Arizona Court of Appeals Awards Attorneys’ Fees in Quiet-Title Action
September 20, 2017 —
Kevin Walton - Snell & Wilmer Real Estate Litigation BlogIn Arizona, a party successfully quieting title to property may recover its attorneys’ fees if it satisfies three requirements: (1) the party requests a quitclaim deed from the party adversely claiming title twenty days before bringing the quiet-title action; (2) the party tenders five dollars for the execution and delivery of the deed; and (3) the adverse party fails to comply. Ariz. Rev. Stat. § 12-1103(B). Recently, in McCleary v. Tripodi, No. 2 CA-CV 2016-0145, 2017 WL 3723472 (Ariz. Ct. App. Aug. 29, 2017), the Arizona Court of Appeals awarded attorneys’ fees to the prevailing party under this statute.
In McCleary v. Tripodi, Mrs. Tripodi, who became the administrator of her husband’s estate upon his death, wrongfully recorded three deeds purporting to transfer property to herself. After unsuccessfully attempting to get Mrs. Tripodi to quitclaim the property, the plaintiffs filed a quiet-title action. The trial court agreed that the plaintiffs were the legal and rightful owners, granted summary judgment in plaintiffs’ favor, and awarded attorneys’ fees to the plaintiffs.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin Walton, Snell & Wilmer
Just Because You Allege There Was an Oral Contract Doesn’t Mean You’re Off the Hook for Attorneys’ Fees if you Lose
March 28, 2022 —
Garret Murai - California Construction Law BlogThere’s certain things in life you shouldn’t mix. Like drinking and driving. Bleach and ammonia. Triple dog dares and frozen poles. And angry lawyers and litigation.
In Spahn v. Richards, Case No. A159495 (November 30, 2021), angry lawyer Jeffrey Spahn sued general contractor Dan Richards claiming that Richards orally agreed to build Spahn’s million dollar plus house for $515,000. Not only did Spahn not recover anything from Richards, he ended up owing Richards $239,171 in attorney’s fees and costs, after he denied a request for admission asking that he admit that there was no oral contract.
The Spahn Case
In 2017, Spahn filed suit against Richards for breach of oral contract, breach of implied covenant of good faith and fair dealing, and promissory estoppel. According to Spahn, he met Richards in June 2015 and the two reached an agreement whereby Richards agreed to demolish Spahn’s house for $12,500 and build a new one for $515,000. Further according to Spahn, Richards agreed to this “fixed price” “oral contract” in June 2015, and then, on July 1, 2015, Richards “confirmed and agreed that he would perform the construction project” for $515,000 and would complete construction by May 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Guidance for Construction Leaders: How Is the Americans With Disabilities Act Applied During the Pandemic?
September 28, 2020 —
Molly Gwin - Construction ExecutiveWith the spread of the COVID-19 pandemic, numerous cities and states have mandated infection control practices, including social distancing, mask requirements and sanitization of work areas and tools. As a result, many construction leaders now have questions as to how government guidance related to COVID-19 interacts with the Americans with Disabilities Act (ADA). For example, can a project manager enforce a mask mandate when a construction worker presents a doctor’s excuse noting breathing difficulties? Or, what if the employer is aware that an individual presents a higher risk for severe illness because of an underlying health condition, but that employee does not request an accommodation?
Thankfully, the United States Equal Employment Opportunity Commission (EEOC) recently published guidance relating to these requests that construction leaders can reference. While our goal is to summarize that guidance and provide practical advice for the construction sector, this article does not substitute for situation specific legal counsel.
SCENARIO 1: AN EMPLOYEE REFUSES TO WEAR A MASK AND PRODUCES A DOCTOR’S NOTE CITING BREATHING DIFFICULTIES. MUST THE EMPLOYER ACCOMMODATE SUCH A REQUEST?
Potentially. Since the request to not wear a mask is considered an accommodation under the ADA, the employer can still require a doctor’s note when considering the accommodation.
Reprinted courtesy of
Molly Gwin, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Gwin may be contacted at
mgwin@isaacwiles.com
Homebuilders Offer Hope for U.K. Economy
August 20, 2014 —
Mark Gilbert – BloombergThe two elements of the U.K. economy that the Bank of England currently finds most worrying are the overheating housing market and the paucity of wage growth. Earnings reports this week from two of the nation's biggest homebuilders make for cheery reading on both counts.
Persimmon Plc, the U.K.'s largest homebuilder by market value, said today it completed 6,408 new homes in the first half of the year, a 28 percent increase from the year-earlier period. Bovis Homes Group, which mostly builds what it calls "traditional" family homes in the south of England outside London, said it sold 1,487 new homes in the first six months, a gain of 54 percent.
