Appeals Court Upholds Decision by Referee in Trial Court for Antagan v Shea Homes
May 10, 2012 —
CDJ STAFFIn the case Antangan v. Shea Homes Ltd. Partnership (Cal. App., 2012), Plaintiffs appealed “an order vacating a judgment and entering a modified judgment in their construction defect action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership,” while the Defendant, Shea Homes Limited Partnership (Shea Homes) appealed “an order of the judicial referee denying its motion to strike and tax costs.”
On the Antagon issue, the appeals court concluded that “the trial court did not err by vacating and modifying its judgment so that the cost of referee’s fees would be equally divided by the parties and consistent with a prior stipulation they filed in court.”
On the Shea Homes issue, the appeals court concluded: “1) the judicial referee did not err by ruling that plaintiffs’ offers to compromise (§ 998) were validly served on Shea Homes’ counsel, 2) the offers substantially complied with statutory requirements, 3) the offers were not required to be apportioned, and 4) the referee’s award of $5,000 as costs for a person assisting plaintiffs’ counsel was not an abuse of discretion.” The appeals court affirmed the judgment.
Here is a brief history of the trial case: “Plaintiffs Chito Antangan, Jimmy Alcova and other homeowners brought an action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership for damages alleging that the properties they purchased from these ‘developer defendants’ were defective. Plaintiffs claimed numerous construction defects required them ‘to incur expenses’ for ‘restoration and repairs’ and the value of their homes had been diminished.”
In response, Shea Homes filed a motion for an order to appoint a judicial referee. The motion was granted and it was ruled that “a referee would ‘try all issues’ and ‘report a statement of decision to this court.’”
On May 10, 2010 the judicial referee (Thompson) “awarded plaintiffs damages and various costs, and ruled that ‘Shea Homes shall bear all of the Referee’s fees.’” The latter ruling would become a matter for contention later on.
In July of 2010, the plaintiffs “sought, among other things, $54,409.90 for expert fees, and $14,812.50 for the services of Melissa Fox for ‘exhibit preparation & trial presentation.’ Shea Homes filed a motion to strike and/or tax costs claiming: 1) Fox was a paralegal, 2) plaintiffs were not entitled to attorney’s fees, and 3) the fees for Fox’s services were an indirect and improper method to obtain attorney’s fees. The referee disagreed and awarded $5,000 for Fox’s services. The referee also ruled that plaintiffs had properly served valid offers to compromise (§ 998) on Shea Homes’ counsel in 2009. He said those offers to defendants in the case at that time did not have to be apportioned.”
“Antangan contends the trial court erred when it vacated and modified its original judgment, which ordered Shea Homes to pay all the referee’s fees. We disagree.”
Antagon contended that the trial court erred when it vacated and modified its original judgment regarding Shea Homes paying the referee’s fees. The appeals court disagreed: “A trial court has inherent authority to vacate or correct a judgment that is void on its face, incorrect, or entered by mistake. (§ 473; Rochin v. Pat Johnson Manufacturing Co. (1998),67 Cal.App.4th 1228; Olivera
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Florida Continues Enacting Tort Reforms, This Time Shortening the Statute of Repose
May 01, 2023 —
William L. Doerler - The Subrogation StrategistOn April 13, 2023, Florida’s governor, Ron DeSantis, signed into law
SB 360 which, among other things, shortens the statute of repose period for improvements to real property. The law also revises the date on which the statute of limitations period runs for these types of damage claims. Florida’s revision of this law provides further evidence of the state’s tort reform efforts.
The new law went into effect upon signing and includes the following changes:
- Shortens the statute of repose period set forth in Fla. Stat. § 95.11(3)(c) for actions founded on the design, planning or construction of improvements to real estate from ten (10) to seven (7) years. The statute of repose period runs from the earliest (rather than the latest) of the date: a) the authority having jurisdiction issues a temporary certificate of occupancy; b) a certificate of occupancy; c) a certificate of completion; or d) of abandonment of construction if not completed. Of note, the revised repose period eliminates that date of actual possession by the owner as one of the accrual dates.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
The Biggest Change to the Mechanics Lien Law Since 1963
December 08, 2016 —
Wally Zimolong – Supplemental ConditionsThe New Year will bring with it the biggest change to Pennsylvania’s Mechanics Lien Law since the current law was passed in 1963. These changes will impact owner, contractors, and subcontractors equally. However, the biggest benefits will probably be for real estate developers and other project owners.
On December 31, 2016, Pennsylvania will go live with a website known as the State Construction Notices Directory. On that date, owners will have the option of making projects costing $1,500,000 or more “searchable projects.” An owner makes a project a searchable project by filing with the Notices Directory a “Notice of Commencement” before works begins. The Notice of Commencement must include the name, address, and email address of the contractor, full name and location of the searchable project, the county where the project is located, a legal description of the searchable property, and the name address, and email address of the searchable project owner. Importantly, the owner must also post a copy of this Notice of Commencement at the project site.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Some Work Cannot be Included in a Miller Act Claim
June 28, 2021 —
Christopher G. Hill - Construction Law MusingsThe Miller Act is close to my heart here at Construction Law Musings. Payment bond claims under the Miller Act help protect subcontractors on construction projects where the national government or its agencies are the owners of the property and therefore mechanic’s liens are unavailable. Even where you follow the proper claims process under this statute, the question remains as to what sorts of costs can be included in the claim.
