04, 2018 —
Jessica Stark - Construction InformerOriginally Published by CDJ on August 30, 2017
There is no question that organization on the job site can mean the difference between efficient performance and costly errors. A simple mistake can cost a company thousands, which is why details are carefully articulated and supervisors become better scrutinizers than magazine editors. But for some reason, many companies don’t consider managing job site inventory under this same attentive category, or perhaps they don’t know about the technology available to help them do it.
For contractors, keeping track of every piece of material and equipment lowers losses and keeps crews busy. This is especially true for contractors in the trades who often have specialized equipment in inventory such as power supplies, HVAC “smart energy” components or inspection equipment. Once everything is accounted for, the possibility of loss is decreased and there’s a chance to evaluate the use of all materials and equipment. This can show the efficiency of allotted resources. Is there enough equipment on the site to get tasks completed? Is there a need for more? Less? Having excess equipment can sometimes prepare a crew for problem scenarios. But it can also mean the construction company is overpaying for unneeded resources. However, the only way to know is by effectively managing job site inventory. That includes all equipment and materials
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Stark, Construction Informer
All Risk Policy Only Covers Repair to Portion of Dock That Sustains Damage
January 06, 2012 —
Tred R. Eyerly - Insurance Law HawaiiA portion of a dock on Lack Michigan operated by the Ports of Indiana suffered visible damage. See Ports of Indiana v. Lexington Ins. Co., 2011 U.S. Dist. LEXIS 130979 (S.D. Ind. Nov. 14, 2011). Lexington Insurance Company insured the port. Lexington agreed that a portion of the dock was damaged and paid $1.2 million for repairs. A dispute arose, however, over whether additional sections of the dock were damaged and whether the damage was the result of more than one "occurrence."
An expert report opined that a significant drop creating record lows in the water level of Lake Michigan in 2007 caused damage to the dock. Lexington maintained that only 128 feet of the dock was damaged; other portions of the dock did not sustain "direct physical loss or damage."
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
FBI Makes Arrest Related to Saipan Casino Construction
April 05, 2017 —
Matthew Campbell & Greg Farrell - BloombergThe Federal Bureau of Investigation arrested one person in connection with the death of a construction worker at Imperial Pacific International Holdings Ltd.’s casino on the remote U.S. island of Saipan, according to an agency spokeswoman.
“The FBI conducted a search and made an arrest in response to the recent death of an individual working at the construction site of the Imperial Pacific Resort,” Michele Ernst, a spokeswoman in the FBI’s Honolulu field office, said in an email Friday. “The investigation is related to allegations of a federal violation of the workplace visa system, including reports the company was systematically harboring individuals who are out of status and in violation of federal statutes."
Reprinted courtesy of
Matthew Campbell, Bloomberg and
Greg Farrell, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Todd Seelman Recognized as Fellow of Wisconsin Law Foundation
February 15, 2021 —
Todd Seelman - Lewis Brisbois NewsroomDenver Managing Partner Todd R. Seelman has been recognized as a Fellow of the Wisconsin Law Foundation, joining a select group of attorneys who comprise no more than 2.5% of the entire membership of the Wisconsin Bar. Mr. Seelman's membership in the Fellows organization represents that his peers have recognized him for his outstanding professional achievements and devotion to the welfare of his community, state, and country, as well as the advancement of the legal profession.
“I am grateful for this honor and opportunity to become a member of an exceptional group of lawyers," Mr. Seelman said. "I look forward to working to advance the Fellows’ important goals, including promoting justice and improving legal education.
The Fellows organization was created to honor members of the Wisconsin Bar who have achieved significant professional accomplishments and contributed leadership and service to their communities.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Seelman, Lewis BrisboisMr. Seelman may be contacted at
Todd.Seelman@lewisbrisbois.com
Home Prices Beat Estimates With 0.8% Gain in November
January 28, 2015 —
Prashant Gopal – Bloomberg(Bloomberg) -- U.S. home prices rose more than economists estimated in November, a sign job growth is helping to boost housing demand.
Prices climbed 0.8 percent on a seasonally adjusted basis from October, the Federal Housing Finance Agency said in a report from Washington. The average economist estimate was for a 0.3 percent increase, according to data compiled by Bloomberg. Prices increased 5.3 percent from November 2013.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Case-Shiller Redo Shows Less Severe U.S. Home-Price Slump
September 03, 2014 —
Lorraine Woellert – BloombergThe collapse in U.S. home prices that stoked the worst recession since the Great Depression wasn’t quite as severe as initially estimated, according to data from S&P/Case-Shiller.
Property values nationally fell 26 percent from the February 2007 peak to the December 2011 trough, not 34 percent as previously reported, revised data showed last week. The index will now be issued monthly rather than quarterly.
The change is the result of CoreLogic Inc. (CLGX)’s $6 million purchase of the S&P/Case-Shiller index from technology company Fiserv Inc. in March 2013. Case-Shiller has spent more than a year retrofitting its model with CoreLogic’s bigger, higher-quality data set, leading to a change in how the index looks.
Read the court decisionRead the full story...Reprinted courtesy of
Lorraine Woellert, BloombergMs. Woellert may be contacted at
lwoellert@bloomberg.net