"The government has told us that we need 230,000 new homes per annum, and far be it for us to disagree with that," Bovis Chief Executive Officer David Ritchie said on a conference call. He expects to build about 3,650 homes this year, and reckons that "5,000 to 6,000 homes per annum is a very sensible target for the business."
Read the court decisionRead the full story...Reprinted courtesy of
Mark Gilbert, BloombergMr. Gilbert may be contacted at
magilbert@bloomberg.net
Contractor Sues Golden Gate Bridge District Over Suicide Net Project
December 18, 2022 —
James Leggate - Engineering News-RecordThe project to install a suicide-deterrence net and perform other upgrades on the Golden Gate Bridge in San Francisco now is expected to complete five years late and cost more than double the original contract price, its contractors say. The joint venture leading the project filed a breach-of-contract complaint against the agency that manages the bridge seeking $195 million in damages, while the agency counters that delays were caused by changes in the contractor’s ownership.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Insurance Client Alert: Mere Mailing of Policy and Renewals Into California is Not Sufficient Basis for Jurisdiction Over Bad Faith Lawsuit
January 28, 2015 —
Valerie A. Moore and Christopher Kendrick – Haight Brown & Bonesteel LLPIn Greenwell v. Auto-Owners Ins. Co. (No. C074546, filed 1/27/15), a California appeals court held that the use of a mailing address to send policies and renewals into California did not support jurisdiction for a California resident's bad faith lawsuit against a Michigan insurer over property coverage for a fire loss to a building in Arkansas.
In Greenwell, the insured was a California resident engaged in real estate investment. He purchased an apartment building in Little Rock, Arkansas. Using the services of an insurance broker in Little Rock, he purchased a package of general liability and commercial property insurance for the building from Auto-Owners Insurance Company, a Michigan insurer not licensed in California. The policy listed the insured's business address in California, the policy was mailed there, and renewed three times via the insured's California address.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com, Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Take-Aways from the 2024 Annual Forum Meeting in New Orleans
May 20, 2024 —
Marissa L. Downs & Brendan Witry - Laurie & Brennan, LLPOver 600 construction lawyers, experts, and consultants met in New Orleans last week for the Forum’s 2024 Annual Meeting where Program Coordinators Brenda Radmacher and Joseph Imperiale together with John Cook and Buck Beltzer put together an insightful program focused on all things construction litigation. Here are our 10 top take-aways from this unique program.
10. Don't underestimate the soft skills that are necessary to effectively represent your clients. There are different ways to measure success when it comes to construction litigation, according to Stephen Dale (WSP USA), Melissa Beutler Withy (Big-D), and Matthew Whipple (Wohlsen Construction). What these (and likely other inside counsel) will look for when retaining outside counsel is the ability to accurately forecast litigation expense and timely communicate case developments. Being able to master these "soft" skills is as important (if not more so) as an attorney's aptitude for trial advocacy. The in-house counsel who hire litigation counsel will be held accountable to deliver results on the investment they are making in legal fees. Outside counsel who cannot manage budgets or avoid surprises in the course of a case will not be successful as litigators.
Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLP and
Brendan Witry, Laurie & Brennan, LLP
Ms. Downs may be contacted at mdowns@lauriebrennan.com
Mr. Witry may be contacted at bwitry@lauriebrennan.com
Read the court decisionRead the full story...Reprinted courtesy of
Oklahoma Finds Policy Can Be Assigned Post-Loss
April 26, 2021 —
Tred R. Eyerly - Insurance Law HawaiiOklahoma joined the majority of court in finding that after a loss occurs, the insured can assign the policy to another. Johnson v. CSAA Gen. Ins. Co., 2020 Okla LEXIS 118 (Okla. Dec. 15, 2020).
Johnson's property was damaged in a storm. She filed a claim with her insurer. She also executed an assignment of her claim in order to repair the property with the execution of assignment to Triple Diamond Construction LLC. An appraiser retained by Triple Diamond determined the storm damage was $36,346.06. The insurer paid only $21,725.36 for the loss.
Johnson and Triple Diamond sued the insurer for breach of contract, seeking $14,620.70, not inclusive of interest, attorneys' fees and costs. The insurer filed a motion to dismiss, or an alternative motion for summary judgment to dismiss Triple Diamond as a party. The insurer argued that both the policy and an Oklahoma statute barred the assignment. The district court granted the insurer's motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com