A recent case out of the Eastern District of Virginia federal court in Alexandria, VA gives some insight into the limits of claims under the federal Miller Act. In Dickson v Forney Enterprises, Inc. et. al., the Court looked at the question of whether costs of a project manager’s purely clerical duties can be included and correspondingly whether performing those duties can extend the relevant one-year limitations period for filing suit.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Contract Basics: Indemnity
October 30, 2023 —
Christopher G. Hill - Construction Law MusingsI’m back after a welcome
change of offices from a Regus location to a separate and more customer-friendly
local shared office space location. I thought I’d jump back into posting with a series of construction contract-related posts, the first of which relates to indemnification clauses.
An indemnification clause in a contract obligates one party (the Indemnitor) to take on liability (read pay for) any damages to another party (the Indemnitee) under certain circumstances. In a construction context, this type of arrangement can arise in a
bonding context with a general indemnity obligation to the surety among other contexts outside of the four corners of any prime or subcontract. I will not be discussing those other contexts and will focus on the typical indemnity clause found in most if not all, construction contracts. These clauses most often state that the “downstream” party is to indemnify all of the upstream parties for any and all damages incurred by the indemnitees due to any action of the downstream party, its employees, subcontractors, sub-subcontractors, etc. The clauses are often not limited in scope and generally include attorney fee provisions and generally require indemnity for breaches of contract by their terms.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Florida Condo Collapse Shows Town’s Rich, Middle-Class Divide
August 04, 2021 —
The Associated Press (Terry Spencer & Freida Frisaro) - BloombergThe condo tower collapse in Surfside could exacerbate the division that already exists between the tiny Florida town’s new luxury buildings built for the global elite and those constructed decades ago for the middle class. It is already creating headaches for some small businesses.
The town has seen the construction of numerous new condos in recent years, where large oceanfront units exceeding 3,000 square feet (280 square meters) with modern amenities can fetch $10 million and up. Meanwhile, small units of 800 square feet (75 square meters) in neighboring condo buildings constructed decades ago can be had for $400,000.
Ana Bozovic, a South Florida real estate broker, said the June 24 collapse of the 40-year-old, middle-class Champlain Towers South will exacerbate this division. At least 46 people were killed and more than 90 remain missing.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Additional Insured Not Entitled to Indemnity Coverage For Damage Caused by Named Insured
February 23, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe additional insured unsuccessfully sought to recover damages to its building caused by the named insured. Brit UW, Ltd. v. Tripar, Inc., 2017 U.S. Dist. LEXIS 2462 (N.D. Ill. Jan. 6, 2017).
Davis Russell Real Estate and Management LLC hired Tripar, Inc., a general contractor, to renovate a 12-unit apartment building. The entire roof was to be replaced by a roofing subcontractor. Davis Russell drafted a Professional Services Agreement (PSA) that governed the project. Tripar was to obtain a CGL policy and provide a certificate of insurance evidencing the coverage. Davis Russell was to be named as an additional insured.
Tripar's insurance broker prepared a certificate of insurance reflecting that a CGL policy was issued to Tripar by Brit UW, Ltd. But the certificate clearly stated that it was not issued by the insurer and that it did not alter coverage. The certificate of insurance further stated that it conferred no rights upon the holder.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
NJ Court Reaffirms Rule Against Coverage for Faulty Workmanship Claims and Finds Fraud Claims Inherently Intentional
September 20, 2021 —
Anthony L. Miscioscia & Frank J. Perch, III - White and Williams LLPAwarding summary judgment to an insurer under both liability and directors & officers (D&O) coverage parts, a New Jersey trial court reaffirmed the principle that claims of defective workmanship without resulting “property damage” are not covered under a general liability policy, and further dismissed claims for fraud and breach of fiduciary duty, finding that such claims were inherently intentional and do not state a covered “occurrence.”
In Velez v. AR Management Company, et al., 2021 N.J. Super. Unpub. LEXIS 1675 (Law Div. Bergen Co. Aug. 10, 2021), owners of a condominium unit rebuilt after a fire sued the condominium association, several association board members, the association’s property management company and the general contractor for the reconstruction work. The owners’ suit alleged faulty workmanship and incomplete repairs. In addition, the owners asserted fraud and breach of fiduciary duty claims against the management company, alleging conflicts of interest and self-dealing between the management company and the general contractor, which had common ownership.
In a third-party complaint, the management company sought coverage from the condo association’s liability and D&O insurer. The court dismissed the D&O coverage claim, noting that the management company was not a director or officer or otherwise entitled to insured status for the D&O coverage part.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Frank J. Perch, III, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Perch may be contacted at perchf@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of